A.3.2.1.2 Memasang 1 m3 pondasi batu belah, campuran 1 Portland cement : 4 Pasir Pasang
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Batu belah 15/20 cm m3 1.2000 583,333.33 700,000.00
Bahan Portland Cement kg 163.0000 1,400.00 228,200.00
Pasir Pasang m3 0.5200 165,000.00 85,800.00
Pekerja OH 1.5000 105,000.00 157,500.00
Tukang batu OH 0.7500 115,000.00 86,250.00
Tenaga Kerja
kepala tukang OH 0.0750 130,000.00 9,750.00
Mandor OH 0.0750 140,000.00 10,500.00
Jumlah harga per satuan pekerjaan 1,278,000.00
A.4.1.1.2 Membuat 1 m3 beton mutu f'c = 9,8 Mpa (K 125), Slump ( 12 ± 2 ) cm, w/c =0,78
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Portland Cement kg 276.0000 1,400.00 386,400.00
Pasir Beton kg 828.0000 117.86 97,585.71
Bahan
Kerikil (max. 30 mm) kg 1012.0000 348.07 352,248.29
Air Liter 215.0000 67.00 14,405.00
Pekerja OH 1.6500 105,000.00 173,250.00
Tukang batu OH 0.2750 115,000.00 31,625.00
Tenaga Kerja
kepala tukang OH 0.0280 130,000.00 3,640.00
Mandor OH 0.0830 140,000.00 11,620.00
Jumlah harga per satuan pekerjaan 1,070,774.00
A.4.4.3.58.b Membuat dan memasang 1 m2 pasang dinding batu alam susun sirih andesit
Harga Satuan
Bahan/ Upah ( Rp. Jumlah
Kebutuhan Satuan Indeks
) ( Rp. )
Batu Alam M2 1.1000 100,000.00 110,000.00
Bahan semen abu-abu Kg 11.7500 26,000.00 305,500.00
Pasir Pasang M3 0.0350 1,400.00 49.00
Pekerja OH 0.7000 105,000.00 73,500.00
Tukang batu OH 0.3500 115,000.00 40,250.00
Tenaga Kerja
kepala tukang OH 0.0350 130,000.00 4,550.00
Mandor OH 0.0350 140,000.00 4,900.00
Jumlah harga per satuan pekerjaan 538,749.00
SNI 3434 : 2008 Memasang 1 m3 kontruksi kuda-kuda konvensional, kayu I, II dan III bentang 6 meter
6.13 Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Balok Kayu m3 1.1000 4,120,454.55 4,532,500.00
Bahan Besi strip tebal 5 mm kg 15.0000 21,570.25 323,553.72
Paku 12 cm kg 5.6000 20,000.00 112,000.00
Pekerja OH 4.0000 105,000.00 420,000.00
Tukang kayu OH 12.0000 115,000.00 1,380,000.00
Tenaga Kerja
kepala tukang OH 1.2000 130,000.00 156,000.00
Mandor OH 0.2000 140,000.00 28,000.00
Jumlah harga per satuan pekerjaan 6,952,053.72
11.6.1 Membuat dan memasang 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Balok kayu m3 1.1000 5,886,363.64 6,475,000.00
Bahan Paku 10 cm kg 1.2500 28,000.00 35,000.00
Lem Kayu kg 1.0000 16,909.09 16,909.09
Pekerja OH 7.0000 105,000.00 735,000.00
Tukang kayu OH 21.0000 115,000.00 2,415,000.00
Tenaga Kerja
kepala tukang OH 2.1000 130,000.00 273,000.00
Mandor OH 0.3500 140,000.00 49,000.00
Jumlah harga per satuan pekerjaan 9,998,909.09
11.6.5 Membuat dan memasang 1 m2 Daun Pintu Panel, kayu Ulin Harga Satuan
Bahan/ Upah ( Rp. Jumlah
