Maintenance:
Planning is one of the major and important functions for effective management. It helps in
achieving goals and objectives in the most efficient and effective manner.
Planning is usually divided into three levels, depending on the objective and the planning horizon.
The levels are as follows:
1. long-range planning (covers a period of five or more years);
2. medium-range planning (covers 1 month to 3 years); and
3. short-range planning (daily, weekly, and monthly plans).
Firstly:
Maintenance strategic planning is a long-range planning and is concerned with the determination
of maintenance mission, strategic goals, and objectives.
Secondly:
Maintenance capacity planning is medium- to long-range planning for maintenance involves the
determination of the maintenance resources that are needed to perform the maintenance load in
order to achieve organizational objectives such as availability, reliability, quality rates and
delivery dates.
Maintenance forecasting is an essential activity for planning.
Maintenance forecasting comprises the estimation and prediction of the maintenance load. and it
consists of two major categories.
(1) The first category is the scheduled and planned maintenance which is formed of
(1) routine and preventive maintenance.
(2) scheduled overhauls which involve closure or plant shutdown,
(3) ) Corrective maintenance that involves determining the causes of repeated
breakdown and substandard performance as a result of design malfunction,
(4) scheduled overhaul, repair, or building of equipment which is not covered
under item.
The forecasting of the maintenance load for a new plant is more difficult and must rely on
. 1similar plants’ experience,
2. benchmarking, management experience
3. and manufacturers’ information
Example
Suppose it is forecasted that the mechanical maintenance load is 100 man-hours
divided into two grades: 60 h of grade 1 and 40 h of grade 2. Grade classification is
based on the skill the work requires and the impact the work has on the facility. The
capacity in man-hours for this work can be provided from two skills of workers, i.e.,
skill 1 and skill 2. Both skills of workers can perform the two types of mechanical
work but with different productivity. The productivity of skill one worker is 0.75
and 0.8 for grade 1 and grade 2 mechanical works, respectively. The productivity of
skill two worker is 0.5 for grade 1 and 0.7 for grade 2 works. The cost of one man-
hour of skill 1 worker is 30 dollars, and the cost of one man-hour of skill 2 worker is
20 dollars. The objective is to determine the number of man-hours from each skill
level workers assigned to perform the maintenance load (work) at a minimum cost.
The first constraint is to meet the load for grade 1 mechanical work. This is stated
mathematically as
0.75 𝑥11 + 0.5𝑥21 ≥ 60
The second constraint is to meet the grade 2 mechanical work mathematically
stated as
0.8𝑥12 + 0.7𝑥22 ≥ 40
The non-negativity restrictions state that the man-hours obtained from each skill
of workers should be nonnegative, mathematically stated as
𝑥11 , 𝑥12 , 𝑥21 , 𝑥22 ≥ 0
The objective function is to minimize the sum of the cost of meeting the required
load from the two skill levels. The linear programming model for determining the
capacity for the mechanical work in the example above is
𝑀𝑖𝑛30(𝑥11 + 𝑥12 ) + 20(𝑥21 + 𝑥22 )
Subject to
0.75𝑥11 + 0.5𝑥21 ≥ 60
0.8𝑥12 + 0.7𝑥22 ≥ 40
𝑥11 , 𝑥12 , 𝑥21 , 𝑥22 ≥ 0
• Solving the above model will determine the allocation of man-hours from
different skills to perform the two grades of mechanical work at minimum
cost.
• The solution of the linear program could be fractional values
• If we want to obtain the solution in whole hours, an additional restriction
must be imposed.
The above model can be solved by any linear programming algorithm such as
1. the simplex-based code in the package Linear Interactive and Discrete
Optimizer (LINDO)
2. or International Mathematical Software Library (IMSL)
3. or the Optimization Software Library (OSL).