Professional Documents
Culture Documents
Stephen Ressler
LEADERSHIP
President & CEO. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . PAUL SUIJK
Chief Financial Officer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . BRUCE G. WILLIS
Chief Marketing Officer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CALE PRITCHETT
SVP, Marketing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . JOSEPH PECKL
SVP, Content Development. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . JASON SMIGEL
VP, Content Production. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . KEVIN BARNHILL
VP, Marketing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . EMILY COOPER
VP, Customer Engagement. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . KONSTANTINE GELFOND
VP, Technology Services. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . MARK LEONARD
VP, Content Strategy . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . KEVIN MANZEL
VP, General Counsel. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DEBRA STORMS
VP, People . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . AUDREY WILLIAMS
Sr. Director, Content Operations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . GAIL GLEESON
Director, Talent Acquisition. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . WILLIAM SCHMIDT
Director, Creative. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OCTAVIA VANNALL
PRODUCTION
Studio Operations Manager . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . JIM M. ALLEN
Video Production Director. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ROBERTO DE MORAES
Technical Engineering Manager . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SAL RODRIGUEZ
Quality Assurance Supervisor. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . JAMIE MCCOMBER
Sr. Post-Production Manager. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . PETER DWYER
Sr. Manager of Production. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . RIMA KHALEK
Executive Producer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . JAY TATE
Sr. Producer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . JAMES BLANDFORD
Content Developer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . BRANDON HOPKINS
Assistant Content Developer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . EZRA COOPER
Image Rights Analyst. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . KATE MANKOWSKI
Post-Production Manager . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OWEN YOUNG
Editor. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ANDREW VOLPE
Audio Engineer. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . GORDON HALL IV
Camera Operators. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . JUSTIN THOMAS
DANIEL BLOOM
Production Assistant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . LAKE MANNIKKO
i
Table of Contents
ii
Table of Contents
iii
Table of Contents
iv
Scope
1
Scope
` inadequate maintenance.
The first 21 lessons address engineering failures that are primarily structural
in nature. Many involve traditional structures like buildings, bridges, towers,
and dams. But you will also explore the failures of aircraft, ships, and a huge
storage tank filled with molasses—all of which are structures in the sense that
they must safely carry loads to fulfill their respective functions.
Then, in the final five lessons, you will consider a series of fascinating
cases that are not structural in nature, but rather involve mechanical,
electrical, nuclear, and systemic failures—often exacerbated by the flawed
organizational dynamics of corporations or governmental bodies.
Many of the case studies covered in this course are quite familiar. The collapse
of the Tacoma Narrows Bridge (“Galloping Gertie”), the explosion of the space
shuttle Challenger, the nuclear meltdown at Chernobyl, and the failure of the
New Orleans hurricane protection system during Hurricane Katrina are prime
examples. Others—such as the Dee Bridge disaster, the Kemper Arena roof
collapse, and the Teton Dam failure—are less familiar but equally important.
In each of these cases, engineers learned from failure—and you will too!
2
1
Learning from
Failure: Three
Vignettes
This course examines a series of historical
case studies, each involving an engineering
failure that’s been instrumental in advancing
technological progress. In each case, the
engineering design, relevant scientific
principles, causes of failure, and impacts on
future engineering practice will be explored.
The human dimension of each case—the
historical context, key players’ decisions,
and the human cost of these tragic events—
will also be considered. Overall, you’ll learn
about engineering failures caused by flawed
design concepts, unanticipated structural
responses, and inadequate maintenance,
among other aspects.
3
1. Learning from Failure: Three Vignettes
Hurricane Katrina
On August 28, 2005, in New Orleans, Louisiana, Hurricane Katrina crossed
the Gulf of Mexico, attaining Category 5 strength. The next morning,
Katrina made landfall about 55 miles southeast of New Orleans. It had
weakened to Category 3 (with sustained winds of 125 mph). Katrina’s eye
would pass within 20 miles of New Orleans before continuing inland.
New Orleans had been preparing for this since Hurricane Betsy in 1965.
Congress had passed flood control legislation directing the US Army Corps
of Engineers to develop a comprehensive hurricane protection system for the
city and surrounding region. New Orleans received special attention because
of its vulnerable location on low-lying ground, sandwiched between a river
and a lake and protected only by earth embankments (called levees). The new
hurricane protection system would consist of floodwalls and enhanced levees,
forming a continuous barrier. It would line the shore of Lake Pontchartrain
and the canals extending from the lake into the city. This system was only
90% complete by August 2005 but had still survived near misses by major
hurricanes in 1974, 1985, and 1992.
But as Katrina’s winds swept across Lakes Borgne and Pontchartrain, they
drove a massive storm surge toward the city. Several levees along the Gulf
Intracoastal Waterway were overtopped and washed away. As the surge
4
1. Learning from Failure: Three Vignettes
reached its peak, floodwalls along the Industrial Canal, 17th Street Canal,
and London Avenue Canal toppled. Ultimately, the hurricane protection
system was breached at more than 50 locations.
For example, along the London Avenue Canal, the floodwall comprised
sheet piling linked together at the edges, driven into the ground along a
levee, and capped with a wall made of reinforced concrete. The canal was
built on a thin layer of local marsh soil, underlain by a thick layer of sand. As
the storm surge started building, the pressure caused by the water’s weight
caused seepage into the sand, beneath the sheet piling, and then back up
to the surface on the downstream side. The water lifted the soil particles
upward, counterbalancing the soil’s weight. Thus, the forces of internal
friction holding the soil particles together dropped to zero, and liquefaction
occurred. As the floodwall was supported only at its base, when the soil on its
downstream side washed away, the entire structure was toppled by the wall of
water behind it. With Lake Pontchartrain pouring into New Orleans through
many such breaches, 80% of the city was flooded.
5
1. Learning from Failure: Three Vignettes
At the upper beam, the only way to get the nut to its required position was
to thread the entire lower portion of the rod 30 feet into the actual structure.
When this design was communicated to the steel fabricator, he recognized
its impracticality and proposed an alternative. Rather than using full-length
continuous hanger rods, this modified configuration used pairs of half-length
rods—one running from the roof structure to the upper beam and a second
running from the upper to the lower beam. Only a few inches at the ends of
each rod had to be threaded.
But this revised configuration was also structurally problematic. Gravity load
refers to any load caused by weight. Here, the gravity loads were the weights
of the walkway and the people standing on it. In the alternative configuration,
the upper beam carried both the fourth- and second-floor loads. The lower
walkway’s weight was transmitted through the lower hanger rod and the
outer segment of the upper beam to the upper hanger rod and then to the roof
structure. Subjected to twice as much load as they were designed to carry,
the upper rods pulled through the ends of the upper beams, causing both
walkways to break free and fall.
The train—a 30-ton locomotive pulling its tender and five carriages—crossed
the first two spans of the Dee Bridge without incident. But as it reached the
middle of the third span, the driver felt the machine sinking beneath his feet.
He applied full steam, and the locomotive barely managed to reach terra
firma as the bridge collapsed behind him. The passenger carriages broke free
and plunged to the river below. In total, 5 people died, and the remaining 19
were injured.
The most likely cause of the collapse was fatigue. Fatigue failures originate at
defects in metal. In structures of cast iron from the mid-19th century, such
flaws resulted from the crude fabrication process. Say there is a small cut on the
6
1. Learning from Failure: Three Vignettes
bottom surface of a cast-iron girder. Repetitive loading causes that small defect
to gradually grow into a crack. The crack enlarges with each subsequent loading
until it reaches a critical length, at which point the girder fractures suddenly.
7
1. Learning from Failure: Three Vignettes
` PHASE 4: The engineer chooses the material, size, and shape of the
structural members, connections, and foundation elements such that they’re
strong enough to resist the calculated internal forces. For example, the
structural engineer who designed the Hyatt walkways determined the hangers
could be fabricated from 1.25-inch-diameter steel rods, each of which could
carry about 74,000 pounds of internal force before failing in tension.
The internal force at which a structural element fails is called its strength.
The strength of these rods was significantly larger than the actual internal
force they were expected to experience. The ratio between these two
numbers is the safety factor—the failure condition divided by the actual
condition. It represents the extent to which a design can accommodate
uncertainties. The safety factor must always be greater than 1; for the
Hyatt Regency hanger rods, it was 1.8, corresponding to an 80% margin
of error. This is a respectable safety level, but unfortunately, the weak
link was the steel box beams. For these beams, the safety factor was never
checked because of communication breakdowns and management issues.
This is where the Hyatt Regency walkway design went awry. The steel
fabricator determined that the engineer’s concept for the fourth-floor
rod-to-beam connection was impractical. He changed the connection
and inadvertently doubled the internal force applied to the walkway’s
supporting beams, radically altering the structural response. Then, the
engineer approved the fabricator’s change without scrutinizing it.
