No Work Package/Task Name Duration (Days) Predecessors

1 Kitchen Heaven Project

2 BUILDING AND CABLING

3 Sign Lease 1

4 Order T1 Connection 45

5 Ethernet Cable Run 2 4

6 Contract With Gomez 2 4

7 Build-Out 120

8 Build-Out Complete 0 7

9 IT HARDWARE

10 Purchase Hardware 14

11 Install and Test Hardware 3 6,10

12 Add Store to Website 1

13 It Tasks Complete 0 12

14 STORE

15 Order Retail Products 15


Hire Retail Products and Stock
16 14
Shelves
17 Train Store Personnel 2 11, 16

18 Grand Opening 2

19 Project Closeout 5 18

20 Project Ends 0 19
Resources Names
t

Jill, Project Manager

Ricardo

Ricardo

Jill, Project Manager

Contractor

Ricardo

Ricardo

Ricardo

Jill, Project Manager

Jill, Project Manager

Jill, Project Manager

Jill, Project Manager

Jill, Project Manager

Project Manager