Professional Documents
Culture Documents
Dashboard (Revised Schedule) - 28 May 23
Dashboard (Revised Schedule) - 28 May 23
اإلتصاالت السعودية
العرض التقدميي اإلسبوعي لتقدم األعامل ابملرشوع
Weekly Progress Presentation
Part-10 t...
Part-2
Part-3
Part-1
Part-8
Part-5
Part-7
Part-6
95% 5- Plastering - Basement (Part 2 - Progressing)
6- MEP 1st Fix in Plumbing Basement (Part 1,2,,3,8,12), Electrical Basement - Part (1,2,3) & Part
2 (GF to 5th Floor) - Progressing
Planned Actual
Areas of Concern
Achieved Remaining
Concrete Progress for Tower (GF+14 Floors) Planned Actual 1- Delay of Payments
Concrete / Skeleton Progress 2- Civil Defence
100% 100% 100% 100% 100% 100% 100% 100% 100%100% 100%
100% 3- Submitted EOT-1 along with delay events & revised BOQ are under process until now.
80% 4- Design review report reply (Design between BOQ & Package Sep-22)
60%
42% 5- MEP activities holding till composite drawing approval & that effect on project SPI
40% 35%
37%
42% 6- Delaying of Response the Technical submittals
58% 20% 7%
0% 7- Sequence of review for material submittals
0%
GF 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor 6th Floor
Achieved Remaining
Planned Actual SAR
Finishes / MEP Progress Planned Actual 75,547,241 SAR
Concrete Progress for Wings (GF+3rd Floor) 68,219,980
100% SAR
100% 95% 93%
90% 87%
0.6% 53,350,445
80%
70%
60%
50%
40% SAR
30%
18%
SAR 14,869,535
20% 7,327,261
99%
6%
10% 0% 4% 0% 0% 0% 0% 0%
0.62% 0%
Part-1 Part 5 Part 10 Part-3 Part 8 Part 12
Submitted Invoices Aprroved Invoices Under Review Invoices Paid Invoices Un-paid Invoics
Planned Actual Achieved Remaining
20 LL Items Histogram 20 PO and Delivery Status Histogram 1500 Shop Drawings Histogram SPI Quality / NCR Status Manpower L/day
18 18 1.20
Planned Submitted Approved A&B Revised C&D 1300
16 Under Review 16 Planned PO Actual PO Planned Delivery Actual Delivery Planned Submitted Approved A&B Revised C&D Under Review
23
1100 1061 1021
1059 1029 1.00 16 844
14 14 957 0.82 0.83
900
12
10 10
12 0.80 650
10 9 9 9 10 700 611
578 0.60
8 8 500 7
406 415
6 6 325 303 0.40
300 268
4 4 219
4 4 3 111 0.20
2 2 2 2 2 2 76 58 54
2 100 34 26 27
2 1
0 0 0 0 0 0 0 0 0 0 0 0 Architectural Strucural Mechanical Electrical 0.00
0 0 100- May-23-21 May-23-28
Architectural Mechanical Electrical Architectural Mechanical Electrical Total Closed Open Planned Actual
Block Works
11%
7% 11%
89%
Revised
Actual 14.53%
Planned 17.54%
SPI 0.83
Actual (Time) 27.62%
Planned (Time) 40.26%
Excavation Progress Achieved 95% Planned
Remaining 5% Actual
SD CURRENT WEEK
Approved
Discipline Total Dwgs Planned Submitted A&B
Architectural 1410 1061 578 219
Strucural 1296 1021 1059 957
Mechanical 612 611 406 268
Electrical 1071 1029 415 303
Total (Nos) 4389 3722 2458 1747
Percentage % 85% 56% 40%
LL Items
Discipline Total LL Items No of Planned PO Actual PO
Materials
Architectural 13 13 0 0
Mechanical 15 15 3 0
Electrical 11 11 2 2
Total (Nos) 39 39 5 2
BASEMENT
Planned Actual
Part-2 100% 99.5%
Part-3 100% 98.4%
Part-1 100% 99.2%
Part-8 12% 63.9%
Part-5 11% 38.4%
Part-7 39% 17.9%
Part-6 0% 0.0%
Part-10 to 12 9% 2.7%
TOWER
Planned Actual
GF 100% 100%
1st Floor 100% 100%
2nd Floor 100% 100%
3rd Floor 100% 100%
4th Floor 100% 100%
5th Floor 35% 100%
6th Floor 0% 7%
WINGS
Planned Actual
Part-1 100% 95%
Part 5 0% 4%
Part 10 0% 0%
Part-3 87% 93%
Part 8 0% 18%
Part 12 0% 0%
SPI Trend
21-May-23 0.82