Kebutuhan Satuan Indeks
) ( Rp. )
Papan kayu ulin m3 0.0400 9,350,000.00 374,000.00
Bahan
Lem kayu kg 0.5000 16,909.09 8,454.55
Pekerja OH 1.0000 105,000.00 105,000.00
Tukang kayu OH 3.0000 115,000.00 345,000.00
Tenaga Kerja
kepala tukang OH 0.3000 130,000.00 39,000.00
Mandor OH 0.0500 140,000.00 7,000.00
Jumlah harga per satuan pekerjaan 878,454.55
11.6.5.a Membuat dan memasang 1 m2 Daun Pintu Panel, kayu Klas II Harga Satuan
Bahan/ Upah ( Rp. Jumlah
Kebutuhan Satuan Indeks
) ( Rp. )
Papan kayu Klas II m3 0.0400 4,000,000.00 160,000.00
Bahan
Lem kayu kg 0.5000 16,909.09 8,454.55
Pekerja OH 1.0000 105,000.00 105,000.00
Tukang kayu OH 3.0000 115,000.00 345,000.00
Tenaga Kerja
kepala tukang OH 0.3000 130,000.00 39,000.00
Mandor OH 0.0500 140,000.00 7,000.00
Jumlah harga per satuan pekerjaan 664,454.55
11.6.6 Membuat dan memasang 1 m2 Pintu dan jendela kaca, kayu kelas II Harga Satuan
Bahan/ Upah ( Rp. Jumlah
Kebutuhan Satuan Indeks
) ( Rp. )
Papan kayu Klas II m3 0.0240 4,000,000.00 96,000.00
Bahan Kaca bening 5 mm m2 1.1000 124,000.00 136,400.00
Lem kayu kg 0.3000 16,909.09 5,072.73
Pekerja OH 0.8000 105,000.00 84,000.00
Tukang kayu OH 2.4000 115,000.00 276,000.00
Tenaga Kerja
kepala tukang OH 0.2400 130,000.00 31,200.00
Mandor OH 0.0400 140,000.00 5,600.00
Jumlah harga per satuan pekerjaan 634,272.73
SNI 2002 12.6.17 Memasang 1 M2. Pasang kaca , tebal 5 mm Harga Satuan
Bahan/ Upah ( Rp. Jumlah
Kebutuhan Satuan Indeks
) ( Rp. )
Bahan Kaca bening 5 mm m2 1.1000 124,000.00 136,400.00
Pekerja OH 0.0150 105,000.00 1,575.00
Tukang kayu OH 0.1500 115,000.00 17,250.00
Tenaga Kerja
kepala tukang OH 0.0150 130,000.00 1,950.00
Mandor OH 0.0008 140,000.00 112.00
Jumlah harga per satuan pekerjaan 157,287.00
SNI 3434 : 2008 Memasang 1 m2 rangka atap genteng metal, kayu kelas II
6.17a Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
kaso-kaso (5x7) cm m3 0.0140 4,120,454.55 57,686.36
Bahan Reng (3x4) cm m3 0.0072 4,120,454.55 29,667.27
Paku 5 dan 10 cm kg 0.2500 20,000.00 5,000.00
Pekerja OH 0.1000 105,000.00 10,500.00
Tukang kayu OH 0.1000 115,000.00 11,500.00
Tenaga Kerja
kepala tukang OH 0.0100 130,000.00 1,300.00
Mandor OH 0.0050 140,000.00 700.00
Jumlah harga per satuan pekerjaan 116,353.63
SNI 3434 : 2008 Memasang 1 m2 rangka langit-langit ( 50x 100 ) cm, kayu kelas II atau III
6.20.a Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
kaso-kaso (5x5) cm m3 0.0154 4,120,454.55 63,455.00
Bahan
Paku 7 dan 10 cm kg 0.2000 20,000.00 4,000.00
Pekerja OH 0.1500 105,000.00 15,750.00
Tukang kayu OH 0.3000 115,000.00 34,500.00
Tenaga Kerja
kepala tukang OH 0.0300 130,000.00 3,900.00
Mandor OH 0.0075 140,000.00 1,050.00