` PHASE 6: The structure is operated and maintained. One year into this
phase, the Hyatt Regency walkways collapsed under a routine loading that
was substantially less than the structure was designed to carry due to a
flawed steel connection and flawed organizational dynamics.
8
1. Learning from Failure: Three Vignettes
Human Influence
Although the engineering process relies on math and science, most
engineering designs are at least as strongly influenced by social, political, and
economic considerations.
` The flawed New Orleans floodwall design was strongly influenced by local
residents’ opposition to a more effective but intrusive design solution.
` Stephenson’s Dee Bridge design would have been a traditional brick arch
structure if local navigation interests hadn’t protested that it would impede
vessel movement on the River Dee.
9
1. Learning from Failure: Three Vignettes
Reading
Akesson, Understanding Bridge Collapses.
Delatte, Beyond Failure.
Levy and Salvadori, Why Buildings Fall Down.
Petroski, Design Paradigms.
———, To Engineer Is Human.
———, To Forgive Design.
Wearne, Collapse.
10
2
Flawed Design
Concept: The
Dee Bridge
The Dee Bridge disaster of 1847 was one
of the most serious railroad accidents to
have occurred during the era when railroad
technology was only just coming of age.
This lesson will take a deep dive into the
disaster, for which the primary cause was a
flawed design concept. Here, you will learn
about the collapse mechanism and causes of
this engineering failure and also explore the
lessons learned and implemented for future
engineering practice.
11
2. Flawed Design Concept: The Dee Bridge
12
2. Flawed Design Concept: The Dee Bridge
some of the most iconic locomotives of the era, including the famous Rocket.
With the acquisition of Stephenson’s Rocket, the Liverpool and Manchester
Railway went into operation in 1830 as the world’s first true intercity
passenger railroad.
Over the next two decades, small private railway companies established
independent local rail links across Great Britain. Eventually, these links
coalesced into a national rail network. This railway mania was rapid,
decentralized, and largely unregulated. Perhaps inevitably, accidents
happened with increasing frequency and severity. In response, Parliament
passed the Railway Regulation Act of 1840, which provided for railroad
safety inspections and established a new agency—Her Majesty’s Railway
Inspectorate—charged with investigating accidents and making
recommendations to prevent future occurrences.
The Dee Bridge disaster was among the first major accident investigations
performed by the inspectorate. Captain John Lintorn Simmons conducted
the inquiry at the bridge site, examining the wreckage and documenting it
with detailed drawings. He performed a series of physical tests by having
locomotives drive onto the surviving spans and measuring their structural
response. He interviewed eyewitnesses, survivors, and the engineer who
designed the bridge and documented their testimony. Based on the
information he collected, Simmons reconstructed the sequence of events and
wrote a final report identifying the probable causes of the failure.
13
2. Flawed Design Concept: The Dee Bridge
Both beam types use the same amount of material, but the I shape is nine
times stronger than the rectangular shape. The Dee Bridge girder was
I-shaped, but the cross section was asymmetrical, with the bottom flange
much larger than the top flange. Cast iron is about five times weaker in
tension than in compression. Thus, Stephenson designed this girder with its
bottom flange five times larger than its top flange. He wanted to distribute
the internal tension force over a larger area, reducing its intensity by a factor of
five to compensate for cast iron’s weakness in tension. In short, Stephenson’s
asymmetrical cross section was matched to cast iron’s asymmetrical properties
to optimize the girder’s load-carrying efficiency.
The profile of Stephenson’s Dee Bridge girder is also unusual. The iron
foundries of this era couldn’t cast a 100-foot-long structural element. Thus,
each girder was cast in three shorter segments, bolted end to end, and
strengthened with elaborate splices to provide continuity across the joints.
Similar curved castings were bolted to the ends of the girder to serve as
attachment points for a pair of chains, each composed of three main links
made from wrought iron. Each link comprised eight parallel elements called
eyebars, connected with heavy iron pins.
These eyebar chains served two purposes. Most importantly, they were
intended to strengthen the girder. At the time, cast-iron bridge girders had
been in use for less than a decade but had already demonstrated a tendency to
fail unpredictably after extended periods of trouble-free service—apparently
14
2. Flawed Design Concept: The Dee Bridge
The second purpose of the eyebar chains was to provide a mechanism for
eliminating the inevitable sag caused by the bridge’s weight. In a simplified
model, each eyebar chain is pinned to the outer ends of the girder. The inner
pins pass through oversized holes in the web and are connected to the girder
only by vertical bolts, which extend down through the lower flange and are
secured with nuts. When a load is added, the girder sags, which would be
problematic for trains crossing the bridge. However, tightening the two nuts
lifts the girder at the two points of attachment, eliminating the sag. The Dee
Bridge design used two vertical bolts at each connection.
Girder Fractures
Each bridge span comprised two girders, placed 12 feet apart and linked with
wrought-iron tie bars. Timber crossbeams were laid across the girders’ bottom
flanges, supporting a wooden deck. Three such spans were required to carry
one set of railroad tracks from abutment to abutment, and an identical set
of three spans constituted an essentially independent bridge for the second
railway line. Along each bridge, the main rails were supplemented by a pair of
guardrails designed to prevent trains from derailing. The guardrails restrained
the flanges on the train’s wheels from moving laterally in both directions.
During the two months between its completion and the initiation of
passenger service, the bridge was used extensively by trains carrying
construction materials to support ongoing work farther up the line. From
opening day onward, numerous trains crossed the bridge daily. On the
morning of May 24, 1847, six trains crossed without incident. Then, the
15
2. Flawed Design Concept: The Dee Bridge
Three days later, Captain Simmons began his investigation to identify the
causes of failure from the perspective of railway safety. A week later, a jury
trial was convened to determine responsibility for the five deaths. In his
testimony, Stephenson claimed the collapse must have been caused by the
train derailing and colliding with one of the girders. The jury rejected this
based on eyewitness testimony that the fracture had occurred while the train
was still on the rails—and because the guardrails included in the design
reduced the likelihood of derailment.
Hammer Blow
It’s important to distinguish between the collapse mechanism, or the physical
phenomenon that caused the problem, and the underlying causes of failure,
which typically involve human errors, omissions, or lack of knowledge during
the design process. Concerning the collapse mechanism, no one could make
a definitive determination, and the crucial physical evidence—the fractured
girder—wasn’t preserved. The only theory that can explain why the Dee
Bridge carried three 30-ton locomotives successfully in September 1846 and
then failed under the weight of a single 30-ton locomotive eight months
later is fatigue—a failure mode to which cast iron is particularly susceptible.
According to this theory, repeated train crossings caused a small defect in the
cast iron to grow into a crack, which elongated with each successive crossing
until it reached the critical length for a sudden catastrophic fracture.
was a reasonable estimate of the total static vehicular load. However, it failed
to consider the substantial additional dynamic loading associated with steam
locomotives—hammer blow.
However, with each turn of the unbalanced drive wheels, the upward and
downward acceleration of these counterweights causes cyclic vertical
forces—or hammer blow. The magnitude of these dynamic forces can
approach 20% of a locomotive’s static weight—meaning a 30-ton locomotive
might apply a peak loading of 36 tons to a bridge. Hammer blow also
contributes substantially to fatigue damage. Because the cyclic vertical force
is applied with each turn of the drive wheels, a locomotive crossing the Dee
Bridge would have applied four or five load cycles per span rather than one—
and each cycle would cause fatigue cracks to grow.
Remember that the safety factor is the failure condition divided by the
actual condition. Thus, with a failure load of 280 tons and (estimated)
actual loads comprising the bridge’s 90-ton weight plus a 90-ton vehicular
17
2. Flawed Design Concept: The Dee Bridge
load, the girders’ nominal safety factor was 1.6, providing a 60% margin
of error. Today, a safety factor of 1.6 might be minimally adequate in some
circumstances. For a cast-iron railroad bridge in the 1840s, it was certainly
too low.
Evidently, these three issues eroded much of the 60% margin of error
incorporated in the design, and fatigue damage claimed the rest. According
to Captain Simmons’s report, a safety factor of 3 was the norm for cast-iron
girders during this era. But this unofficial standard of practice didn’t account
for Stephenson’s inclusion of supplemental eyebar chains in the design, and
neither did Hodgkinson’s formula.
18
2. Flawed Design Concept: The Dee Bridge
To fulfill their purpose, the eyebar chains were supposed to stretch in tension,
but this inward movement of their attachment points caused them to go slack.
Consequently, they contributed little or nothing to the girders’ strength.
Lessons Learned
First, this case demonstrates that failure is a powerful stimulus for engineering
advancement. It took the Dee Bridge disaster to focus attention on the risk
of using cast-iron girders and to mobilize the political will and governmental
resources to deal with it.
19
2. Flawed Design Concept: The Dee Bridge
Reading
Gagg and Lewis, “The Rise and Fall of Cast Iron in Victorian Structures.”
