You are on page 1of 4

"Breach of Contract" under FIDIC

Conditions of Contract for Civil


Engineering Construction
Mao Yihua Li Qingcheng
Institute of Construction Management Institute of Construction Management
Zhejiang University Zhejiang University
HangZhou,China HangZhou,China
zjumyh@163.com leafliqing@hotmail.com

Abstract—With the development of theory and practice of the conditions. They have the introduction of the specific conditions of
international project claim management, the contractor carrying the Red Book’s(the fourth edition in 1996)additional provisions,
out the contract claims is no longer based solely on the contract namely the substitute of the clause 67, DAB (Dispute Adjudication
agreement, but rather towards the combination of contractual Board) procedures. In this clause it declares the DAB is made up of
and legal trends. In FIDIC Conditions of Contract for Civil an arbitrator. The original commencement date was December 14,
Engineering Construction (Red Book, 1987 edition), there has a 2002 while the completion date was May 13, 2005.
more comprehensive description and requirements of the rights On January 21, 2008 the contractor submitted to the DAB NO.01
of the employer, engineer and the contractor. So the specific acts controversial documents requesting for arbitration. In the documents
of the parties involved the contract may result in "Breach of the contractor pointed out that the Breach of Contract by the
Contract" and trigger claims of time and cost. In this paper, Employer results in the time at large since May 13, 2005. The breach
according to a further analysis of a series of claim cases based on of the contract of the employer is as follows:
the Red Book we have studied the background of the contractual First, were the employer’s contract counterwork, including
and legal of "Breach of Contract" in depth. instructed extra and additional works and/or breach of contract by the
employer. And the employer didn’t not give the contractor a
Key words—FIDIC conditions of contract for civil engineering corresponding extension of the time;
construction; Contract Management; Breach of Contract Secondly, during the performance of the contract the employer
interfered the certification process to prevent the Engineer from
proper administration of the Contract so that the engineer was forced
Ⅰ. INTRODUCTION to breach of contract against the contractor.
In the performance of international project contract, the employer, The contractor suggested that the work was delayed because of
engineer and contractor perform their rights and obligations under "abnormal weather conditions", "employers failed to provide timely
the conditions of the contract to ensure the smooth implementation of the access to the site", "design changes (an additional layer of
the contract and the project completed on time, quality and quantity. asphalt)" and "local residents riots on site ".Theses were all the
The responsibilities and obligations of the parties are conferred by employer’s risks. The employer should be charged for these delays
the applicable contract document and laws. For example, engineer in and give the contractor an extention so that the contractor can
the "Red Book" playing a role of designer, supervisor, the certificate reasonably arrange the resources allocation and construction.
issuer and arbiter. Therefore, he will design the work during the However, as at the end of the contract the contractor had not received
design and construction phases. Under the "Red Book" the employer the approval to extend the time of the work.
also has the duty to transfer the site and make payments to the In the reply to the contractor’s claim document on February 25,
contractor. The contractor has the duty to finish the works in the 2008, the employer refused to endorse the breach of contract. He
completing time. thought that the engineer had made it clear on October 31, 2007 that
The responsibilities of employer, engineer and contractor are time “is and has been, at large since 03 December 2006 ".And this
very complex in practice, especially under the combination of had not been approved by the employer so it was not conformity with
conditions of contract and applicable laws. The violation of the the contract. On the claims and additional work instructions the
conditions of the contract and the applicable laws may result in employer identified to give the EOT to April 13, 2007 and asked the
"Breach of Contract", which raises the claim of time or/and cost. contractor to pay 5000 U.S. dollars per day as liquidated damages
Therefore, the analysis of the responsibilities and obligations under from the April 13, 2007 to February 2008.
the Red Book and the applicable laws as well as the conditions of the In the DAB's decision the arbitrator pointed out that in dealing
"Breach of Contract" and the following-up effects is necessary for with the disputes it needed to consider three issues:
z
the parties to perform the contract better. whether the employer and engineer have given EOT
under the contract;
. CASE STUDY
A Chinese international contractor gained a 112km-long highway z whether the provisions of the original contract period
project in an Africa country. The fund is from the KFW automatically lapse;
z
Bankengruppe. The employer is the country's Ministry of whether the engineer was interference by the employer
Communication. The engineer is the joint venture of a German
when he extended the time of the work- just as
international consulting company and an African consulting
company. The conditions of the contract are the FIDIC Conditions of
"blocking principle";
Contract for Civil Engineering Construction (Red Book, 1987 edition) z whether the employer’s decision led to the breach of
in 1992 revised edition, accompanied by the special revised contract.