Jumlah harga per satuan pekerjaan 122,655.00
SNI 3434 : 2008 Memasang 1 m' listplank ukuran ( 2 x 20 ) cm, kayu kelas II
6.22 Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Papan kayu m3 0.0108 4,000,000.00 43,200.00
Bahan
Paku 5 dan 7 cm kg 0.1000 20,000.00 2,000.00
Pekerja OH 0.1000 105,000.00 10,500.00
Tukang kayu OH 0.2000 115,000.00 23,000.00
Tenaga Kerja
kepala tukang OH 0.0200 130,000.00 2,600.00
Mandor OH 0.0050 140,000.00 700.00
Jumlah harga per satuan pekerjaan 82,000.00
11.6.10a Memasang 1 m2 Jalusi kusen, kayu kelas II
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Papan kayu m3 0.0600 4,000,000.00 240,000.00
Bahan
Paku 1-2,5 cm kg 0.1500 20,000.00 3,000.00
Pekerja OH 0.6700 105,000.00 70,350.00
Tukang kayu OH 2.0000 115,000.00 230,000.00
Tenaga Kerja
kepala tukang OH 0.2000 130,000.00 26,000.00
Mandor OH 0.3350 140,000.00 46,900.00
Jumlah harga per satuan pekerjaan 616,250.00
SNI 2839 : 2008 Memasang 1 m2 langit-langit Kalsiboard ukuran (120 x 240) cm, tebal 4 mm
6.5.b Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Kalsiboard 9 mm lembar 0.3750 70,000.00 26,250.00
Bahan
Paku teripleks kg 0.0300 25,000.00 750.00
Pekerja OH 0.1000 105,000.00 10,500.00
Tukang kayu OH 0.1000 115,000.00 11,500.00
Tenaga Kerja
kepala tukang OH 0.0100 130,000.00 1,300.00
Mandor OH 0.0050 140,000.00 700.00
Jumlah harga per satuan pekerjaan 51,000.00
A.4.4.1.9 Memasang 1 m2 dinding bata merah ukuran ( 5 x 11 x 22 )cm tebal 1/2 bata
campuran spesi 1 Portland cement : 4 Pasir pasang
Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Bata merah buah 70.0000 600.00 42,000.00
Bahan Portland cement kg 11.5000 1,400.00 16,100.00
pasir pasang m3 0.0430 165,000.00 7,095.00
Pekerja OH 0.3000 105,000.00 31,500.00
Tukang batu OH 0.1000 115,000.00 11,500.00
Tenaga Kerja
kepala tukang OH 0.0100 130,000.00 1,300.00
Mandor OH 0.0150 140,000.00 2,100.00
Jumlah harga per satuan pekerjaan 111,595.00
SNI 2410 : 2002 1 M2. Pengecatan bidang kayu baru ( 1 lapis plamir,1 lapis cat dasar,2 lapis cat penutup )
6.8 Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Plamir kayu / dempul kayu kg 0.1500 61,818.18 9,272.73
Bahan Cat meni kg 0.2000 50,000.00 10,000.00
Cat dasar kg 0.1700 75,000.00 12,750.00
Cat penutup 2 kali kg 0.2600 75,000.00 19,500.00
Pekerja OH 0.0700 105,000.00 7,350.00
Tukang cat OH 0.0090 115,000.00 1,035.00
Tenaga Kerja
kepala tukang OH 0.0060 130,000.00 780.00
Mandor OH 0.0025 140,000.00 350.00
Jumlah harga per satuan pekerjaan 61,037.73
SNI 2410 : 2002 1 M2 Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar,2 lapis cat penutup )
6.14 Harga Satuan Jumlah
Kebutuhan Satuan Indeks Bahan/ Upah ( Rp.