Lewis and Gagg, “Aesthetics versus Function.”
Simmons and Walker, “Report to the Commissioners of Railways.”
Taylor, “Iron, Engineering and Architectural History in Crisis.”
20
3
Wind Loading:
The Tay Bridge
The engineering advances stimulated by
the Dee Bridge disaster engendered a new
spirit of confidence among British engineers.
This newfound confidence led to the design
of vastly more ambitious structures, and
that overconfidence then led to a disaster
of even greater proportions. This lesson will
consider wind loading and the Tay Bridge
collapse. This course has advanced to phase
2 of structural design with a case where the
engineer’s flawed estimation of loads resulted
in catastrophe.
21
3. Wind Loading: The Tay Bridge
The two-mile-long bridge carried one rail line; thus, the railway had instituted
a token system to manage two-way traffic. The driver of a northbound train
had to pick up a baton from a signal cabin located on the southern approach
to the bridge and deposit it at a cabin on the northern side after crossing.
No train could cross without the baton. Therefore, two trains traveling in
opposite directions could never occupy the bridge simultaneously.
That evening, signalman Thomas Barclay was on duty at the southern cabin
with his friend John Watt. At 7:13 pm, as the Edinburgh-to-Dundee train
came by, Barclay handed the baton to the driver. Watt was standing at the
window, watching the train. As it moved onto the bridge, he saw sparks flying
from its iron wheels—indicating the wind was pushing the train sideways
with such force that its wheel flanges were grinding against the iron rails’
22
3. Wind Loading: The Tay Bridge
sides. About three minutes later, as the train approached the middle of the
bridge, Watt saw a bright flash of light—and then nothing. Watt told Barclay
that the train seemed to have derailed. When the men went to the shoreline,
they saw that a 3,000-foot section of the bridge had vanished.
23
3. Wind Loading: The Tay Bridge
of a solid girder, and the lattice corresponds to the girder’s web. These two
structural elements carry load in essentially the same way. When subjected
to a transverse load, they bend, resulting in compression on top, tension on
the bottom, and shear in the lattice or web. However, the lattice girder carries
load more efficiently because the lattice uses less material than a solid web.
Bouch’s design concept for the Tay Bridge was to carry a single rail line across
the two-mile-wide estuary on 86 wrought-iron lattice girder spans supported
on masonry piers. For most spans, the rail line was mounted on top of the
girders, but for the longer spans crossing the estuary’s navigable channel, the
rails were supported on the girders’ bottom chords. The trains would pass
through the girders rather than above them. These spans—the high girders—
provided the required 88-foot overhead clearance for tall ships passing
beneath the bridge.
By 1871, Bouch’s design was complete, and the project commenced with
construction of the masonry piers, starting at the southern shore and working
northward. To build the foundations underwater, the key technology was an
iron enclosure called a caisson. Open on the top and bottom but otherwise
watertight, the caisson was prefabricated on shore, barged to its designated
position, and lowered to the riverbed. Temporary cylindrical segments were
bolted on top; thus, the upper rim would always extend above the water
level. Then, the water was pumped out, allowing workers to descend into the
caisson to excavate the soft sand and mud from the riverbed. As this soil was
removed, the caisson gradually sank until it reached bedrock. It was then
lined with brick and filled with concrete to create a firm foundation for the
pier. Finally, the temporary segments were removed, and the pier was built on
this foundation.
This process worked well for the first 14 piers. But in May 1873, as the 15th
caisson was being emplaced, the excavators found no bedrock but rather a
four-foot-thick stratum of conglomerate rock, below which was more sand
and mud. Bouch had to redesign the entire bridge. He decided to replace the
planned brick-and-concrete piers with lightweight iron towers so that the
bridge could be supported safely on that stratum of conglomerate.
24
3. Wind Loading: The Tay Bridge
Points of attachment for the iron towers were installed in the plinth by
drilling holes through the top two courses of stone and securing wedge-
shaped wrought-iron anchor bolts into these holes with concrete. These bolts
were used to secure six cast-iron baseplates, to which cast-iron columns were
attached. Each column segment was an 11-foot-tall pipe, with integrally cast
flanges and lugs at the upper and lower ends. Each lug was a projection with a
bolt hole to which additional structural elements could be fastened.
Each high girder comprised two main trusses, laterally connected with
transverse struts and diagonals. The railway was supported on closely spaced
fish-bellied beams. Mounted on top of the bottom chords, these beams
supported the wooden deck on which the railroad rails were mounted. Most
of the adjacent high-girder spans were connected with riveted iron plates to
increase their load-carrying efficiency.
Construction was completed in early 1878. The bridge was inspected and load
tested by the UK’s Board of Trade and placed into service in June. At that time,
North British Railway retained Bouch as maintenance manager for the bridge.
25
3. Wind Loading: The Tay Bridge
The Inquiry
After the disaster, the Board of Trade established a three-man court of
inquiry, which began on January 3, 1880. The court’s presiding officer
was Henry Rothery, a lawyer who also served as the UK’s Commissioner
of Wrecks, and the other two members were engineers—Colonel William
Yolland, Inspector of Railways, and William Barlow, president of the
Institution of Civil Engineers.
The physical evidence strongly indicated that the high girders fell because
their supporting piers had been toppled by the force
of the wind. Thus, the court examined Bouch’s
consideration of wind loading. In structural
engineering, a wind load is typically defined
as a pressure. For example, modern building
codes specify that structures built in
California must be able to withstand a wind
pressure of about 20 pounds per square foot
(psf), meaning a force of 20 pounds is applied
to every square foot of surfaces facing the wind.
This code-specified loading can vary widely
depending on geographic location.
26
3. Wind Loading: The Tay Bridge
wind loading. He explained that this was justified by guidance from the
Astronomer Royal of the UK, Sir George Airy. Bouch had consulted with
Airy in 1873, when designing the bridge across the Firth of Forth. Airy had
reported that Scotland’s localized wind pressure might exceed 40 psf over a
short distance; however, the average pressure over the 1,600-foot spans of the
proposed Firth of Forth suspension bridge could reasonably be estimated at
10 psf. Thus, Bouch concluded that wind loading could be ignored in his Tay
Bridge design. The court rejected this as a misapplication of Airy’s guidance
because the bridge’s individual spans were much shorter than 1,600 feet and
wouldn’t benefit from the averaging effect Airy had described. The court also
heard testimony that, at the time, engineers abroad were designing bridges for
wind loadings of 50–55 psf.
The court struggled with determining the actual wind pressure at the time of
the accident because methods for measuring wind pressure were still in their
infancy. The experts’ testimonies varied widely, with estimates ranging from
15 to 45 psf. Thus, the court asked Law to estimate how much wind pressure
the bridge should have been able to withstand if constructed exactly as Bouch
designed it.
Wind Pressure
Wind pressure is manifested primarily as a horizontal force. A truss is a
rigid framework composed of slender members connected at their ends and
arranged in interconnected triangles. When a truss is loaded, its members
experience either tension or compression. If wind loading causes the diagonals
to stretch, they must be in tension. If the wind blows in the opposite
direction, the diagonals shorten, and they must be in compression. Because
these diagonal bars are so slender, they buckle under a small compressive
force. An efficient solution involves adding a second set of slender diagonals
oriented in the opposite direction. Thus, regardless of which direction the
wind blows, one diagonal in each pair will always carry the load in tension,
while the other goes slack.
Law’s analysis of the wind pressure at which the Tay Bridge piers would
collapse considered two possible failure modes. A wind pressure of
approximately 64 psf acting on both the bridge and the passing train might
cause one of these diagonal members (or its connections) to fail, and a collapse
27
3. Wind Loading: The Tay Bridge
would ensue. Alternatively, the wind might cause the pier to overturn. The
wind pressure required to cause overturning depended on whether the anchor
bolts could prevent the column baseplates from lifting off the plinth. If not,
the wind pressure required to cause overturning was 33 psf. But if the anchor
bolts effectively prevented uplift, the pressure required to cause overturning
would be much higher—the diagonals would fail before overturning became
an issue.
Although the baseplates were secured with anchor bolts, they were not
sufficiently effective at restraining uplift. Law found that numerous anchor
bolts had pulled out of the plinth and that several overturned columns had
lifted the top two stone courses off the plinth as they toppled. In both cases,
the anchor bolts did little to prevent the pier from overturning. Thus, given
the numerous known anchor bolt failures, wind pressure ranging from 33 to
45 psf could easily have caused the bridge to collapse, even if the structure had
been built exactly as designed.
To cast a bolt hole into this lug, a temporary core was inserted into the mold
prior to casting. The molten iron flowed around the core in two streams that
joined together on the far side of the core to form the lug. If these two streams
didn’t join fully, a defect called a cold shut was created, and the lug’s strength
was compromised. The court found evidence of many cold shuts in the Tay
Bridge column lugs.