978-1-4244-5326-9/10/$26.00 ©2010 IEEE


In accordance with special conditions of the contract, prior to z One party’s breach of contract;
z
the granting of any EOT the engineer should gain the approval from
the employer. Although in the letter the engineer had said the One party refuses to perform the contract;
contractor should be entitled to receive EOT, the letter was only z One party fails to perform the contract on time.
preparation and assistance before amicable settlement, not the formal
EOT. It is noteworthy that not all breach of contract can cause the
Besides, the arbitrator pointed out in the detailed description that, invalidation of the contract and need to turn to legal processing.
z According to the Red Book the employer had the According to the severity degree of breach of contract the action can
responsibility to provide the access to the site and if he be divided into two kinds, material breach and immaterial breach.
failed he would cause breach of contract. Thus the z If is the immaterial breach the usual practice adopted are:
employer should give the EOT. ignores the existence of the breach of contract or
forgives the defects and continues to perform the
z According to the Red Book the employers had the contract as usual;
responsibility not to interfere the contractor’s work
otherwise it would cause the breach of contract and z Points out the defects and let other party to remedy the
should give the contractor EOT; defects;

z There were not any clauses in the conditions that the z Refuses to make any payments until the charged party
employer had the right of retroactive adjustment of the remedy the defects;
contractual completion date and receiving liquidated z Responsible party should be deducted relative
damages cost; payments after remedying the defects.
z According to the clause 1.5 if the engineer want to If it is the material breach that one party should make claims
extend the time of the contract he should be granted by according the legal process or contract claim procedure, especially
the employer, so amicable settlement was not a reason after the failure of informal negotiation. If the amount is small the
for the employer to give the contractor an EOT in two parties can turn to the small claims court, negotiation, mediation,
and half years .This was an unreasonable delay caused conciliation or arbitration.
by the employers.
z
C. Damages payments under the breach of contract
The employer’s unreasonable delay made the engineer
In accordance with the law, if one party breaches of contract then
not give the approve of EOT on time, resulting in the the other party has the right to seek compensation under the contract.
contractor not clear their responsibility of completing The main payment kinds include damages, specific performance,
the work on time through reasonably arranging the cancellation and restitution.
resources allocation. 1)Damages
Based on these reasons the arbitrator made the final decision: The most common breach of contract damages are as follows:
z Employer's actions were consistent with the principle a) Compensatory damages:The purpose is used to make
of prevention and breach of contract; the non-breaching party to revert to the default state
when an incident takes place.
z Employer's actions resulted in engineers’ failing of
meeting its obligations, giving the EOT on time, also b) Punitive damages: It aims at a party for breach of
result in engineer being forced to breach of contract; contract against default penalties to compensate the
injured party.
z Employer’s breach of contract led to time at large;
c) Nominal damages: Usually the breach of contract
z Employer didn’t not have the right to ask for liquidated doesn’t cause the loss while it is necessary let the party
damages; at fault know it.
According to the contract the contractor only have the d) Liquidated damages: The liquidated damages are
responsibilities to complete the work within a reasonable time.
agreed in the contract in advance. The amount is
depended on the reasonable estimate.
THE CONTRACTUAL AND LEGAL ANALYSIS OF THE BREACH 2) Specific Performance
OF CONTRACT If the compensation can not fully compensate for the loss in legal
way, then the non-breaching party may seek an alternative method,
A. Concept of the "breach of contract" specific performance. Usually it rarely occurs but just only under the
"Breach of Contract" refers to breaking the contract or not circumstances that the compensation is not sufficient to restore the
obeying the contract. From a legal point of view, it means that one non-breaching party to the default state. For example, the service
party to the contract fails to fulfill contractual obligations and there is provided by a party of breaching is rare or can not be replaced and
no valid legal grounds for exemption, which should be undertake the compensation paid is unable to meet the needs of the other party.
corresponding obligations. Also it can’t achieve to compliance with the follow-up procedures,
the non-breaching party has to rely on the breaching party to
B. Several kinds of breach of contract continue to perform the contract. In this case, the non-breaching
Breach of contract are as follows: party may seek to the court to make the other party to fulfill a
z One party’s action makes the other party can not specific performance in accordance with instructions.
perform the contract; 3)Cancellation and Restitution
The non-breaching party may cancel the contract and ask the 39,40,41,42,44,45,46,48,49,50,51,52,53,54,56,57,58,59,60,62,63,64,
other party to return of profits (profit may not be able to restore the 65,67,68,69,70.
breaching party to the previous state, but this trend is reflected in the
legal connotation: one party can not benefits because of its own fault C. The contractor's obligations
and make the other party damaged). Restitution means that the The contractor's obligations under Red Book include:
z
breaching party to restore the state while cancellation means that one
party declares that the contract is invalid and all parties are cleaned To construction the work in the time for completion
the slate. and finish the works on time;
z To use materials, equipments and technology in
. CLAUSES OF RESPONSIBILITIES AND OBLIGATIONS UNDER accordance with the contract requirements and
RED BOOK instructions of the engineers;
z To provide guarantees, security and insurance for the
A. The employer’s obligations
work in the time for completion;
The employer's general obligations under FIDIC conditions of
contract for civil engineering contraction are as follows: z To provide required information and notification of
z Specifies the various elements of the project, such as performance and completion and to warn the
site as well as project-related personnel; employers when the issue increasing the cost or
z The appointment of a contract management engineer; delaying the time of completion may occur;
z
z To give the contractor the possession of the access to To perform some routine management and other
site; functions to finish the work.