) ( Rp. )
Diperiksa : Dibuat :
Pejabat Pelaksana Teknis Kegiatan (PPTK) CV. MITRA JASA
Disetujui :
Kuasa Pengguna Anggaran
(KPA)
Mengetahui :
Pengguna Anggaran
(PA)
II. BAHAN
1 Atap multi roof uk.77 x 100 cm pakai lembar Rp 75,000.00
pasir
#Atap multi roof (1 M2 = 1,3 lembar). M2 Rp 97,500.00
2 Air Liter Rp 67.00
4 Balok kayu kelas II M3 Rp 4,120,454.55
5 Balok kayu ulin kelas A M3 Rp 5,886,363.64
6 Batu bata Buah Rp 600.00
7 Bataco Buah Rp 2,640.00
8 Batu pecah 1 - 2 cm M3 Rp 487,300.00
# Batu pecah 1 - 2 cm Kg Rp 348.07
9 Batu belah M3 Rp 583,333.33
10 Dempul kayu Kg Rp 61,818.18
11 Pasir Pasang M3 Rp 165,000.00
12 Pasir beton M3 Rp 165,000.00
# Pasir beton Kg Rp 117.86
13 Pasir urug / timbunan M3 Rp 165,000.00
14 Paving Stone Buah Rp 2,892.56
15 Tanah urug biasa M3 Rp 109,375.00
16 Tanah Subur M3 Rp 121,212.12
17 Besi beugel / baut ( kuda - kuda ) Kg Rp 21,570.25
18 Besi beton polos Kg Rp 12,800.00
19 Bubungan Genteng Sakura Roof Buah Rp 45,000.00
20 Cat kayu dasar Kg Rp 75,000.00
21 Cat kayu mengkilap Kg Rp 75,000.00
22 Cat menie Kg Rp 50,000.00
23 Cat tembok Kg Rp 75,000.00
24 Engsel jendela DPJ 3" Bh Rp 60,000.00
25 Engsel pintu DPJ 5" Bh Rp 127,000.00
26 Kawat beton Kg Rp 25,000.00
27 Kayu bulat dia 10 cm / 4 m Btg Rp 20,000.00
28 #Kayu bulat dia 10 cm / 4 m M' Rp 5,000.00
29 Kayu perancah / terentang M3 Rp 1,975,537.19
30 Kunci pintu tanam biasa Bh Rp 250,000.00
31 Minyak cat Liter Rp 50,000.00
32 Paku atap metal , sejenisnya Kg Rp 28,500.00
33 Paku kayu Kg Rp 20,000.00
34 Paku seng 13/4 " Kg Rp 59,000.00
35 Paku ulin Kg Rp 28,000.00
36 Paku plywood Kg Rp 25,000.00
37 Papan begisting / bouwplank M3 Rp 1,975,537.19
38 Papan ulin 2 x 20 cm M3 Rp 9,350,000.00
39 Papan kayu kelas II M3 Rp 4,000,000.00
40 Plywood 3 mm Lembar Rp 70,000.00
41 Plamur tembok Kg Rp 11,272.73
42 Semen PC ( 50 kg / zak ) Zak Rp 70,000.00
43 # Semen PC Kg Rp 1,400.00
No KETERANGAN SATUAN HARGA
I PEKERJAAN PERSIAPAN
1 Pek. Pengukuran
2 Pek. Mobilisasi dan Demobilisasi
II PEKERJAAN TANAH
1 Pek. Galian tanah pondasi Luar Bt. Kali 35.60 0.70 0.80 19.94
Rollag 7.50 0.30 0.40 0.90
20.84 m3
2 Pek. Urugan tanah bawah lantai Kamar 6.50 3.00 0.40 2.60
R. Keluarga & R. Dapur 2.50 7.50 0.40 1.00
Teras 2.00 1.50 0.40 0.80
Ruang Tamu 2.50 4.50 0.40 1.00
Teras Belakang 1.00 2.00 0.40 0.40
5.80 m3
3 Pek. Urugan tanah kembali 6.95 m3
4 Pek. Urugan pasir bawah lantai dan Pondasi Bt. Kali 35.60 0.70 0.10 2.49
Rollag 7.50 0.30 0.10 0.23
Kamar 6.50 3.00 0.10 1.95
