Professional Documents
Culture Documents
Risk Response Strategy Summary
Risk Response Strategy Summary
• Escalate: For threats that clearly exceed the project’s or project manager’s threshold for
management, escalate or hand off to the designated party. If the risk can’t be handled, the
project may be cancelled.
• Avoid: If overall project risk is significantly negative and outside the agreed-upon risk
thresholds for the project, adopt an avoid strategy to take focused action to reduce the
negative effect of uncertainty on the project back inside the threshold.
• Transfer: If the level of overall project risk is high but the organization is unable to
address it effectively, a third party may be involved to manage the risk on behalf of the
organization. Where overall project risk is negative, a transfer strategy is required, which
may involve payment of a risk premium.
• Mitigate: Change the level of overall project risk to optimize the chances of achieving
the project’s objectives — e.g., replan the project, change the scope and boundaries,
modify project priority, change resource allocations, adjust delivery times, etc.
• Accept: Where no proactive risk response strategy is possible to address overall project
risk, the organization may choose to continue with the project as currently defined, even
if overall project risk is outside the agreed-upon thresholds. Acceptance can be either
active or passive. The most common active acceptance strategy is to establish an overall
contingency reserve for the project, including amounts of time, money or resources to be
used if the project exceeds its thresholds. Passive acceptance involves no proactive action
apart from periodic review of the level of overall project risk to ensure that it does not
change significantly.