You are on page 1of 8

Proceedings of the ASME 2017 India Oil and Gas Pipeline Conference

IOGPC2017
April 20-22, 2017, Mumbai, India

IOGPC2017-2448

Offshore Oil and Gas Pipeline – Flow Assurance and Corrosion Modelling for
Inspection Prioritization

Lewis Barton Ian Laing


ROSEN Group ROSEN Group
Newcastle, UK Newcastle, UK

Ramesh Ladwa
Ashwin Pinto
ROSEN Group
ROSEN Group
Stans, CH
Newcastle, UK

ABSTRACT consequent inspection requirements in order to limit excavation


Flow modelling and corrosion risk assessment are used to activities and provide cost-effective solutions to the client.
study a challenging multiphase pipeline, where the main focus
is the identification and prioritization of critical locations for INTRODUCTION
direct inspection (DA). Through the internal corrosion direct It is now well-established that corrosion contributes to the
assessment (ICDA), flow modelling sensitivity studies is carried overall cost of operation of any industrial assets. For instance, it
out to identify critical locations with risks of high shear stresses is estimated that the direct annual cost of corrosion in the USA
and water holdup. Through corrosion risk assessment (CRA), is approximately 276 billion USD [1]. Corrosion remains a
the critical locations were narrowed down to four primary dominant causal factor that compromises reliability and safety
locations, which through direct inspection could provide the [2,3]; e.g. between 1990 and 2013, in the province of Alberta
information necessary to estimate the overall pipeline condition. (Canada), up to 64 % of incidents that resulted in pipeline
It is highlighted that without the In-line inspection (ILI) data, failures, were associated with either internal or external
selection of inspection locations becomes problematic. corrosion [4].
However, carrying out a CRA in combination with dynamic Overall, demonstrating the integrity of assets requires both
flow modelling can build a more representative analysis and the development and effective implementation of a corrosion
assist with effective engineering decision making. management system (CMS). In the United Kingdom, the key
One of the available industry standard tools that can assist instruments which manage operational integrity and safety of
with demonstration of pipelines’ integrity requirement is an pipeline assets, include Pressure Systems Safety Regulations
approach that integrates flow assurance with corrosion 2000 and Pipeline Safety Regulations 1996 (PSR) documents.
modelling known as Internal Corrosion Direct Assessment The UK PSR were instigated as a result of the Piper Alpha [ 5]
(ICDA). More specifically, an industry standard multiphase disaster, implementing a goal setting approach to ensure that
dynamic flow model (OLGA) with well-established corrosion operators are operating pipelines safely and effectively while
models, CRA and engineering judgement have been employed associated risks and consequences are controlled and kept as
to identify and prioritize inspection locations. low as reasonably practical. As a demonstration, one of the
A benefit of this work is the validation of predictions by main statements covering maintenance is reflected in Clause 13
both OLGA and the corrosion engineer in close adoption to the (Maintenance): “The operator shall ensure that a pipeline is
procedures of the NACE ICDA standard practice. maintained in an efficient state, in efficient working order and
Considerations from corrosion engineering aspect on modelling in good repair.”
requirements and corrosion diagnosis will be presented, where In response to the above and overall pipeline integrity
the primary focus is on identification of hot spots and management requirements, we stress on the importance of

1 Copyright © 2017 ASME

Downloaded From: http://proceedings.asmedigitalcollection.asme.org/ on 08/15/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use