R. Keluarga & R. Da 2.50 7.50 0.10 1.88
Teras 2.00 1.50 0.10 0.30
Ruang Tamu 2.50 4.50 0.10 1.13
Teras Belakang 1.00 2.00 0.10 0.20
0.00 8.17 m3
PEKERJAAN BETON DAN PASANGAN
Pek. Pondasi Batu Belah 1pc:4ps Bt. Kali 35.60 0.50 0.60 10.68 m3
7.50 0.30 0.40 0.90 m2
Pek. Sloof 15/20, camp. 1pc : 2ps : 3kr 43.10 0.15 0.20 1.29
Pek Pasangan Bata
Dinding 1 35.60 4.00 142.40
Dinding 2 0.00
m2
Lubang kolom
19.16
156.99
Pek. Plat Dak, camp. 1pc : 2ps : 3kr teras 2.50 2.00 0.10 1.00 0.50 m3
2.50 1.50 0.10 1.00 0.38 m3
3.50 1.20 0.10 1.00 0.42 m3
1.30 m3
Pek. Plat Canopy, camp. 1pc : 3ps : 5kr jendela 1.50 0.50 0.08 2.00 0.12 m3
Plat Jendela Siku 5.00 0.50 0.08 1.00 0.20 m3
0.32 m3
Pas. Keramik Lantai 50x50 Kamar 6.35 3.00 19.05 M2
R. Keluarga & R. Dapur 2.50 7.50 18.75 M2
Teras 2.00 1.50 3.00 M2
Ruang Tamu 2.50 4.50 11.25 M2
Teras Belakang 1.00 2.00 2.00 M2
54.05 M2
0.00
PEKERJAAN KAYU
Pek. Kusen Kayu Ulin 6/12 P1 5.20 0.06 0.12 4.00 0.15
P2 5.10 0.06 0.12 1.00 0.04
j1 5.84 0.06 0.12 2.00 0.08
j2 9.66 0.06 0.12 2.00 0.14
bv 2.96 0.06 0.12 1.00 0.02
Boven Angin Jendela 2.60 0.06 0.12 6.00 0.11
Boven Angin Pintu 2.48 0.06 0.12 5.00 0.09
Boven Angin siku 7.80 0.06 0.12 1.00 0.06
j siku 15.60 0.06 0.12 1.00 0.11
boven atas pintu 5.50 0.06 0.12 1.00 0.04
0.84 m3
Pek. Gording kayu kelas II 5/10 10.00 0.05 0.10 10.00 0.50
0.05 0.10 10.00 0.00
0.50 m3
Pek. Penutup atap genteng metal glasir pasir 10.00 7.20 2.00 144.00
0.00
144.00 m2
Pek. Bubungan genteng metal 10.00 1.00 10.00
0.00
10.00
Pek. Listplank kayu Klas II 2/20 dan 2/10 40.00 40.00 m'
Pek. Daun pintu panil kayu kelas II P1 0.80 2.10 4.00 6.72 m2
P2 0.70 2.00 1.00 1.40 m2
0.00 m2
8.12 m2
Pek. Daun Jendela panil kaca (Ky. Klas II) j1 1.60 0.50 2.00 1.00 1.60
j2 1.80 0.50 2.00 1.00 1.80
bv 0.60 0.60 1.00 1.00 0.36
Boven Angin Pintu 1.72 0.50 1.00 1.00 0.86
Jendela siku 0.60 0.50 1.00 1.00 0.30
4.62 m3
II
A3
I
35.6
9.5
20.8
5.1
11.68
19.32
2.96
15.6
12.4
7.8
15.6
5.5
116.76
9.5 19.000
5.833333 11.667
RENCANA ANGGARAN DAN BIAYA (RAB)
PEKERJAAN = PEMBANGUNAN RUMAH TYPE 50 ATAP LURUS
LOKASI = KOTAWARINGIN BARAT
HARGA JUMLAH
KODE SATUAN HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA
( Rp. ) ( Rp. )
I PEKERJAAN TANAH
1 Pek. Galian tanah pondasi A.2.3.1.1 20.836 M3 47,600.00 991,793.60
2 Pek. Urugan tanah bawah lantai A.2.3.1.11.a 5.800 M3 164,150.00 952,070.00
3 Pek. Urugan tanah kembali A.2.3.1.9. 6.945 M3 27,416.67 190,417.91