28
3. Wind Loading: The Tay Bridge
Moreover, the temporary core had a slightly conical shape to facilitate its
withdrawal from the mold, but this shape caused the bolt holes to be slightly
conical too. This was serious from the perspective of structural integrity.
When inserting the bolt into a hole, it fit snugly on one side—but on the
opposite side, there was a substantial gap between the bolt and hole because
of the hole’s conical shape. Thus, when the bolt was loaded by the structural
member to which it was attached, the bolt bore entirely on this narrow edge
on one side of the lug. This increased the intensity of internal force on the
lug—and greatly increased its susceptibility to failure. In laboratory tests of
columns salvaged from the Tay Bridge wreckage, many lugs failed at about
one-third of their expected strength, largely because of these conical bolt
holes. This weakness could have been remedied by drilling out the holes after
the columns were cast.
Final Report
Another contributor to the Tay Bridge collapse was the loosening of the
diagonal braces over time. The braces loosened partly because the conical
bolt holes deformed excessively under load but also because the mechanism
intended to keep these braces tight—a double-wedge connection—was
badly designed and poorly fabricated. As the braces loosened over time, the
resulting sidesway of the piers increased their susceptibility to overturning
and amplified the vibrations caused by locomotives crossing the bridge. These
vibrations surely contributed to fatigue damage in the critical cast-iron lugs,
accelerating their eventual fracture under load.
The court of inquiry described these and other probable causes of failure in its
final report to the Board of Trade. The report also hypothesized the sequence
of events leading to the collapse, as follows:
` Before the structure was placed into service, many of its cast-iron column
lugs were weakened by fabrication defects.
` These lugs had probably incurred further damage during previous windstorms.
` Over time, the loosening tie bars increased the piers’ lateral sway,
decreasing their stability.
29
3. Wind Loading: The Tay Bridge
` During the storm of December 28, gale-force winds acting on both the
structure and the train caused enough lug failures to fatally compromise
one pier’s lateral stability.
` As each lug failed, loss of the associated diagonal brace caused the adjacent
lugs to be overloaded, leading to the collapse of the pier and the two high-
girder spans it supported.
` The remaining high girders and piers were dragged down by the
interconnections between the spans.
The court members focused on the UK’s lack of common standards for wind
loading and recommended that the Board of Trade address this issue. But
Rothery, the lawyer, maintained that assigning blame was integral to the court’s
charge. Largely because of this judgment, Bouch was discredited, and his
contract to design a suspension bridge across the Firth of Forth was cancelled.
Bridges he had built previously were scrutinized, and several were condemned
and torn down. But Bouch’s Tay Bridge had stood long enough to demonstrate
its economic value to North British Railway. Thus, work began almost
immediately on a replacement—a double-track structure still in use today.
Lessons Learned
In engineering, details matter. Central to this disaster was a seemingly
minor single-bolt connection. This also illustrates the need for redundancy
in engineering design. A small, localized failure should never be allowed to
propagate into systemic collapse. Finally, this case demonstrates that after
a major failure, public perceptions often have a stronger influence than
technical considerations on the subsequent course of events.
30
3. Wind Loading: The Tay Bridge
Reading
Board of Trade, “Report of the Court of Inquiry.”
Lewis and Reynolds, “Forensic Engineering.”
Martin and MacLeod, “The Tay Rail Bridge Disaster Revisited.”
Petroski, Engineers of Dreams.
31
4
Rainwater
Loading:
Kemper Arena
Welcome to the second in a series of lessons
addressing engineering failures caused
primarily by inadequate estimation of loads—
the second phase of the structural design
process. In this case study, we’ll investigate
the influence of rain loading on the collapse
of the Kemper Arena roof. We will explore the
arena’s innovative design and then discover
how several disparate phenomena, some of
which were related to the design, combined
to lead to the roof collapse.
32
4. Rainwater Loading: Kemper Arena
33
4. Rainwater Loading: Kemper Arena
greater stability than a traditional planar truss and can be more structurally
efficient. When a planar truss is loaded, the top chord tends to buckle
sideways. This is why structural systems that use planar trusses typically
require two or more of them, interconnected with a bracing system that
prevents the top chord
from buckling. But in a
space truss, the three-
dimensional orientation
of the diagonals prevents
the top chord from
buckling laterally—no
supplemental bracing
needed.
Load Paths
Engineers conceptualize a complex structural system like this one in terms of
load paths, which represent the flow of internal forces through the system.
The principal load path for this structure originates with the weight of
accumulated snow or rainwater on the roof surface. The snow and rain loads
applied to this surface are directly supported by the roof slab. These loads,
combined with the slab’s weight, are supported by the bar joists, carrying load
in flexure (or bending). The joists transmit the associated internal forces to
the main trusses, which also carry load in flexure, up through the hangers in
34
4. Rainwater Loading: Kemper Arena
tension, and then out through the portal trusses to the supports and down
into the foundations. For the structure to carry load successfully, every link
in this chain must be strong enough to carry its internal forces with an
appropriate safety margin.
The hangers constitute an important link in this chain because they carry the
entire 1,500-ton roof plus the total weight of accumulated rain or snow on the
four-acre roof surface. With 42 hangers sharing this load nearly equally, the
internal tension force in each hanger is about 140,000 pounds. As the hangers
carry this tension force, they must also accommodate substantial horizontal
movements of the roof, caused by wind loading and the roof system’s thermal
expansion and contraction. In Kansas City, the average temperature difference
between January and July is about 70°F. This change causes the arena’s
concrete roof slab to change in length by about two inches.
more land surface, the corresponding increase in storm runoff will eventually
overwhelm and inundate a storm drainage system. A common preventive
technology is a stormwater detention pond—an earthen enclosure designed
to store such runoff temporarily and release it into the storm drainage system
at a controlled rate to prevent flooding.
The Kemper Arena designers recognized that the rainfall captured by the
building’s four-acre concrete roof would overwhelm the local storm drainage
system during intense storms unless they provided a means of temporarily
storing the runoff. Their ingenious solution was to use the roof itself. The arena
roof included drains designed to capture accumulating rainwater and channel it
through a five-inch-diameter pipe to the local storm drainage system.
To meet Kansas City’s building code requirements, the arena’s four-acre roof
should have had 55 such drains—but only 8 were provided in the design.
This was not a design error but rather an intentional means of stormwater
management. During an intense storm, the limited capacity of the eight
roof drains would prevent the local storm drainage system from being
overwhelmed and cause the excess runoff to accumulate on the roof. After the
storm subsided, this accumulated rainwater would slowly drain away. Thus,
the arena roof would function as a de facto stormwater detention pond.
The inherent danger here is that an extreme storm could cause so much
rainwater accumulation that its weight might overload the structure. To
prevent overloading, the designers provided additional stormwater outlets
called scuppers, which are openings in the parapet wall along the roof
perimeter. On the arena roof, the scuppers were positioned two inches above
the roof surface, ensuring that the water depth could never exceed two inches.
Logically, it could never be overloaded. Yet, during the storm of June 4, 1979,
the center section of the arena roof was overloaded by accumulated rainwater.
How could this have happened? Responsibility for the collapse was decided
through the adjudication of civil lawsuits in the courts. In preparation for
these suits, all involved parties hired experts to investigate the collapse on
their behalf. These consultants—each representing a particular organization’s
interest—tended to focus on different aspects of the failure and thus reached
somewhat different conclusions.
36
4. Rainwater Loading: Kemper Arena
The second factor contributing to the collapse was wind. As the storm
raged, the 70-mph wind drove an ever-growing pool of rainwater toward
the southern end of the roof. The result was a storm surge. At the time of
the collapse, the depth of water at the downwind roof drains was more than
eight inches—a fourfold increase over the two-inch depth limitation that
should have been enforced by the scuppers. Astonishingly, this increase in
rain loading didn’t cause the collapse by itself because the safety factor used
in the structural design was large enough to accommodate the unanticipated
overload. This observation is supported by weather records, which indicate
that Kemper Arena had experienced numerous storms with more rainfall and
higher winds during the previous five years. Thus, the collapse didn’t occur
until two additional factors manifested themselves.
The third contributing factor was metal fatigue. Because fatigue involves
the gradual accumulation of damage, this is the only phenomenon that can
logically account for the arena roof’s failure after it had survived greater
storms. Today, fatigue is always considered in the design of structures
subjected to multiple load cycles. But it is rarely considered in building design
because these structures typically experience relatively few large load cycles.
37
4. Rainwater Loading: Kemper Arena
This is probably why the connections between the arena roof structure’s
42 hangers and its 7 main roof trusses used an A490 bolt, which has high
strength but is considered unsuitable for cyclic loading.