adopting a holistic approach [6,7], whilst upholding that even combination with flow modelling to identify critical locations
with a well-established CMS, it is the implementation and within a pipeline where internal corrosion will occur. These
correct application of processes and “tools” that is critical to its critical locations are then subjected to direct inspection and the
success. It is this aspect that is often misunderstood, especially overall condition of the pipeline is inferred from these results.
in the current economic climate (dominated by low oil prices), The ICDA process comprises the following four stages;
where the cost of preventative measures is too often seen as Stage 1 – Pre-Assessment – Data gathering and analysis.
excessive, and corrosion management reverts to a “firefighting” Stage 2 – Indirect Assessment – Flow modelling and CRA.
approach. In our experience, we emphasize the importance of Stage 3 – Direct Inspection.
the four main tools that make up and effective CMS control: Stage 4 – Post-Assessment – Review of process success.
Each of these stages has a crucial part in the overall ICDA
Corrosion Risk Assessments (CRA) process and an ineffective assessment in any one of them will
Pipeline Risk Assessments (PRA) only have a detrimental effect of the overall assessment.
In-line Inspection (ILI) and The process and improvement of ICDA has been discussed
Corrosion Control Strategy (CCS) in numerous papers over the past decade
[18,19,20,21,22,23,24,25,26]; however, the validation of ICDA
As already discussed elsewhere [7], the principal objective predictions is not. The simple reason for this being, if a pipeline
of CRA and PRA studies is to encourage a balanced approach to can be subjected to ILI then there is no need to perform ICDA.
risk management, by ensuring that inspection and monitoring Likewise if the pipeline is subject to ICDA, there is no need for
resources are aligned with (and sufficient) in light of the ILI. It is because of this the overall validation if the ICDA
identified risks. As part of the integrity review process, these process is limited to results with a small inspection area,
risk assessments then drive future monitoring and inspection compared to the overall pipeline.
strategies, and outputs can be used to validate CRAs and In the current work, through a case study, we outline our
ultimately help to optimize the CCS [7], which defines the approach to combine flow modelling and corrosion risk
overall strategy for corrosion management. assessment into a synergistic methodology to identify and
As part of an effective CMS, it is now also widely accepted prioritize critical locations for direct inspection of a challenging
that operational pigging is a key maintenance activity for multiphase pipeline.
controlling or monitoring, internal corrosion of pipelines
[8,9,10]. An effective operational pigging strategy, when EFFECT OF FLUID DYNAMICS ON CORROSION
deployed as part of an overall CMS can result in significant The relationship between flow and corrosion has been
reductions in operating costs, by maintaining integrity and widely discussed and researched [27,28]. It is generally
pipeline operation to its optimum. This is especially true in the considered that flow, in particular turbulent and slugging, leads
prevention of water hold-up. Through the elimination of the key to the breakdown of the protective films and/or scales on the
elements required for corrosion to occur; corrosion rates can be pipe wall, exposing the metal beneath to corrosion attack
lowered and in the process, increase pipeline throughput. The [29,30,31]. The formation of these protective layers can be
additional benefit can also be considered as the reduction of related to CCS activities, e.g. corrosion inhibitor injection; or as
stress on topsides processing facilities, especially in the a result of the natural corrosion process, e.g. formation of iron-
presence of slugs. based oxides or carbonates [32]. In the case of iron carbonates
Evidently, if regular operational pigging or an ILI cannot (siderite, FeCO3), this relatively common scale found in CO2
be conducted, it is under these circumstances that flow containing environments is known to provide sufficient
assurance and modelling would play a vital role in providing protection against corrosion, under the right environmental
input for engineering decisions. Especially in challenging, and conditions [33,34]. However, physical damage to the formed
even in readily piggable pipelines, this need for flow assurance protective layers can lead to rapid localized corrosion [35]. It
is becoming ever more recognized [11,12]. For instance, there must be commented that there is an ongoing (and mixed) debate
are now a number of studies which show relevance of flow regarding the removal of FeCO3 scales (or corrosion products,
modelling in predicting internal corrosion [13] and optimization in general), induced by shear stresses related to multiphase
of corrosion management [14] of multiphase pipelines. flow. For instance, it appears [36] that shear stresses required
Standardized approaches have already been developed for for removal of protective scales far exceed what is considered
Internal Corrosion Direct Assessment (ICDA) [15,16,17] of gas as realistic in terms of flow behavior, whilst it is also claimed
and liquid petroleum pipelines; however, ICDA for multiphase [37] that isolated “freak” shear stress episodes (especially
fluids is still under development. during slugging) can occur and lead to scales removal. As a
developed result, there is not a definitive evidence to confirm or deny the
removal of corrosion scales or products as a consequence of
INTERNAL CORROSION DIRECT ASSESSMENT flow; however, corrosion inhibitor films can be highly sensitive
The ICDA process in summary uses all inputs, assumptions, to flow regimes. Slug flow is known to reduce the effectiveness
and results of a Corrosion Risk Assessment (CRA) in of corrosion inhibitors as shear stresses above 20 Pa are