28-May-23 0.83
NCR
Total
Closed
Open
Manpower
Planned
Actual
Schedule %
95%
95%
37%
42%
6%
0.62%
7%
11%
CURRENT WEEK SD
Under
Revised C&D Review Discipline Total Dwgs
NCR
23
16
7
Manpower
650
844
Time Wise Time Wise
Time
Performance % Weightage
% Actual % Planned
Complete Complete
0.00% 2.00% 0.00% 0.00%
1.16% 2.00% 0.02% 0.21%
84.94% 10.00% 8.49% 9.17%
40.11% 46.00% 18.45% 16.97%
10.51% 3.00% 0.32% 0.20%
0.00% 1.00% 0.00% 0.00%
0.00% 1.00% 0.00% 0.00%
23.81% 1.00% 0.24% 0.41%
0.00% 2.00% 0.00% 0.00%
0.00% 10.00% 0.00% 0.13%
0.00% 4.00% 0.00% 0.00%
0.00% 2.00% 0.00% 0.00%
1.04% 8.00% 0.08% 0.84%
0.24% 8.00% 0.02% 0.22%
Actual (Time) 27.62% 28.14%
Planned (Time) 40.26%
PREVIOUS WEEK
Approved Revised Under
Planned Submitted A&B C&D Review
1041 551 219 34 298
1001 1029 924 49 56
611 397 253 28 116
1009 411 295 61 55
3662 2388 1691 172 525
83% 54% 39% 4% 12%
PREVIOUS WEEK
Planned Submitted Approved Revised Under
A&B C&D Review
8 1 0 0 1
12 10 4 4 2
10 9 8 0 1
30 20 12 4 4
14% 9% 5% 2% 2%
LONG LEAD ITEMS - PROCUREMENT STATUS الموقف التفصيلي للمواد طويلة األجل لمشروع برج اإلدارة العامة 28-May-23
Pre-Qualification طلبات التأهيل Technical Submission تقديم المواد PO Issue أمر الشراء Delivery التوريد
Payment Manufacturing
Invoicing
Status Start Date
Planned Date First Sub Last Sub Code Planned Date First Sub Last Sub Code Planned Date Actual Date Planned Date Remarks
S# Architectural
1 AC Panel for Shell 09-Mar-23 25-Aug-22 11-Dec-22 B 30-May-23 17-Jun-23 8-Nov-23
3 Curtain Wall Glazed System for Wings 09-Mar-23 25-Aug-22 11-Dec-22 B 30-May-23 17-Jun-23 8-Nov-23
4 Curtain Wall Glazed System for Tower 09-Mar-23 8-May-22 18-May-22 P 04-Jun-23 15-Jul-23 1-Dec-23
Mechanical
14 Submersible Pump 24-Dec-22 3-Jul-22 7-Jul-22 B 24-Dec-22 30-Jun-22 7-Jul-22 B 02-Sep-23 29-Feb-24 PO issue in 23 May 23
18 Air Separator 24-Dec-22 1-Nov-22 9-Oct-22 B 19-Jun-23 12-Sep-22 12-Sep-22 C 03-Oct-23 31-Mar-24
Related to item at Sr 18
19 Expansion Tank 14-Mar-23 1-Nov-22 9-Oct-22 B 19-Jun-23 14-Sep-22 14-Sep-22 C 03-Oct-23 31-Mar-24
22 Water Supply (Cu Pipes) 22-Dec-22 10-Apr-22 17-Apr-22 B 22-Dec-22 30-Jul-22 8-Nov-22 B 21-Jan-23 21-Mar-23
23 Chiller Units 24-Dec-22 10-May-22 13-Feb-22 B 24-Dec-22 13-Sep-22 13-Feb-23 B 03-Aug-23 30-Mar-24
24 Air Handling Units 05-Jan-23 10-May-22 12-Mar-23 B 05-Jan-23 14-Sep-22 6-May-23 P 03-Aug-23 30-Mar-24
25 Fan Coil Unit 24-Dec-22 10-May-22 B 24-Dec-22 13-Sep-22 11-May-23 P 29-Apr-23 26-Oct-23
28 Elevators 15-Dec-22 10-Apr-22 16-May-22 B 15-Dec-22 30-Oct-22 25-Jan-23 B 06-Feb-23 4-Dec-23 PO waiting Arch. Approval
Electrical
29 PV Solar System 15-Apr-23 2-Nov-22 C 04-Jun-23 01-Aug-23 31-Jul-24
31 Panel Boards 01-Mar-23 14-Aug-22 23-Aug-22 B 01-Mar-23 1-Feb-23 6-Mar-23 B 31-Jan-24 30-Jun-24
Related to item at Sr 18
32 MCC Panels 01-Mar-23 14-Aug-22 23-Aug-22 B 01-Mar-23 1-Feb-23 6-Mar-23 B 31-Jan-24 30-Jun-24
33 Generator 24-Dec-22 13-Sep-22 21-Sep-22 B 24-Dec-22 5-Nov-22 13-Mar-23 B 14-Feb-23 15-May-23 7-Aug-24
34 UPS System 01-Jan-23 19-Nov-22 9-Feb-23 B 01-Jan-23 22-Nov-22 9-Feb-23 B 28-Jan-24 31-Jul-24
35 ATS 15-Dec-22 17-Sep-22 27-Sep-22 B 15-Dec-22 3-Nov-22 5-Feb-23 B 04-May-23 3-Oct-23 PO issue in 30 May 2023
37 Ring Main Unit 24-Dec-22 21-May-22 1-Jun-22 B 24-Dec-22 9-Aug-22 30-Oct-22 B 30-Aug-23 29-Aug-24
38 Switch Board and ACB 01-Feb-23 14-Aug-22 23-Aug-22 B 01-Feb-23 1-Feb-23 6-Mar-23 B 31-Jan-24 30-Jun-24