This was the fourth contributing factor. These hanger rotations occurred
many times each day due to wind gusts and temperature changes. By the
time of the collapse, the A490 bolts in the lower hanger connections had
experienced about 24,000 cycles of internal tension—a repetitive loading for
which they were never intended. This loading caused fatigue cracking in the
bolts, significantly reducing their strength. The collapse began when one of
these bolts fractured. By one expert’s estimate, the internal tension in this bolt
was only about one-quarter of its factory-specified strength when it failed.
The roof was supported by 42 hangers, and each lower hanger connection
used four bolts. These bolts should have had sufficient reserve strength that
the loss of one wouldn’t overload the remaining three, but they didn’t—partly
because they had suffered fatigue damage but also because the combined
effects of ponding and wind had increased the bolt tension far beyond
the designers’ expectations. Once all four bolts in one hanger connection
fractured, the loss of support from the associated hanger instantly overloaded
the adjacent hangers, which also failed. All 14 hangers suspended from the
central portal then failed in rapid succession. Deprived of support, the entire
center section of the roof fell.
Lessons Learned
Back in 1879, lack of redundancy in the design of the Tay Bridge caused a
localized fracture of a single bolted connection to propagate into the collapse
of 13 spans. In 1979, the similar progressive collapse of the Kemper Arena
38
4. Rainwater Loading: Kemper Arena
Perhaps the most important lesson here is that innovative design solutions can
provoke unanticipated modes of failure. In response to this risk, engineers
have only two viable choices: either don’t innovate or be prepared to learn
from failure. Fortunately, the continuing story of Kemper Arena has followed
the latter path. After the collapse, the structure was rebuilt with substantially
stronger hangers, a crowned roof surface to prevent ponding, and 14 additional
drains around the perimeter. These improvements have inspired sufficient
confidence to justify the arena’s continued use well into the 21st century.
Reading
Goldberger, “Kansas City Arena Loses Roof in Storm.”
39
5
Earthquake
Loading: The
Cypress Structure
Welcome to the third in this series of case
studies exploring failures caused primarily
by inadequate load estimation. This lesson
investigates the earthquake-induced collapse
of the Cypress Structure in 1989. This case
study is pertinent to the course for three
reasons. First, it provides interesting insights
on the historical development of earthquake
engineering. Second, it is an excellent vehicle
for learning about earthquakes and their effects
on structures. And third, it provides a good
opportunity to learn about reinforced concrete.
40
5. Earthquake Loading: The Cypress Structure
This two-level elevated highway was built in 1957 to carry the Nimitz
Freeway (Interstate 880) west of downtown Oakland. The structural system
comprised 124 reinforced-concrete frames, spaced about 80 feet apart and
supporting two decks, one above the other. Each deck segment was a hollow
reinforced-concrete box beam, extending continuously across three adjacent
41
5. Earthquake Loading: The Cypress Structure
frames and connected to the adjacent deck segments at expansion joints. The
upper deck carried four lanes of southbound traffic, and the lower carried
four northbound lanes.
When the quake struck, the viaduct oscillated wildly for a few seconds. Then,
48 of its 124 frames collapsed along a 400-foot stretch of the freeway. As these
frames splayed outward, the upper deck fell onto the lower one, crushing
many vehicles in the northbound lanes and killing 42 motorists.
Reinforced Concrete
Concrete is the world’s most common construction material. It’s made by
combining a fine gray powder—Portland cement—with sand and gravel,
mixing them together, adding water and mixing again, pouring the mixture
into a mold, consolidating the wet concrete, and then finishing the surface.
This process is called casting, and the mold is called formwork. Within the
42
5. Earthquake Loading: The Cypress Structure
concrete mixture, the water and cement form a paste. This will eventually
harden into a rocklike mass through a chemical reaction called hydration.
Concrete can be cast into any shape for which formwork can be fabricated.
43
5. Earthquake Loading: The Cypress Structure
Reinforced-Concrete Frames
The reinforced-concrete frames of the Cypress Structure are what failed
during the Loma Prieta earthquake. Each frame comprised three major
components, which were cast separately:
` Above this was another bent, also consisting of two columns and a beam.
` Gravity loads include the weight of the structure and the weight of vehicles
traveling on its two roadways.
` Lateral loads are caused by wind and earthquake effects. Because such
loads can be applied from either direction, we must consider the mirror
image of these deformations too.
The steel reinforcement in the frame must be capable of resisting the internal
tension caused by these loading conditions. Thus, longitudinal rebars are
required on both sides of all beams and columns. In a typical frame of the
Cypress Structure, the dense arrangement of rebars reflected the substantial
structural demands associated with heavy loads applied to the frame’s 50-foot
spans. Interestingly, there were two locations where the steel reinforcement
was both sparse and discontinuous—two column stubs that extended above
the lower bent and incorporated the connections between the lower and
upper bents.
44
5. Earthquake Loading: The Cypress Structure
Hinges were incorporated into the Cypress Structure frames for two reasons.
First, they greatly simplified mathematical analysis of the structure. Second,
they facilitated the construction process by allowing the upper and lower bents
to be cast separately. However, the flawed design of these hinged column stubs
would prove to be a major factor in the Cypress Structure’s collapse.
Earthquakes
Earth’s outer shell (the lithosphere) comprises seven large, rigid plates and
dozens of smaller ones, which float on the asthenosphere, a soft layer of
Earth’s mantle immediately below the lithosphere. These tectonic plates are
constantly moving at speeds ranging from a fraction of an inch to about five
inches per year. The boundaries between tectonic plates are called faults.
Most occur along the coastlines of continents—like the San Andreas Fault
along the coast of California.
At a fault, the adjoining tectonic plates often move with respect to each
other—sometimes horizontally, sometimes vertically. But because the
interface between these plates is irregular, friction can restrain their motion,
resulting in a buildup of internal forces along the fault. When this stored
45
5. Earthquake Loading: The Cypress Structure
energy becomes large enough to overcome the friction between the plates,
they undergo a sudden, violent slip. As this stored energy is released, it’s
manifested as a series of seismic waves, which propagate out from the
epicenter. As they move through the lithosphere, they cause rapid, cyclic
ground motions—an earthquake.
Earthquake-Resistant Design
In designing a structure to resist earthquakes, the engineer’s challenge is
to ensure the structural system is strong enough to resist the inertial forces
caused by the largest earthquake the structure is expected to experience in its
lifetime. According to Newton’s second law, inertial force can be calculated
as the mass of the structure times the ground acceleration associated with the
earthquake for which the structure is being designed.
More specifically, for a two-level frame like those used in the Cypress
Structure, this loading is idealized as two horizontal forces applied at
the elevations of the two decks, where most of the structure’s mass is
concentrated. The lower force, F1, is equal to the mass of the lower half of the
structure times the ground acceleration. The upper force, F2 , equals the mass
of the upper half times the ground acceleration. In 1949, when the Cypress
46
5. Earthquake Loading: The Cypress Structure
These loads, along with the gravity and traffic loads, would have been used
as the basis for an analysis of the structural response—a calculation of the
internal forces in the beams and columns of each frame. These calculated
internal forces would be the basis for determining the number and size of
rebars required in these members.
For the second cause, the Cypress Structure’s response to the Loma
Prieta earthquake was greatly amplified by a dynamic phenomenon
called resonance. Like all structures, when a frame is displaced from its
equilibrium position and released, it vibrates at a characteristic frequency,
measured in cycles per second (or hertz). The natural frequency of this frame
happens to be approximately one cycle per second. One cycle of vibration for
each second equals 1 hertz.
47
5. Earthquake Loading: The Cypress Structure
In the region around Oakland, California, the three soil types are sandstone
bedrock to the east, a deep stratum of soft sediment (“bay mud”) along the
San Francisco Bay, and relatively firm alluvial sand and gravel in between.
The Cypress Structure was built partially on sand and gravel and partially
48
5. Earthquake Loading: The Cypress Structure
on bay mud. The extent of the collapsed spans corresponds exactly to the
boundary between these soil types. Thus, sediment-induced amplification was
a decisive factor in the collapse.
We can’t fault the designers for using an inadequate ground acceleration as the
basis for their design—or for specifying too little shear reinforcement in the
column stubs. The design was in full compliance with the standards of the
era. But we should question the most fundamental decision they made during
the first phase of the structural design process—to use a double-decked
configuration in a seismically active area.
49
5. Earthquake Loading: The Cypress Structure
Lessons Learned
The collapse of the Cypress Structure could have been prevented. In the
aftermath of the 1971 San Fernando earthquake, researchers gained a deeper
understanding of the vulnerabilities associated with reinforced-concrete
structures designed according to the inadequate standards of earlier eras. As a
result, two seismic retrofits of the Cypress Structure were planned—but only
one was implemented.