2 Copyright © 2017 ASME

Downloaded From: http://proceedings.asmedigitalcollection.asme.org/ on 08/15/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use


sufficient to remove films once formed [38]. Therefore, under corrosion, a chemical treatment regime, based on dosing of wax
most turbulent flow conditions, the removal of corrosion suppressants and corrosion inhibitors was used, but their
inhibitor films can and will occur, if consistent replenishment is availability was considered insufficient.
not achieved [39]. It was understood that CO2 corrosion rates, estimated using
It needs to be stressed that although shear stresses assist in NORSOK M-506 corrosion model, were in excess of
providing the conditions necessary for corrosion to occur, 1 mm/year, which raised concerns over the potential condition
without an electrolyte, corrosion would not ensue [32]. As is the of the pipeline.
case in most production pipelines, it is the free water entrained
Technical Background
within the fluids that provides not only the electrolyte, but also
The assessment methodology consisted of the three
carry and replenish corrosive and/or electrochemically active
following steps:
species, e.g. CO2, H2S, Cl- etc., necessary to drive the
(i) Data acquisition and analysis,
corrosion process [40]. In addition to shear stresses, inhibitor
(ii) Pipeline flow modelling (simulation), and
efficiency is reduced in stagnant or low flow velocity conditions
(iii) Corrosion risk assessment.
[41]. As a result, identification of locations susceptible to water
Sections below outline our overall approach to ICDA of
hold-up or water wetting is critical in corrosion assessments
multiphase pipelines. It should be noted that currently, there is
[42].
no standardized approach to ICDA that is applicable to
Flow modelling using a rigorous dynamic multiphase
multiphase pipelines; however, the general process structure can
simulator simplifies the ICDA process by rigorously calculating
be deferred from the approach adopted in gas pipelines ICDA
the thermo-hydraulic behavior within each segment of the
methodologies.
pipeline based on the pipeline design and bathymetry and
process parameters such as flow, pressures, temperatures and Data Acquisition and Analysis
compositions. Such simulators provide useful information such The first step is to evaluate the historical data available and
as the phase velocities, flow regime, water holdups, shear perform a gap analysis. As is the case in many situations, the
stresses, water wetting, condensation rates etc. within the data available, is not always sufficient, and thus suitable
pipeline which helps in a qualitative and quantitative ranking of assumptions must be made which are generally on the
corrosion risks. conservative side. Once the data was analyzed and assumptions
finalized, a number of sensitivity studies were considered such
CASE STUDY that the flow modeling scenarios consider the pipeline
The case study presents a pipeline ICDA analysis, where operational envelope, ensuring the worst case scenario with
the main objective is to identity corrosion hotspots, and respect to pipeline integrity is analyzed.
locations for inspection on a challenging subsea multiphase Flow Modelling
pipeline. Considering that only design fluid composition data was
The assessed pipeline was at the end of its design life (a life made available, and was not detailed enough, it was decided
extension study was thus required), and exhibited potentially that the “black-oil” model would be employed for flow
high CO2 corrosion rates; but could not be subject to ILI and modelling. It was recognized that although the “black-oil”
operational pigging. Therefore, flow modelling and corrosion model does not represent the exact fluid properties, it does
assessments were considered as relevant tools to identify high provide a good estimate as to the fluid behavior characteristics
risk areas and then conduct direct assessment (ultrasonic in the absence of full fluid analysis. In summary, the “black-oil”
testing, UT) in those locations to infer the internal pipeline model, expresses oil as a liquid phase containing dissolved gas
condition. In order to inspect the pipeline it was determined that from the oil reservoir. The model accounts for the gas that
subsea excavation activities would have to be conducted. “bubbles off” from the oil solution and predicts fluid properties
Considering the extent of inspection effort required, it was vital from the density of the gas, the oil, and the volume ratio of
to keep the number of locations to a minimum; yet still be produced gas to liquid. Empirical correlations evaluate the
concise enough for the assessment to identify representative phase split and physical properties of both elements in order to
critical locations within the pipeline. determine the properties of each phase [43].
Technical Background Flow modelling (simulations) was performed using a
Beyond what was considered at the pipeline design stage, dynamic multiphase flow simulator (OLGA®) with the
very little information on the fluid composition was available. following details:
A historical CRA and operational measurements indicated
an increased risk of CO2 corrosion, mainly due to high water (i) Three-phase flash calculations enabled
cuts (up to 90 %vol.) and the CO2 content above 1.5 mol.%. (ii) Pipeline profile input from as-laid pipeline bathymetry,
Formation of wax and its precipitation was known to occur; Provision in the model was made for a riser that
however, the exact locations and extent were unknown. In order extended 50 m above LAT (lowest astronomical tide)
to minimize the occurrence of wax deposits and control internal and for a further 50 m on the platform.

