Create & Extending Multiple Material Master in SAP MM

If we want to Create & Extending Multiple Material Master in SAP MM. For this
we are using the T-Code: - MMCC. If we have the Same Multiple master data
with only change in Description for this, we have the option of using Create a
single material for reference & by using this reference material we can create a
multiple master record with extending this Material master for multiple plants.
Material Description
SCREW, ALLEN HEAD, M3 x 10 Reference Material (MM01)
SCREW ALLEN HEAD - M3*16 Copied form Reference
SCREW ALLEN HEAD M3 x 20
SCREW, ALLEN HEAD, M3 x 25
ALLEN HEAD BOLT M4X10
SCREW, ALLEN HEAD, M4 x 12
ALLEN BOLT M4 X 16
SCREW, ALLEN HEAD, M4 x 20
SCREW, ALLEN HEAD M4 x 25
SCREW ALLEN HEAD 4 x 30
SCREW ALLEN HEAD M 4 x 40
SCREW ALLEN HEAD M 4 x 60
SCREW, ALLEN HEAD, M5 x 10
SCREW, ALLEN HEAD, M5 x 12
SCREW, ALLEN HEAD -M5 * 16
SCREW, ALLEN HEAD, M5 x 20
SCREW, ALLEN HEAD, M5 x 25
SCREW, ALLEN HEAD, M5 x 30
ALLEN SCREW M5 x 40
ALLEN SCREW M5 x 45
SCREW ALLEN HEAD M5 x 50
ALLEN SCREW M5X70
SCREW ALLEN HEAD M6 x 16
SCREW,ALLEN HEAD M6 x 20
SCREW, ALLEN HEAD, M6 x 25
ALLEN HEAD BOLT M6 x 35
SCREW, ALLEN HEAD, M6 x 40
ALLEN SCREW M6x45 FULL THREAD
SCREW, ALLEN HEAD, M6 x 50
ALLEN SCREW M6x55 FULL THREAD
SCREW ALLEN HEAD, M6 x 75 HALF THREAD
ALLEN BOLT 8 x 10
SCREW ALLEN HEAD M8 x 20
SCREW, ALLEN HEAD, M8 x 25
SCREW ALLEN HEAD M8 x 30
SCREW, ALLEN HEAD, M8 x 40
SCREW, ALLEN HEAD, M8 x 50-FULL THREAD
SCREW, ALLEN HEAD, M8 x 60
SCREW, ALLEN HEAD, M8 x 70
SCREW ALLEN HEAD M8 x 80
SCREW, ALLEN HEAD, M10 x 16
SCREW, ALLEN HEAD, M10 x 25
ALLEN HEAD BOLT M10 X 30
SCREW, ALLEN HEAD, M10 x 35
SCREW, ALLEN HEAD, M10 x 50-FULL THRD.
SCREW, ALLEN HEAD 12X30
SCREW, ALLEN HEAD, M12 x 45
SCREW, ALLEN HEAD, M12 x 50-FULL THRD.
SCREW ALLEN HEAD 12x55
SCREW ALLEN HEAD 12x60
SCREW ALLEN HEAD 12x65

Step by Step process of creation of Multiple Material Master Creation

Step: - 1
➔First step is Create a Reference Material Master by using T-
Code: - MM01
➔ As above shown here I have created Reference Material with
description SCREW, ALLEN HEAD, M3 x 10
➔ Material 22965 created

Step: - 2
➔ As above we have created one Reference Material.
➔ With the reference of this Master data we can create other remaining
Material Master data.
➔For the Multiple Master Data Creation we can use T-Code:-
MMCC
➔ Enter the T-Code in command bar. Below screen opens.

➔ Enter here Reference Material number which is Just created.


➔ Enter the Number of New Material i.e. just enter the count of material
which are creating with the reference material. E.g. 50,100 etc. as per
requirement.
➔ Enter the data & Execute. Below screen opens.

➔ In this screen just copy the description of material in short text by


selecting column. As shown below.
➔ After copying the description of data. Click on Plant.
➔ As shown above we can Add multiple plant here.
➔ Ten click on Storage Location.

➔ Here Add store location for specific plant as above shown.


➔ Then next Click on Valuation Areas.

➔ Enter the valuation of Plant here as shown above.


➔ Then Click on SAVE.

Step: - 3
➔Check the List of Material by using T-Code: - MM60
➔Enter the T-Code in command bar. Below screen opens.
➔ Enter here Plant & Material type as shown above & Execute.

➔ System will show you all list of material just we have created.
➔ For second Plant Also all material is created as per we are extending this
material from another Plant as above.
➔ This is how we are Create & Extend Multiple Master Data by using
MMCC T-Code.