4 Pek. Urugan pasir bawah lantai dan Pondasi A.2.3.1.11 8.167 M3 230,900.00 1,885,760.30
Sub Total I 4,020,041.81
II PEKERJAAN BETON DAN PASANGAN
1 Pek. Pondasi Batu Belah 1pc:4ps A.3.2.1.2 10.680 M3 1,278,000.00 13,649,040.00
2 Pas. Rollag 1 Bata 1pc:2ps A.4.4.1.1 0.900 M2 250,900.00 225,810.00
3 Pek. Sloof 15/20, camp. 1pc : 2ps : 3kr A.4.1.1.29.a 1.293 M3 3,929,493.04 5,080,834.50
4 Pek. Pasangan dinding batako 1pc : 5ps A.4.4.1.9 156.990 M2 105,830.00 16,614,251.70
5 Pek. Kolom Praktis 11/11, camp. 1pc:2ps:3kr A.4.1.1.35 64.000 M' 82,491.77 5,279,473.28
6 Pek. Ring Balk 10/15, camp. 1pc:2ps:3kr A.4.1.1.36 67.600 M' 115,761.11 7,825,451.04
7 Pek. Rabat Beton, camp. 1pc : 3ps : 5kr A.4.1.1.2 1.450 M3 1,070,774.00 1,552,622.30
8 Pek. Kolom Teras, camp. 1pc : 3ps : 5kr A.4.1.1.30.d 0.390 M3 6,196,592.22 2,416,670.97
9 Pek. Plat Meja Dapur 6.32c 0.150 M3 5,311,014.45 796,652.17
10 Pek. Plat Dak, camp. 1pc : 2ps : 3kr 6.32c 1.295 M3 5,311,014.45 6,877,763.71
11 Pek. Plat Canopy, camp. 1pc : 3ps : 5kr 6.32c 0.320 M3 5,311,014.45 1,699,524.62
12 Pek. Plesteran dinding camp. 1pc : 4ps A.4.4.2.4. 313.980 M2 65,496.00 20,564,434.08
13 Pek. Acian dinding A.4.4.2.27. 313.980 M2 39,750.00 12,480,705.00
14 Pas. Keramik Lantai 50x50 A.4.4.3.34 54.050 M2 421,091.00 22,759,968.55
15 Pas. Keramik lantai KM/WC 20/20 A.4.4.3.36 3.000 M2 171,505.45 514,516.36
16 Pas. Dinding Keramik WC (25x20) A.4.4.3.54 10.400 M2 173,830.45 1,807,836.73
17 Pas. Meja Dapur 60x60 A.4.4.3.55 1.440 M2 246,029.44 354,282.40
18 Pas. Dinding Keramik Dapur(25x20) A.4.4.3.54 1.200 M2 173,830.45 208,596.55
Sub Total III 120,708,433.95
III PEKERJAAN KAYU
1 Pek. Kuda-kuda Ulin 6/12 6.13 0.518 M3 6,952,053.72 3,603,944.65
1 Pek. Kusen Kayu Ulin 6/12 11.6.1 0.841 M3 9,998,909.09 8,405,802.90
2 Pek. Gording kayu kelas II 5/10 6.15 0.500 M3 6,106,453.72 3,053,226.86
3 Pek. Rangka langit grid 60x120 cm, kayu klas II 6.20.a 105.050 M2 122,655.00 12,884,907.75
4 Pek. Plafond Plywood 3 mm 6.5.b 105.050 M2 51,000.00 5,357,550.00
5 Pek. Penutup atap genteng metal glasir pasir 6.32 144.000 M2 146,890.00 21,152,160.00
6 Pek. Bubungan genteng metal 6.36 10.000 M' 98,195.00 981,950.00
7 Pek. Listplank kayu Klas II 2/20 dan 2/10 6.22 40.000 M' 82,000.00 3,280,000.00
8 Pek. Daun pintu panil kayu kelas II 11.6.5.a 8.120 M2 664,454.55 5,395,370.91
9 Pek. Daun Jendela panil kaca (Ky. Klas II) 11.6.6 4.620 M2 634,272.73 2,930,340.00
10 Memasang 1 M2. Pasang kaca , tebal 5 mm SNI 2002 12.6.17 0.774 M2 157,287.00 121,740.14