3 Copyright © 2017 ASME

Downloaded From: http://proceedings.asmedigitalcollection.asme.org/ on 08/15/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use


(iii) Rigorous discretization of pipeline segments (limited Results and Discussion
to >20m and <100m in length) The data analysis showed that operational pressure
(iv) Accurate input of pipe wall, insulation layers and remained consistent during production, as well as the pressure
discretization, ambient medium (air exposed, buried/ drop between the inlet and outlet monitoring points. This
trenched, river crossing etc.) and ambient temperature consistency was also mirrored in the temperature measurements,
for accurate heat transfer calculations. at both the inlet and the outlet. It then became clear that the
(v) OLGAS 3-Phase mechanistic model which is pipeline operated under four distinct flow conditions, since its
applicable for all inclination angles, pipe diameters commissioning, i.e.:
and fluid properties is employed. OLGAS considers
four flow regimes: stratified, annular, slug and (i) Initial well operation – period of high and variable
dispersed bubble flow; and uses a unique minimum flow, associated with a high Oil-Gas to Water ratio.
slip criteria to predict flow regime transitions. (ii) Start of well stabilization – period of relatively
(vi) Integrated corrosion calculations are enabled. consistent flow, associated with a high Oil-Gas to
Water ratio.
A full schematic of the pipeline model incorporating the (iii) Stable well operation – period of consistent flow with
elevation profile can be seen in Figure 2. a steadily increasing water cut; well operation
suspended (shut-down) after this period.
Determination of Boundary Conditions
(iv) Re-start of well operations – period of unsettled flow
In order to account for different operational conditions,
with a variable water cut.
determination of representative operational parameters was
essential in the selection of sensitivity studies. More Within each of these four flow conditions, there were a number
specifically, the following parameters were considered: (i) flow of sensitivity studies considered; these were dictated by the oil,
rate, (ii) fluid temperature, (iii) pipeline pressure and (iv) fluid water and gas production volumes. These sensitivity studies
composition. were based on the different operational parameters monitored
The flow regimes and wall shear stresses for selected during each flow condition. A total of thirteen sensitivity studies
scenarios (sensitivity studies) were predicted from the model, were considered, with one of these representing a typical
which would be representative of the flow conditions reported operational condition prior to the shut-down period. Any water
for the pipeline, since its commissioning date. Both factors holdup locations identified under this specific sensitivity study
together, i.e. the shear stress and water hold-up, were used to would be considered representative of where free water would
determine locations with the highest risk of corrosion; as a exist upon cessation of flow.
direct result of the presence of free water and the likelihood of Figure 3 shows the distribution of the time-averaged wall
inhibitor or corrosion scale stripping. shear stresses (generated by the conveyed fluids) along the
Corrosion Modelling and Risk Assessment pipeline. In general, the estimated values fluctuated around
The high risk areas identified through corrosion and flow 1 Pa, but were also observed to exceed 20 Pa in some locations.
modelling were subject to a corrosion risk assessment. However, the viscosity of the fluids calculated by the “black
Corrosion modelling was based on the NORSOK M-506 CO2 oil” model was approximately 60% less than defined in the
corrosion model [44], with the following input parameters: (i) design documents. The lower viscosity was ultimately used in
temperature and pressure values at the critical locations as the modelling; hence, the actual wall shear stresses will vary
estimated thorough flow modelling, based on the inlet and from those predicted.
outlet measurement from operational data, (ii) wall shear stress Figure 4 shows the distribution of the time-averaged water
values at the critical locations, (iii) gas CO2 concentration hold-up along the pipeline length. For most cases the water
measured at the platform separator and (iv) pH value for hold-up was predicted to be in the range of 25 to 50 % vol. At
formation water estimated using NORSOK M-506 CO2 some low point sections of the pipeline, up to 60 % vol. water
corrosion model. pooling was identified.
Each of the corrosion rates were considered against the Slugging was predicted to occur for all of the cases
realization of corrosion at each location and ranked in terms of considered, except for cases where the gas to oil ratio was low.
criticality for inspection. The number of critical locations can As these results were time averaged, they represent the most
vary depending on the specific characteristics of each site; probable locations and the most frequently occurring wall shear
however, having a location scatter helps to provide extra stresses. Although, during individual slugging events, actual
confidence as to the total pipeline condition as opposed to a water holdup and wall shear stresses are likely to be higher, the
small segment. Although the benefit of inspecting scattered locations at which these events occur are expected to remain the
locations must also be considered against the likely benefit in same and would only present a difference in magnitude.
relation to the additional cost. This was confirmed on completion of the review of all
model outputs; all of the sensitivity studies showed that water
hold-up and maximum shear stresses occurred at the same

