CONSTRUCTION CONTRACT

TIPS: DIFFERENCE BETWEEN INSTRUCTION AND VARIATION

The below content gives general tips on the difference between Instruction and Variation provisions
in the Construction Contract.

INSTRUCTION VARIATION
Initiation It will be initiated by the Engineer It can be initiated by the Engineer
or Contractor.
Purpose It gives rights to the Engineer to issue It gives rights to the Engineer to
the instruction to the Contractor for vary the Contract.
carrying out his duties without varying
the Contract.
Does it impact the No Yes
Contract by default?
Employer’s Consent The Engineer does not need any prior The Engineer should have prior
consent from the Employer before consent from the Employer before
issuing it. issuing it.
Contractor’s Notice The contractor must notify back if he It does not require further notice
finds that the Instruction for confirmation by the
impacts/changes the Contract. Contractor.
Variation It is not a Variation unless otherwise It is a Variation by default.
confirmed by the Engineer upon the
Contractor’s Notice of Variation
Closing Out It may need a closeout letter from the It does not need any further
Engineer if the Contractor issued a closeout letter.
Notice of Variation.
Next Action Based on closing out, the Contractor The Contractor should submit
shall take necessary further action as Variation cost and EOT and
per the Contract. additional cost claim, if any, as per
the Contract.

By:

Sagaya, Director,

M: +971 – 55 368 9767, E: Ku.Sagaya@GoodFaith.LLC

For Good Faith (LLC), Dubai, UAE

www.GoodFaith.App