Sub Total IV 67,166,993.21
IV PEKERJAAN KUNCI DAN PENGGANTUNG
1 Pasang Kunci tanam biasa Ls 4.000 Bh 250,000.00 1,000,000.00
2 Pek. Grendel 3" Lokal Biasa Ls 5.000 Bh 7,102.73 35,513.64
3 Pasang Engsel Pintu Ls 15.000 Bh 127,000.00 1,905,000.00
4 Pasang Engsel Jendela Ls 16.000 Bh 60,000.00 960,000.00
5 Pasang hak angin kuningan Ls 8.000 Bh 15,727.27 125,818.18
6 Pasang Tarikan jendela Ls 8.000 Bh 14,090.91 112,727.27
Sub Total V 4,139,059.09
HARGA JUMLAH
KODE SATUAN HARGA
NO URAIAN PEKERJAAN VOLUME
ANALISA
( Rp. ) ( Rp. )
V PEKERJAAN INSTALASI LISTRIK
1 Pek. Instalasi titik lampu Ls 8.000 Ttk 250,000.00 2,000,000.00
2 Pek. Instalasi + stop kontak Ls 5.000 Ttk 250,000.00 1,250,000.00
3 Pasang MCB Ls 2.000 Ttk 65,454.55 130,909.09
4 Lampu LED 9 Watt Ls 8.000 Ttk 95,000.00 760,000.00
Sub Total VI 4,140,909.09
VI PEKERJAAN INSTALASI AIR BERSIH DAN AIR KOTOR
1 Pek. Pasang Bak mandi 50 x 50 cm Ls 1.000 Bh 220,000.00 220,000.00
2 Pek. Pasang Closed Jongkok porselin Ls 1.000 Bh 494,690.00 494,690.00
3 Pek. Pasang Kran air Ls 5.000 Bh 56,000.00 280,000.00
4 Pek. Pasang Floordrain Ls 1.000 Bh 25,000.00 25,000.00
5 Pek. Kitchen Zinc Ls 1.000 Bh 600,000.00 600,000.00
6 Pek. Pasang Instalasi pipa air bersih dia. 3/4 " Ls 40.000 M' 7,609.09 304,363.64
7 Pek. Pasang Instalasi pipa air kotor dia. 4 " AW Ls 10.000 M' 67,431.82 674,318.18
8 Pek. Pasang Instalasi pipa air kotor dia. 2 " AW Ls 20.000 M' 21,136.36 422,727.27
9 Pek. Aksesories Pipa dan Lem Pipa Ls 1.000 Ls 1,000,000.00 1,000,000.00
10 Pek. Pembuatan septick tank Ls 1.000 Bh 4,000,000.00 4,000,000.00
Sub Total VII 8,021,099.09
VII PEKERJAAN PENGECATAN
1 Pengecatan tembok 6.14 419.030 M2 37,482.50
2 Pek. Cat Kilap Kayu 6.8 76.245 M2 61,037.73 4,653,809.52
Sub Total VIII 4,653,809.52
Total (I s/d VII ) 212,850,345.76
#VALUE!
0.9
1.8
2.7
196,036,378.06
#VALUE!
75,000,000.00
74,869,090.91
54.050 45
3,938,026.75 180,000,000.00 32,850,345.76
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN = PEMBANGUNAN RUMAH TYPE 50 ATAP LURUS
LOKASI = KOTAWARINGIN BARAT
I PEKERJAAN PERSIAPAN -
II PEKERJAAN TANAH 4,020,041.81
III PEKERJAAN BETON DAN PASANGAN 120,708,433.95
IV PEKERJAAN KAYU 67,166,993.21
V PEKERJAAN KUNCI DAN PENGGANTUNG 4,139,059.09
VI PEKERJAAN INSTALASI LISTRIK 4,140,909.09
VII PEKERJAAN INSTALASI AIR BERSIH DAN AIR KOTOR 8,021,099.09
VIII PEKERJAAN PENGECATAN 4,653,809.52
JUMLAH 212,850,345.76
PEMBULATAN 145,000,000.00
Terbilang : Seratus Empat Puluh Lima Juta Rupiah