4 Copyright © 2017 ASME

Downloaded From: http://proceedings.asmedigitalcollection.asme.org/ on 08/15/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use


respective locations. The locations which were identified as Corrosion Rate Predictions
critical, where high shear stresses and water holdup were most The uninhibited corrosion rates ranged from 2.1 to 0.96
likely, were not necessarily only those associated with low mm/year, depending on the critical location. However, based on
points, but also declining and transitioning straight sections our experience in modelling corrosion rates, it is very likely that
where turbulent flow was identified. These locations were the estimated corrosion rates would decrease by one order of
labelled A to M and are discussed in further detail below. magnitude under correct inhibiting conditions, e.g. 90%
corrosion inhibitor efficiency. As expected, the highest CO2
Critical Location Identification
corrosion rates were observed at the inlet section of the
The identified locations showed a clear grouping along the
pipeline, and gradually decreasing towards the pipeline outlet.
entire pipeline.
Although, it is known that the NORSOK M-506 CO2 corrosion
Locations A to D model tends to provide conservative estimates [47], the
These critical locations represent approximately the first corrosion rates at these locations should therefore be considered
third of the pipeline length, i.e. the inlet section, and showed the generic estimates rather than actual corrosion rates.
highest levels of flow turbulence and water hold-up. The flow
Inspection Location Prioritization
modelling results showed the highest shear stresses, indicating a Based on the magnitude of corrosion risk at the identified
high risk of corrosion inhibitor films stripping, removal of critical locations, A to M, four primary locations for inspection
already existing corrosion scales and/or disruption of their were selected and justifications for ranking are summarised as
formation. Additionally, it is very likely that the corrosivity of follows:
the fluid in this segment will be higher due to the combined
effects of higher pressure and temperature. It is possible that Location A
water wetting will occur over the full pipe circumference, Characterised by a low point, approximately 20 m
considering high water cuts in the conveyed fluids; this is now downstream of the pipeline inlet. Presence of high shear stresses
considered typical for water cuts higher than 10 % vol. [45]. and high turbulence, with full circumferential water wetting of
This in combination with corrosion inhibitor film stripping and the pipe wall. The location is also dominated by the availability
corrosion scale disruption would likely enhance internal of corrosive species and free water holdup.
corrosion in this section of the pipeline.
Location C
Locations E to J Associated with steep decline, approximately 1 km
Six critical locations were identified for the middle section downstream of the pipeline inlet. The area was also found to be
of the pipeline and found at a lower risk of corrosion, when associated with high shear stresses, turbulent flow (due to steep
compared to those at the inlet. This is primarily due to lower decline) and the availability of corrosive species.
temperature and pressure values, and at this point the conveyed
Location K
fluids would start to become saturated with corrosion products.
Located at the base of decline, approximately 2 km
The results from the modelling also suggest that the wax
upstream of the pipeline outlet. There was a combination of
appearance temperature will be met, which means that there
high shear stress and water holdup within this location.
would be an increased risk of wax precipitation and deposition
on the pipeline wall [46], and thus limited wetting. Flow within Location N
this section was predicted to be less turbulent, as the fluid and Associated with the base of the riser. It was identified that
gas phases began to stratify, aided by the relatively flat pipeline there were a high probability for slugging creating high
profile. As a result, the lowest shear stresses were estimated for turbulence resulting in high shear stresses. It was confirmed that
these locations. Consequently, corrosion is more likely to occur the area was susceptible to water hold-up.
at the bottom of the pipeline as a separate water phase develops Conclusions
and accumulates. In this specific case study, we identified four operational
Locations K to M flow conditions. Using temperature, pressure, water cut and the
The final critical locations are found toward the end of the oil to gas ratio as variables we conducted flow modelling of 13
pipeline where the conveyed fluids show the lowest corrosivity. sensitivity studies and identified 13 critical locations with the
It is our view that this is due to the fluids becoming saturated potential for high shear stresses and water holdup. Through
with corrosion products and the effects of lower temperature corrosion risk assessment we narrowed down the critical
and pressures. However, these locations were found to show locations to four primary locations, which through direct
some of the highest values of wall shear stresses, which was due inspection could provide the client with the information
to the fluctuation in fluids velocity, exacerbating the effects of necessary to estimate the overall condition of the pipeline.
slugging at low points and the pressure head of the riser
pipework. Although the fluids are less corrosive, these locations A series of general observations on similar case studies
pose the highest water hold up, especially at the base of the have identified aspects for review in the overall approach to the
riser. pipeline integrity plan:

5 Copyright © 2017 ASME

Downloaded From: http://proceedings.asmedigitalcollection.asme.org/ on 08/15/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use


Locations identified by indirect inspection can show a very
good correlation with the ILI inspection results and where REFERENCES
anomalies exist, these need to be explained.
[1] International Measures of Prevention, Application, and
The identified corrosion hotspot locations from the indirect Economics of Corrosion Technologies Study, Report No.
inspection stages can correlate well to the actual corrosion OAPUS310GKOCH (PP110272)-1, DNV GL USA, Houston,
clusters. However, engineering experience and the OLGA TX (2016)
multiphase model strongly suggests that corrosion can occur at [2] M.B. Kermani, D. Harrop, The impact of Corrosion on the Oil
certain locations due to the presence of water accumulation, and Gas Industry, SPE Production and Facilities, 11(3), 186
high shear stresses and slugging. The fact that no corrosion may (1996).
be found would indicate either a problem with the indirect [3] P.R. Roberge, Corrosion Inspection and Monitoring, John
inspection or direct inspection results. As the indirect inspection Wiley & Sons, Inc., Hoboken, NJ (2007).
could correctly identify the majority of critical corrosion [4] Alberta Energy Regulator, Report 2013-B: Pipeline
locations to a <1% degree of accuracy, it is unlikely this is the Performance in Alberta 1990-2012 (2013).
cause of the lack of correlation. In order to identify the possible [5] B. Singh, P. Jukes, B. Wittkower, B. Poblete, “Offshore
cause for this, a further review of the ILI inspection report and Integrity Management 20 Years on – Overview of Lessons
results would be recommended. Learnt post Piper Alpha”, Offshore Technology Conference,
Paper No. OTC 20051-PP, Houston, TX, 4-7 May 2009.
Analysis of ILI inspection reports can indicate that there [6] D. Sandana, J. Soltis, J. of Pipeline Eng., 14(4), 269 (2015).
are multiple factors that can lead to the reason no corrosion was [7] D. Sandana, J. Soltis, J. Wilkinson, “Effective Implementation
found at certain locations., for example, the speed tolerance of of Asset Integrity Management Systems with Visualisation
the tool may have been exceeded numerous times during the ILI Tools”, Paper No. C2016-7276, Corrosion 2016, NACE
run. As a result areas where these speed excursions apply, the International, Houston, TX (2016).
normal tool sizing tolerances may therefore not be applicable. [8] J. Walker, In-Line Inspection of Pipelines: Advanced
In addition to this, the inspection tool may have been designed Technologies for Economic and Safe Operation of Oil and Gas
to work effectively up to a certain maximum wall thickness. Pipelines, Die Bibliothek der Technik, Vol. 327, 2nd Ed.,
Suddeutcher Verlag onpac GmbH, Munich (2014).
CONCLUDING REMARKS [9] D. Sandana, M. Dale, “An Integrated Approach to Corrosion
In this study we combine flow modelling and corrosion risk Management of Aging Offshore Assets”, Paper No. C2012-
assessment in to a synergistic approach to identify and prioritize 0001390, Corrosion 2012, NACE International, Houston, TX
critical locations for direct inspection of the challenging (2012).
multiphase pipeline. Internal corrosion is arguably not the [10] J. Soltis, P. Birkinshaw, D. Sandana, “Operational Pigging – A
primary cause of pipeline failures. However, while internal Frontline Tool to Control Internal Corrosion of Pipelines”,
corrosion might not be considered a dominant or immediate PPSA Seminar and Workshop, Aberdeen, UK, 18 November
integrity threat to pipelines; it is undoubtedly the most difficult 2015.
to manage and probably the main reason why production assets [11] J. Brill, “Modeling Multiphase Flow in Pipelines”, The Way
are ultimately retired from service. Ahead, 6(2), 16 (2010).
[12] B. Guo, S. Song, A. Ghalambor, T.R. Lin, Offshore Pipelines
Flow assurance together with corrosion risk assessments, or (Second Edition), Design, Installation, and Maintenance (2014).
separately, can be used to form another key pillar within a [13] G. Gabetta, M. Margarone, A bennardo, “Internal Corrosion
holistic CMS. Individual ILI runs, can detect and report metal Prediction using Fluid Dynamics for Pipeline Integrity”, 10th
loss (often attributed to corrosion), but further analysis of the Offshore Mediterranean Conference, Ravenna, Italy, 23-25
reported results can help to identify and diagnose the likely March 2011.
cause of corrosion. In lieu of inspection data, flow assurance [14] P. Gartland, J. Salomonsen, “A Pipeline Integrity
aids with focusing direct inspection on areas most likely Management Strategy Based on Multiphase Fluid Flow and
effected by internal corrosion. Without ILI data, selection of Corrosion Modelling”, Paper No. 622, Corrosion 99, NACE
inspection locations becomes problematic, and the confidence International, Houston,TX (1999).
in results representative of the entire pipeline could be [15] Standard Practice, “Wet Gas Internal Corrosion Direct
perceived as unsafe. However, integrations of flow modelling Assessment Methodology for Pipelines”, NACE SP0110-2010,
allows for a more representative condition assessment to be NACE International, Houston, TX (2010).
built from a firm foundation, with decisions constructed upon [16] Standard Practice, “Internal Corrosion Direct Assessment
clear, transparent reasoning. Methodology for Pipelines Carrying Normally Dry Natural Gas
(DG-ICDA)”, NACE SP0206-2006, NACE International,
Houston, TX (2006).