z
With the obligations of relevant clauses of the contractor have
To issue information, instructions, approvals and
clauses1,3,4,6,7,8,9,10,11,12,14,21,23,24,25,26,27,28,29,30,31,33,3
notices when necessary; 4,35,36,37,38,39,40,41,42,44,45,46,48,49,50,52,53,56,57,58,59,60,6
z To avoid any acts that might interfere with the works; 3,65 , 67,68,69,70.

z To provide materials and the implementation of the . DAMAGE PAYMENTS UNDER THE BREACH OF CONTRACT
work;
z
A. The contractor’s damages under breach of contract
To nominate the specialist sub-contractors and
suppliers when necessary As stated in part IV, the obligations of the contractor has a detailed
description in Red Book. Failure to fulfill the contractual obligations
z To make payments in full and on time. will result in the contractor’s breach of contract. The typical breach
of contract has a lot during the performance of the contract, such as
With the obligations of the relevant clauses of the employers
the non-authorized subcontractor, failure to pay the insurance fees,
have
give notice, provide reports or statements timely and amend the
clauses1,2,6,10,11,19,21,22,25,26,30,31,42,51,59,60,63,65,67,71.
schedule, etc.
When the contractor fails to finish the work because of its own
B. Engineer's obligations fault, the standard measure of the loss is the gap of the contract price
Red Book follow the introduction of the traditional method as in
and the actual cost of work. Here the actual cost should consider: (1)
the field of civil engineering consultation. The engineer’s major
The employers should finish the work in compliance with the
obligations include:
original standard; (2) The employer should finish the work in a
z
reasonable manner; (3) the employer should finish the work in the
To finish technically the design of the concept earliest reasonable opportunity. At this point the employer’s damages
proposed by the sponsor; formula should be as follows:
z The preparation of a total set of tender documents and damages=the actual cost to finish the work-contract price + the
attract capable contractors to bid at competitive prices; amount paid to the contractor of breach of contract-the actual cost
make recommendations to the employers on the the contractor spends in finishing the work.
For the defective works (ie. construction does not meet the
analysis of tenders and selection of contractors;
contract’s requirements) assessment of damages is usually consider
z To supervise and inspect the contractor of the work and the following three ways:
ensure that it meets to the design requirements; contract z Restoration costs;
z
management; The gap between the actual cost to finish the works and
z To deal with the unexpected incidents, issue of the contract price;
z
certificates and adjudication of disputes. The work’s value damage because of the contractor ‘s
In the first and second above, the engineer's plays the role of breach of contract.
architect; in (3), the engineer's role is as a supervisor and employers
In the general engineering contract, the delay damages are usually
agents; in (4) above, the engineer's role is as a manager, certificate
agreed in the contract. The way often depends on the type of project.
promulgator or the adjudicator.
If the project is a commercial building such as factories or shops then
With the obligations of relevant clauses of the engineer have
the profit will be considered while if they are the general public
clauses
works or other non-profit buildings the profit will not be considered.
1,2,4,5,6,7,8,10,12,13,14,15,16,17,18,19,20,25,27,30,31,33,36,37,38,
B. The damages under the employer’s breach of contract
The measure of damages to the contractor will not have
theoretical difficulties under the employer’s breach of contract and it
usually does not produce indirect loss. Obviously the contractor’s
aim to accept the work is to gain profit. So when the contractor can
not gain the payment under the employer’s breach of contract then
the profit is the only factor will be considered to measure the
contractor’s lose. The following two conditions will be considered:
z As the employer's breach of contract leading to the
termination of, or have simply failed to work. In this
case, the contractor has been deprived of the right to
profit through perform the contract;
z As the employer's breach of contract led the contractor
to pay more to finish the work, therefore he gain less
profit.
The two types are often referred to as “total" or "partial"
prevention. According to Robinson charged of Harman Principle, the
total prevention causes the contract can not be continued so the
contractor is entitled to gain the payment of the finished works and
another sum to compensate for the remaining works’ profit. For
partial prevention, the main method of measuring the contractor’s
damages is the additional costs arose when the contractor perform
the contract.
When the employer breaches of the contract the contractor is
entitled to compensation of prime cost, site overheads, plant
disturbance and loss of productivity. In addition, claims on the same
principle with the lower efficiency of the claim are acceleration
claims.

CONCLUSION
The employer, engineer and contractor’s responsibilities under the
Red Book are connected with a specific performance environment.
The breach of contract is also not a single emergence, often it is
because of multiple reasons. The impact of post-breach of contract
also has a number of situations. We need to do a lot to make the
reasons and responsibilities clear. This is the key to solve the
disputes. The breach of contract’s contractual and legal connotations
is very complex so the research on it will be meaningful in the field
of international claim management and settlement of legal disputes.

REFERENCES
[1] Nael G, Bunni, The FIDIC Forms of Contract, Third Edition,
Blackwell Publishing, 2005
[2] FIDIC, Conditions of Contract for Civil Engineering
Construction Application Guide (1988 revised edition), Beijing
Aviation Industry Press, 1998
[3] FIDIC, Conditions of Contract for Construction, 1998
[4] Chiu Chuang, International Engineering Principles and Practices
of the contract, Beijing, China Building Industry Press, 2002

You might also like