The retrofit involved strengthening the deck expansion joints. Here, U-shaped
steel cables were installed inside the box beams, extending across each expansion
joint, so that the beams wouldn’t pull apart during an earthquake. During the
Loma Prieta earthquake, despite the tremendous horizontal forces transmitted
across the expansion joints, none of them separated.
Reading
Hough, et al., “Sediment-Induced Amplification and the Collapse of the
Nimitz Freeway.”
Nims, et al., “Collapse of the Cypress Street Viaduct as a Result of the
Loma Prieta Earthquake.”
50
6
Vehicle Collisions:
Land and Sea
The last three lessons have examined cases
in which forces of nature—wind, rainfall,
and earthquakes—have contributed to
engineering disasters. This lesson examines
the failures caused by extreme loads for
which humans, rather than nature, were
primarily responsible. Here, you will learn
about two different cases, the Sunshine
Skyway Bridge collapse and the Skagit River
Bridge collapse, both of which demonstrate
the need for systematic assessment and
modernization of our civil infrastructure—
before such tragedies occur.
51
6. Vehicle Collisions: Land and Sea
The Sunshine Skyway was a 15-mile-long multi-span steel truss bridge carrying
Interstate 275 across Tampa Bay. It comprised two independent structures. The
first was built in 1954 to carry two lanes of traffic—one in each direction. Its
twin was added in 1971 when the highway was reconfigured to four lanes—two
northbound on the eastern bridge and two southbound on the western bridge.
Each parallel bridge consisted of a three-span through truss crossing the
navigation channel, a pair of deck trusses on either end of the through truss,
and a series of shorter girder spans connecting these trusses to the shorelines.
In a through truss, the deck and roadway are positioned at the truss’s bottom
chord, such that traffic passes through the bridge. The through trusses were
used above the navigation channel to provide additional overhead clearance
for the ships passing beneath. A deck truss has its deck and roadway at the top
chord such that vehicles drive on top of the bridge.
52
6. Vehicle Collisions: Land and Sea
Summit Venture proceeded into the shipping channel. The weather was cloudy
with intermittent light rain, but visibility remained good. The National
Weather Service had issued no storm warnings. However, at 7:21 am, the
rainfall intensity increased significantly. Lerro ordered the engine speed reduced
to “half ahead.” Minutes later, as Summit Venture was about one nautical mile
from navigation buoys 1A and 2A—and the final 18-degree turn that would
take the ship beneath the bridge—they were suddenly enveloped in a fierce
squall. As an unexpected line of thunderstorms swept across Tampa Bay, 60-
mph winds blasted the vessel from astern. Intense rain reduced visibility to zero,
rendering the ship’s radar ineffective. Steaming at half speed directly toward the
bridge, the pilots were completely blinded by the squall.
` He could order the engine reversed and the anchors dropped in an effort
to stop the vessel before it reached the bridge. But given the wind, the ship
couldn’t be stopped in time.
` He could cut power, drop anchors, and steer the ship hard to starboard,
out of the channel and parallel to the bridge. In retrospect, this probably
would have worked—but only if Lerro had initiated the turn immediately
upon the onset of the squall. However, by the time Lerro and Atkins
realized they might never spot buoys 1A and 2A, the window of
opportunity for a turnout had already passed. Even if Lerro could complete
the turn successfully, the strong wind might still drive the vessel sideways
into the bridge.
` The sole remaining option was to remain in the channel and attempt to
navigate beneath the bridge. But at that moment no one could even see the
bridge.
Moments later, a lookout sighted buoy 2A just off the starboard bow—
meaning the ship was still in the channel and had reached the required
turning point. Lerro immediately ordered a turn to port and a further
reduction in speed. But the massive vessel was slow to come around. Both
its inertia and the wind drove it out of the navigation channel to the south.
One of the bridge piers finally came into view, dead ahead, less than one ship
length away. Lerro immediately reversed the engine, steered hard to port, and
dropped both anchors—but it was too late.
53
6. Vehicle Collisions: Land and Sea
At 7:34 am, Summit Venture collided with the southernmost pier of the
western three-span through truss. The pier had a protective crash wall
extending 15 feet above the waterline—but the ship’s flared bow struck
the pier 40 feet above the crash wall. This sheared off both of the pier’s
reinforced-concrete columns and toppled 1,300 feet of the Sunshine Skyway
into Tampa Bay. Several vehicles were on the falling spans, and several others
drove over the edge. Thirty-five people died.
Cantilever Bridges
The Sunshine Skyway’s three main spans constitute a cantilever bridge. The
structure consists of six concrete piers, three on either side of the navigation
channel, and two inner deck trusses. These trusses are classified as simply
supported spans because each is supported only at its outer ends. To bridge
the three center spans, a single three-span truss extends continuously across
the two intermediate piers. However, because this three-span continuous truss
is supported at four points rather than two, it’s more challenging to analyze
and design than simply supported spans would be. Fortunately, the designers
of the Sunshine Skyway had a third alternative at their disposal—the
cantilever configuration.
the three-span continuous configuration had been used instead, it’s possible
that none of the spans would have fallen. This configuration would have been
significantly more redundant than the cantilever.
` a 40% longer center span, which provides a greater margin of safety against
navigational errors
The Washington permit required that the truck be led by an escort vehicle
equipped with a height pole—a flexible rod fixed to the vehicle’s front
bumper to warn its driver of any overhead obstructions lower than the
pole’s height. Mullen hired G&T Crawlers to provide the escort vehicle in
Washington state. G&T’s escort vehicle linked up with the Mullen truck
as it crossed the border from Canada into the United States around 6:30
pm on May 23. The escort vehicle’s height pole was set at 16 feet, 2 inches,
extending 3 inches above the height of the truck’s oversized load to provide an
55
6. Vehicle Collisions: Land and Sea
additional margin for error. After their successful link-up, the G&T escort led
the Mullen truck onto Interstate 5. Fifty miles ahead, the highway crossed the
Skagit River on a four-span steel through-truss bridge.
Each span of the Skagit River Bridge consisted of two main trusses. Their
bottom chords were interconnected by a system of beams that supported the
deck, and their top chords were connected by sway braces. Each sway brace
was a truss, with a curved bottom chord forming an arched portal through
which traffic passed. Because of their arched shape, these portals provided
overhead clearance of 17 feet for vehicles traveling in the highway’s inner
lanes. However, at the extreme right edge of the outer lanes, the clearance was
only 14 feet, 9 inches.
As they approached the bridge, both the G&T escort and the Mullen truck
were driving in the right lane at 60 mph, about 400 feet apart, in radio
contact with each other. After the incident, the G&T driver would claim her
height pole did not make contact with the overhead portals as she crossed
the bridge. However, an eyewitness testified that the pole did strike several
portals—and phone records demonstrated that the G&T driver was talking
on her cell phone as she drove across the bridge. In any case, the escort should
have notified the Mullen driver about the approaching overhead obstruction
56
6. Vehicle Collisions: Land and Sea
because the truck’s oversized load was so much wider than the escort vehicle.
The highway was straight and level at this location; thus, the escort should
have seen the bridge when it was still a quarter mile away.
These deficiencies contributed directly to the disaster. The first two created the
conditions for the truck’s impact with the overhead portals. The third resulted
in the structure collapsing—even though the impact didn’t directly damage any
of the bridge’s principal load-carrying members. These deficiencies were caused
by a major change to the bridge’s function after it had already been built.
57
6. Vehicle Collisions: Land and Sea
The bridge was originally designed to carry only two traffic lanes 12 feet
wide with 10-foot shoulders. Because there were only two lanes, the 14-foot,
9-inch overhead clearance constraint affected only the extreme outer edges
of the shoulders. But one year after the bridge was opened, President Dwight
Eisenhower signed the Federal Aid Highway Act of 1956, which created
the US Interstate Highway System. To accommodate all four lanes of the
newly created Interstate 5, the Skagit River Bridge was reconfigured with
substandard 11-foot, 4-inch lane widths, virtually nonexistent shoulders, and
overhead obstructions that impinged upon the traveled way.
After the collapse, the failed truss span was replaced with a girder span. The
remaining three simply supported truss spans were modified to replace the
arched lower chord of the sway braces with a horizontal chord, providing
a uniform 16-foot clearance across the entire roadway. However, the
substandard lane and shoulder widths of the original trusses remain.
Buckling Failure
To understand the fourth reason for the Skagit River Bridge’s functional
obsolescence—structural nonredundancy—the collapse of the northernmost
span must be considered. According to the National Transportation Safety
Board investigation, when the truck impacted the portal on the northern
span, it caused a vertical member of the main truss to bend sharply inward.
As such, the vertical member could no longer brace the top chord of the truss
against buckling. The top chord’s consequent buckling failure precipitated the
collapse of the entire span.