6 Copyright © 2017 ASME

Downloaded From: http://proceedings.asmedigitalcollection.asme.org/ on 08/15/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use


[17] Standard Practice, “Internal Corrosion Direct Assessment [33] S. Nesic, “Key issues related to modelling of internal
Methodology for Liquid Petroleum Pipelines”, NACE SP0208- corrosion of oil and gas pipelines – A review”, Corrosion. Sci.,
2008, NACE International, Houston, TX (2008). 49, 4308 (2007).
[18] DG-ICDA: How confident Are You in Your Inspection [34] J. Soltis, K. Lichti, A. Crisford, “Understanding and
Locations, NACE, Corrosion 2012, C2012-0001437, Houston, Controlling CO2 corrosion through materials research, Oil &
TX (2012) Gas Australia, 9, 36 (2012).
[19] Internal Corrosion Direct Assessment of Buried Steel Pipeline [35] J. Han, D. Young, H. Colijn, A. Tripathi, S. Nesic, "Chemistry
in Chinese Oil Industry, NACE, Corrosion 2008, Paper No. and Structure of the Passive Film on Mild Steel in CO2
08130, Houston, TX (2008) Corrosion Environments," Ind. Eng. Chem. Res. 48 p. 6296-
[20] Practical Application of the Internal Corrosion Direct 6302. (2009).
Assessment Process for Natural Gas Pipelines, NACE, [36] Y. Yang, B. Brown, S. Nesic, M. Elena Gennaro, B. Molinas,
Corrosion 2003, Paper No. 03189, Houston, TX (2003) “Mechanical Strength and Removal of a Protective Iron
[21] The Challenges of implementing the Internal Corrosion Direct Carbonate Layer Formed on Mild Steel in CO2 Corrosion,”
Assessment Method, NACE, Corrosion 2003, Paper No. 03185, Paper No. 10383, CORROSION 2010, NACE International,
Houston, TX (2003) Houston, TX ( 2010).
[22] Internal Corrosion Direct Assessment of Gas Transmission [37] R.H. Hausler, G. Schmitt, “Hydrodynamic and Flow Effects
Pipelines, NACE, Corrosion 2002, Paper No. 02087, Houston, on Corrosion Inhibition,” Paper No.04402, CORROSION
TX (2002) 2004, NACE International, Houston, TX (2004).
[23] Facilitating Internal Corrosion Direct Assessment Using [38] A. C. Palmer, R. A. King, “Subsea Pipeline Engineering “,
Advanced Flow and Corrosion Prediction Models, NACE, 2nd Edition. PennWell (2008).
Corrosion 2008, Paper No. 08131, Houston, TX (2008) [39] Y. Chen, H. J. Chen, W. P. Jepson, “Effects of Multiphase
[24] Internal Corrosion Direct Assessment for Multiphase Flow Flow on Corrosion Inhibitor”, Paper No. 12, Corrosion 99,
Pipeline Systems, SPE International, SPE 103922 (2006) NACE International, Houston, TX (1999).
[25] Internal Corrosion Direct Assessment for Offshore Pipelines, [40] M. Davies, P. J. B. Scott, “Oilfield Water Technology”, 1st
NACE, Corrosion 2016, Paper No. 7092, Houston, TX (2016) Edition, NACE International, Houston, TX (2006).
[26] Internal Corrosion Direct Assessment of a High Pressure Wet [41] E.M. Prodger, “An Overview of the Selection Procedures
