The dates pm this list are the official Ford Gateway dates.

To support filing and delivery on time the supplier supporting material is required ahead of the gateway. Detailed timing needs to be aligned with the Ford D'R engineer.

"C519 ACTIVE GLOBAL SUPPLIER DATA SHEET" - GI-VPP 4481 on 22-Jan 2018
(based on authorized C519 Active FNA <PA> VPP-4481, approved in GPDS LL2 Forum on 22-Jan 2018)

KEY PLANT MILESTONES FoE China FNA Australia - BU


5dr, Wagon 5dr 5dr 5dr from SLS Plant, FoE
Saarlouis Chongqing II Chongqing II

MR 07-Dec 2015 N/A N/A ---


PS 23-Mar 2016 N/A N/A ---
PSC 06-Jun 2016 12-Dec 2016 12-Dec 2016 ---
PTC 12-Dec 2016 --- --- ---
M1DJ 09-Dec 2016 09-Dec 2016 09-Dec 2016 ---
M1 M1.1 - 24-Mar '17 --- M1.3 - 25-Sep '17 ---
M1.2 - 12-May '17 --- ---
M1DC 17-Jul 2017 17-Jul 2017 08-Dec 2017 ---
PA 24-May 2017 24-May 2017 07-Feb 2018 ---
FDJ 24-Jul 2017 24-Jul 2017 15-Dec 2017 ---
VP/DCV 09-Jan 2018 09-Jan 2018/HB - 02-Jul 2018 14-May 2018 ---
PEC 16-Apr 2018 16-Apr 2018 21-Sep 2018 ---
FEC 14-May 2018 14-May 2018 30-Oct 2017 ---
LR 28-May 2018 Stg. 5/6 - 13-Nov '18 13-Nov 2018 ---
LS 13-Aug 2018 Stg. 5/6 - 12-Feb '19 12-Feb 2019 ---
MP1 15-Oct 2018 Stg. 5/6 - 08-May '19 08-May 2019 15-Oct 2018
MP2 05-Nov 2018 Stg. 5/6 - 05-Jun '19 05-Jun 2019 05-Nov 2018
OKTB 26-Nov 2018 Stg. 5/6 - 02-Jul '19 02-Jul 2019 26-Nov 2018

M1 - FoE & China UN-Phase

M1.1 Elect BB/Bailment MRD 03-Feb 2017 UNV0 Start 15-Aug 2016
M1.1 S/M MRD 17-Feb 2017 UNV0 Finish 28-Oct 2016
M1.1 T/C MRD Re-Build's 03-Mar 2017 UNV1/2 Start 28-Oct 2016
M1.2 S/M MRD 03-Apr 2017 UNV1/2 Finish 30-Nov 2016
M1.2 T/C MRD Ground-up's 21-Apr 2017
UP-Phase
M1 - FNA
UPV0 Start 05-Jul 2016
M1.3 Elect BB/Bailment MRD 10-Jul 2017 UPV0 Finish 05-Dec 2016
M1.3 S/M MRD 24-Jul 2017 UPV1 Start 05-Dec 2016
M1.3 T/C MRD 07-Aug 2017 UPV1 Finish 27-Feb 2017
UPV2 Start 27-Feb 2017
UPV2 Finish 22-May 2017
DCV (VP) - FoE & China

DCV Elect BB/Bailment MRD 13-Oct 2017 P-Releases


DCV S/M MRD 27-Oct 2017 24-Jul - 21-Aug 2017
DCV T/C MRD 17-Nov 2017

DCV (VP) - FNA

DCV (VP) Elect BB/Bailment MRD 16-Mar 2018


DCV (VP) S/M MRD 30-Mar 2018
DCV (VP) T/C MRD 13-Apr 2018

HB - 1.5l GTDI Active Stage 5/6

HB SM MRD 16-May 2018


HB TCF MRD 30-May 2018

Powerpack - FoE

1.5l DV NEO 120PS B6+ 2.0l Panther 150PS MMT6


1.5l DV NEO 120PS 8F35 2.0l Panther 150PS 8F40
1.5l GTDI 150PS B6+ 1.0l GTDI 125PS 6MX65
1.5l GTDI 150PS 8F24 1.0l GTDI 125PS 8F24

1.5l GTDI 175PS 8F24 - for Australia BU from SLS Plant, FoE

Powerpack - FNA

1.5l GTDI 175PS 8F24

Powerpack - China

1.5l Active GTDI 175PS 8F24 - Stage 5/6 - MP1 = 08-May 2019

Launch Timing FoE, China, FNA,


Saarlouis Chongqing Chongqing

TCB1 IPD 12-Feb 2018 --- ---


TCB1 Start Assy 26-Feb 2018 --- ---
TCB2 Start Assy 18-Jun 2018 --- ---
TCB3 Start Assy 27-Aug 2018 --- ---

TT Body IPD / (FoE /- subs) 25-May 2018 20-Nov 2018 20-Nov 2018
TT T/C IPD 15-Jun 2018 05-Dec 2018 05-Dec 2018

PP Body IPD 17-Aug 2018 12-Feb 2019 12-Feb 2019


PP T/C IPD 24-Aug 2018 27-Feb 2019 27-Feb 2019

MP1 IPD 21-Sep 2018 30-Apr 2019 30-Apr 2019


MP2 Start 05-Nov 2018 29-May 2019 29-May 2019

24.01.2018