In the Skagit River Bridge, the top chord was designed to take advantage of
the strengthening effect provided by the vertical brace. But when the brace was
compromised by the collision, the resulting loss of strength triggered a buckling
failure of the top chord—and a structural collapse. This is the epitome of a
nonredundant structural system. Damage to a secondary member—the lower
element of a portal—triggered a progressive collapse of the entire structure.
Lessons Learned
In many cases, accidents are the direct result of human negligence. This was
true for the Skagit River Bridge collapse. However, in the Sunshine Skyway case,
the occurrence of an unexpected squall at the worst possible moment made the
catastrophe practically unavoidable. In either case, “accidents happen” is not a
legitimate excuse for an engineering failure. High-quality engineering design
purposefully accounts for the possibility of accidents, seeks to prevent them
from happening when possible, and minimizes their adverse consequences when
prevention isn’t possible. As engineers learn from failure, materials are replaced
by safer alternatives, and design methods are improved to account for new, better
understandings of physical phenomena. Failures also cause well-established
structural forms, such as the cantilever bridge, to fade into obsolescence.
Reading
National Transportation Safety Board, Collapse of the Interstate 5 Skagit
River Bridge.
———, Marine Accident Report.
59
7
Blast Loading:
The Murrah
Federal Building
During the past few decades, terrorism
has profoundly influenced our worldviews,
lifestyles, and sense of security. In 1995, a
heinous act of domestic terrorism set the US
engineering community on a path toward the
purposeful incorporation of blast resistance
into the design of important structures.
This lesson will focus on the collapse of the
Murrah Federal Building due to the Oklahoma
City bombing. You will learn about blast
loading, the failure mechanisms that led
to the building’s collapse, and the design
insights gained from the analysis of this
collapse.
60
7. Blast Loading: The Murrah Federal Building
As he approached his target, McVeigh lit two fuses in the truck’s cab,
then parked the truck in the planned location and fled to his getaway car.
Moments later, at 9:02 am, the bomb detonated. The explosion shattered
the curtain wall, sending glass shards flying through the building’s interior.
The blast knocked out several structural columns, triggering a collapse that
61
7. Blast Loading: The Murrah Federal Building
destroyed about half of the building’s occupied space. The force of the blast
also destroyed or damaged 324 other structures within a 16-block radius.
Overall, over 700 people were injured and 168 killed, including 15 children.
Immediately after the collapse, first responders began to locate and extract the
victims from the debris. Structural engineers advised the rescue teams on how
to stabilize and temporarily support both the wreckage and the portions of the
structure that remained erect. Moreover, the Federal Emergency Management
Agency (FEMA) deployed an assessment team to investigate the building’s
collapse and formulate strategies for improving the blast resistance of new and
existing buildings.
This structural system was effective for resisting gravity loads—the weight of
the building and its occupants. However, the local building code also required
the structure to resist the lateral forces caused by wind. As the system wasn’t
particularly effective at this, the building designer filled select rectangular
panels with a shear wall on each story. This provided the frame with the
required stability and lateral load-carrying capacity. The shear walls were
placed around the elevator shafts and stairwells at the center of the building’s
south side, providing a structural core capable of resisting wind loads in
the north-south and east-west directions. Massive cylindrical pillars at the
building’s corners enclosed the vertical air ducts of the ventilation system.
62
7. Blast Loading: The Murrah Federal Building
Blast Loading
Blast loading is the effect of an explosion on a structure. There are three
different categories of explosions—physical, chemical, and nuclear. The
one that destroyed the Murrah Building was a chemical explosion, defined
as a large, rapid release of energy caused by a chemical reaction—the rapid
oxidation of fuel elements contained within the explosive material. For a
typical high explosive like trinitrotoluene (TNT), this oxidation reaction
generates enough heat to raise the air temperature at the point of detonation
by over 5,000°F. This near-instantaneous temperature increase generates
extremely high pressure. This causes the hot gases to expand violently
outward in all directions at the speed of sound. As this sphere of hot gas
expands, a layer of compressed air—the blast wave—forms at its outer edge.
The blast wave contains much of the energy released by the explosion and is
responsible for most of the resulting destruction. As the wave passes through
a given point in space, that point experiences an instantaneous increase in
pressure—called the incident peak overpressure—for a fraction of a second.
The peak overpressure can be in the order of 1 million pounds per square inch
63
7. Blast Loading: The Murrah Federal Building
(psi) at the point of detonation, but decreases sharply as the wave propagates
outward. However, an overpressure as low as 2 psi can cause significant
structural damage. When the blast wave encounters a solid object, its reflection
off that surface significantly increases the pressure applied to the object.
The blast wave that produced this crater also propagated upward and outward
through the Murrah Building. When the wave had traveled 10 feet—the
shortest distance between the point of detonation and the northern façade—
the peak overpressure was about 10,000 psi. By the time it reached the
building’s upper northwest corner, the wave had dissipated to 9 psi, but the
structural system had been fatally damaged.
The first structural member affected by the blast was an exterior column
located 16 feet away from the point of detonation. Subjected to an estimated
peak overpressure of 5,600 psi, the concrete column—36 inches wide, 20
inches thick, and 21 feet tall—was obliterated. The technical term for this
failure mode is brisance—the shattering effect of an explosion acting upon a
brittle material like concrete. The next two closest columns were 37 feet and
50 feet from the point of detonation. The blast wave’s intensity was sufficiently
diminished that brisance didn’t occur. Nonetheless, the peak overpressure still
bent the columns laterally until their upper ends failed in shear.
With the catastrophic loss of three adjacent exterior columns, the transfer
girder—designed to span the 40 feet between columns—was suddenly
spanning 160 feet. With this loss of support, the immense weight of all the
beams, columns, and slabs caused the girder to fail in flexure. As it sagged and
fell, the beams, columns, and slabs of the northern wall collapsed along with it.
This sequence of events, from explosion to collapse, took about seven seconds.
64
7. Blast Loading: The Murrah Federal Building
Of the 11 exterior columns that originally supported the northern wall, only
1 on the east end and 3 on the west end survived. One interior column also
failed, though the cause of this failure remains uncertain. One plausible
theory is that it was knocked out by flying debris. Another is that the blast
destroyed the surrounding floor slabs at the second-floor level and that loss of
the lateral bracing doubled the length of the compression member, causing a
buckling failure.
Regardless of its cause, the failure of this interior column had dire
consequences—the progressive collapse of all columns, beams, and slabs
immediately above it and thus the loss of an additional 11,000 square feet of
occupied space on eight floors. However, the structural core on the south side
of the building was essentially undamaged by the blast, partly because of the
added strength provided by the shear walls.
As the blast wave propagated upward through the Murrah Building, the peak
overpressure below each slab greatly exceeded the pressure above the slab for a
few milliseconds. This resulted in a net uplift force that significantly exceeded
the slabs’ own weight, causing them to flex upward—exactly opposite the
bending mode for which they were designed. Thus, tension occurred in the
regions without steel reinforcement, causing the concrete to fracture in these
areas. Once the blast wave had passed, the fractured slabs could no longer
support their own weight—and collapsed.
65
7. Blast Loading: The Murrah Federal Building
66
7. Blast Loading: The Murrah Federal Building
Moreover, FEMA suggested that the transfer girder might have survived the
loss of a single column but for one reinforcement detail. Based on the girder’s
deformed shape, we know the rebars were appropriately placed in regions
that experience tension—along all surfaces that deform into a convex shape.
The crucial reinforcement detail was the discontinuity in the bottom rebars
at the supporting columns. In the intact structure, this discontinuity wasn’t
problematic because it occurred in a region experiencing compression. But
when a column was removed, the transfer girder’s bending changed, and the
girder suddenly experienced substantial tension in a region with no flexural
reinforcement. This resulted in a catastrophic fracture through this plane of
weakness, prompting the girder’s collapse.
But if this same girder were designed according to the NEHRP standards
for earthquake-resistant structures, this problematic reinforcement
detail wouldn’t have been permitted. The standards specify that flexural
reinforcement must run continuously through column supports. Had the
Murrah Building’s transfer girder been reinforced in this way, it probably
would have retained sufficient load-carrying capacity to survive the loss of one
column. Similarly, the NEHRP standards require continuous top and bottom
reinforcement in slabs. If the building’s floor slabs had been reinforced like
this, blast-induced uplift would have caused significantly less damage.
The implication of these observations was that a few modest changes to the
Murrah Building’s steel reinforcement might have provided a structural system
with enough resilience to survive the bombing with only localized damage.
Lessons Learned
The FEMA team’s crucial insight—that there’s a strong commonality between
blast resistance and earthquake resistance—led to a new engineering design
philosophy called multi-hazard mitigation. This attempts to account for a
67
7. Blast Loading: The Murrah Federal Building
wide range of extreme loads caused by earthquakes, intense storms, and blast
effects in a holistic way that is both effective and cost-efficient. According
to FEMA’s investigation report, inclusion of these NEHRP-recommended
reinforcement details—which would have protected the Murrah Building
from both earthquakes and blast effects—would have added only 1% to 2%
to the total building cost.