Gas Pipeline Using NACE SP0110, NACE, Corrosion 2013, Employed for Oilfield Chemicals”, Proceedings of the
Houston, TX (2013) Conference on Redefining International Standards and Practices
[27] V. Lagad, S. Srinivasan, K.W. Yap, “Effect of flow on in the Oil and Gas Industry, IIR, (1992).
Corrosion – Experimental Findings and Empirical correlations”, [42] V. V. Lagad, S. Srinivasan, R. D. Kane, “Facilitating Internal
Paper No. C2012-0001194, Corrosion 2012, NACE Corrosion Direct Assessment Using Advanced Flow And
International, Houston, TX (2012). Corrosion Prediction Models”, Paper No. 08131, Corrosion
[28] R.B. Dooley and V.K. Chexal, “Flow-Accelerated Corrosion”, 2008, NACE International, Houston, TX (2008).
Paper No. 347, Corrosion 99, NACE International, Houston, [43] Pipesim User Guide 2012.2
TX (1999). [44] NORSOK Standard M-506 CO2 Corrosion Rate Calculation
[29] G. Schmitt, C. Bosch, P. Plagemann, K. Moeller, “Local Wall Model, March 2005.
Shear Stress Gradients in the Slug Flow Regime – Effect of [45] C. Li, X. Tang, F. Ayello, J. Cai, S. Nesic, C. Iavn, T. Cruz, J.
Hydrocarbon and Corrosion”, Paper No.02244, CORROSION Al-Khamis, “Experimental Study on Water Wetting and CO2
02 , NACE International, Houston, TX (2002). Corrosion in Oil-Water Two-Phases Flow”, Paper No. 06595,
[30] L. Maley, P. Jepson, “Wall Shear Stress and Differential Corrosion 2006, NACE International, Houston, TX (2006).
Pressure in Large-Diameter Horizontal Multiphase Pipelines” [46] A. Aiyejina, D. Chakrabarty A. Pilgrm, M. Sastry, “Wax
Journal of Energy Resources Technology, 122 ): p.193-197 formation in pipelines: A critical review”, Int J. Multiphase
(2000). Flow, 37, 671 (2011).
[31] C. Canto, et al, “Integrity of Corrosion Inhibitor Films in [47] S. Olsen, “CO2 Corrosion Prediction by Use of the NORSOK
Multiphase Flow”, Paper No. 11238, Corrosion 2011, NACE M-506 Model – Guidelines and Limitations”, Paper No. 03623,
International, Houston, TX (2011). Corrosion 2003, NACE International, Houston, TX (2003).
[32] V. D. Atkinson, “Corrosion and Its Control” NACE
International, 2nd Edition, Houston, TX (1995).

7 Copyright © 2017 ASME

Downloaded From: http://proceedings.asmedigitalcollection.asme.org/ on 08/15/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use


ANNEX A

GRAPHS

Figure 1: Pipeline volumetric flow rate constituents. Figure 4: Distribution of the time-averaged water hold-up along
the pipeline length.

Figure 2: OLGA pipeline elevation schematic.

Figure 3. Distribution of the time-averaged wall shear stress along


the pipeline length.

8 Copyright © 2017 ASME

Downloaded From: http://proceedings.asmedigitalcollection.asme.org/ on 08/15/2017 Terms of Use: http://www.asme.org/about-asme/terms-of-use

You might also like