Annexure D - Detail Scope of Work
Annexure D - Detail Scope of Work
SCOPE OF WORK
NO. DESCRIPTION REMARKS
IDC CONTRACTOR
1 Preparation and Survey Working Area
Mob-demob Man Power, Tools and Temporary
2
Support
3 Drawing dan Manual Document Dokumen Vendor Fender
All permit required for installation (HIRA, JSA, Mine
4
Permit, ect.)
5 Worker Transport and Accommodation
Supply Fender, Extension Piling, Adaptor dan
6
Accessories
Mobilizing All Installation Material from Shore to Jetty
7 Est. distance 750 meter
2
All consumable required for Installation, Test and
8
Commissioning
Dismantling existing UHMW-PE Plate dan Tire
9
Fender
10 Install Extension Piling Pipe
11 Modified Existing Adaptor to Suit New Fender
12 Installation New Adaptor Fender KVF 600X2500
13 Install Fender KVF 600 X 2500
14 Material Painting and Touch up Painting
15 House Keeping
16 Power source from Existing Panel
17 Extension cable from Panel to Contractor Panel
18 Test and Commissioning
19 As-built Drawing
20 Advisor for Install Vendor PT. Kemenangan