Reading
Federal Emergency Management Agency, The Oklahoma City Bombing.
Mlakar, et al., “The Oklahoma City Bombing.”
Sozen, et al., “The Oklahoma City Bombing.”
68
8
Structural
Response: The
Hyatt Regency
Walkways
The past five lessons have explored
engineering failures caused primarily by
extreme loads—wind, rainwater, earthquakes,
vehicle collisions, and blast effects—that were
larger than expected or entirely unexpected
when the structure was designed. This lesson
focuses on failures associated with phase 3 of
the design process—analysis of the structural
response. The case study concerns the Hyatt
Regency Hotel walkway collapse. Here, you
will explore the collapse mechanisms as
well as the communication breakdowns that
contributed to them.
69
8. Structural Response: The Hyatt Regency Walkways
Underestimated
Structural Response
When loads are applied to a structure, the structure responds by experiencing
internal forces and deforming. In engineering design, this structural
response must be calculated and used as the basis for choosing the sizes and
configurations of structural members and connections such that they’ll carry
the load safely and won’t deform excessively. Underestimating the structural
response can be a major contributor to engineering failures.
Design-Bid-Build
The three principal players in the planning and delivery of a construction
project are the owner, the design professional, and the constructor.
70
8. Structural Response: The Hyatt Regency Walkways
that develops a complete design for the facility. The principal product of the
design process is a set of plans and specifications. These describe the project
in sufficient detail so that potential constructors can prepare accurate cost
estimates for building the planned facility.
The owner then advertises the project, and interested general contractors
submit bids for the job. A bid is the price the contractor will charge if selected
to construct the project. The owner usually selects the lowest bid that is
responsive to all specified project requirements. The selected constructor
enters a contract with the owner, hires the appropriate subcontractors, builds
the project for the agreed-upon price, and then turns over the completed
facility to the owner.
Design-Build
These disadvantages are addressed in the design-build system. Here, the
owner hires one company to assume full responsibility for both design and
construction. This single corporate entity—which might be an architectural
or engineering firm, a construction company, a project management firm, or
a consortium of companies—hires all consultants and subcontractors required
for the project. This system saves time and provides better opportunities for
coordination. However, it can also create significant uncertainties about the
project cost and scope because the contract between the owner and company
is signed before the project is even designed.
71
8. Structural Response: The Hyatt Regency Walkways
In such commercial projects, the owner starts incurring finance costs as soon
as the project begins, but the facility doesn’t start generating income until
it’s completed. In the Hyatt Regency case, the owner addressed this using
a management technique called fast-tracking, in which construction is
begun before the design is complete. Fast-tracking can save time, but it’s also
susceptible to problems with coordination, communication, and delineation
of responsibilities. Such management issues would contribute substantially to
the Hyatt Regency disaster.
The most distinctive feature of the atrium interior was a set of three elevated
walkways, suspended from the roof and designed to facilitate movement
between the tower and service block at the second‑, third‑, and fourth-floor
levels. Each walkway comprised a reinforced-concrete deck supported on
transverse steel I-shaped beams. These were supported on larger longitudinal
beams called stringers. The outer ends of the outer pairs of stringers were
supported on shelf angles anchored to the reinforced-concrete frames of the
72
8. Structural Response: The Hyatt Regency Walkways
tower and service block. Their inner ends were framed into steel box beams.
Each beam was fabricated from two C-shaped elements called channels,
welded together at the tips of their flanges.
These box beams extended outward beyond the deck to provide attachment
points with steel hangers from which the entire walkway was suspended. In
Gillum’s design, the upper end of each hanger would be secured to the roof
structure; the lower end would be threaded, inserted through a hole at the end
of its associated box beam, and secured with a nut. The third-floor walkway
was supported independently on its own set of six hangers. However, the
second- and fourth-floor walkways were supported—one directly beneath
the other—on one set of hangers. Each hanger would run continuously from
the second-floor box beam and up through the fourth-floor beam to its
connection with the roof structure. This apparent simplicity belied a serious
flaw in the configuration of these vital beam-to-hanger connections.
In the 1970s and 1980s, structural engineers typically delegated the design
of most structural connections to the project’s steel fabricator. This way, the
steel fabricator gained the flexibility to choose connection configurations best
suited to the company’s capabilities and preferred fabrication methods. This
often yielded improved economy and constructability.
73
8. Structural Response: The Hyatt Regency Walkways
structural engineer of record before the first piece of steel was cut. Therefore,
the engineer had both the opportunity and obligation to identify and fix any
problems during the shop drawing review.
Consistent with this well-established process, the steel fabricator for the Hyatt
Regency atrium—Havens Steel Company—assigned a technician to prepare
shop drawings for the project, starting in December 1978. Shortly thereafter, this
technician encountered an ambiguity in Gillum’s sketch of the beam-to-hanger
connection. Gillum’s sketch was appropriate for the second- and third-floor
connections, where the hanger terminated immediately below the box beam. But
it didn’t address the unique configuration at the fourth floor, where the hanger
was supposed to run continuously through the beam. The only feasible way to get
the nut to its proper position on the hanger would be to thread the entire bottom
30 feet of the rod. However, these threads would be susceptible to damage when
the fourth-floor walkway was lifted into position during construction.
Even during construction, there were warning signs and missed opportunities.
On several occasions, workmen noticed the recently erected walkways were
sagging excessively—indicating that the box beams were already in distress
when carrying only the walkways’ own weight. The contractor reported these
excessive deformations to the architect’s on-site representative, but no one
passed this report to the structural engineer.
Even worse, a mandatory design review by the Kansas City Public Works
Department did not identify the connection deficiency but did mandate that
the walkways’ steel framing be fully encased in gypsum board to improve
its fire resistance. Once this fireproofing was installed, the box beams were
entirely hidden from view. The possibility that anyone might notice their
abnormal deformations dwindled to zero.
75
8. Structural Response: The Hyatt Regency Walkways
76
8. Structural Response: The Hyatt Regency Walkways
First, the walkways were not overloaded when they failed. An analysis of
videotapes shot before the collapse verified that there were, at most, 64 people
on both the second- and fourth-floor walkways at the time. Had the structure
been properly designed to support its code-specified loads, each walkway
could have carried more than 400 people with an ample margin of safety.
Second, the walkways didn’t fail because of resonant vibrations caused by
people dancing to the music, as reported in the media.
Third, Gillum’s decision to fabricate the box beams by welding pairs of steel
channels together was a major contributor to the failure. A high-quality weld
can be as strong as the pieces of steel it joins. However, in the Hyatt box
beams, the welds were too small—and large holes for the hangers were drilled
directly through the welds, weakening them. This weakness could easily have
been remedied, such as by adding steel bearing plates on the top and bottom
of the box beams. Had an engineer designed the connection, the need for such
reinforcement would have been obvious. Fourth, the disaster’s severity was
exacerbated by a lack of redundancy in the design of the walkway structural
system. The localized failure of one connection shouldn’t have triggered a
progressive collapse of the entire system.
77
8. Structural Response: The Hyatt Regency Walkways
Lessons Learned
The Hyatt Regency walkway collapse exposed deep, systemic flaws in the
processes by which owners, design professionals, and constructors were
managing complex projects in the US during this period. Consequently, the
disaster stimulated new laws, policies, and technical standards to improve the
delineation of professional responsibilities, design change processes, and use of
independent design reviews.
This case reveals an important insight about how the engineering enterprise
has changed over the past few centuries. Today, the development of
constructed works has become a corporate endeavor, performed by large
ad hoc organizations composed of many specialized companies. Now,
management issues are as important as engineering issues. Failures are as
likely to result from coordination and communication breakdowns as from
design and construction errors.
Reading
Bernhardt, “Hyatt Regency Skywalk Collapse Remembered.”
Marshall, et al., Investigation of the Kansas City Hyatt Regency Walkways
Collapse.
78
9
Bridge
Aerodynamics:
Galloping Gertie
This lesson continues this course’s
exploration of engineering failures caused
by an unanticipated structural response. In
the early 1800s, a science-based analysis
tool inspired the design of bridges that were
increasingly optimized for gravity loads but
increasingly vulnerable to wind-induced
vibration—suspension bridges. This case
study chronicles the trials and errors of the
first suspension bridges, the subsequent
advances made in their construction, and the
folly of the Tacoma Narrows Bridge design,
which led to its collapse.
79
9. Bridge Aerodynamics: Galloping Gertie
80
9. Bridge Aerodynamics: Galloping Gertie
To test Navier’s equation, say two cables are suspended side by side—one
loaded with a series of equal weights that approximate a uniform loading
and one with no loading at all (other than the weight of the cable itself).
If we hang a concentrated load from the center of each cable and compare
the magnitudes of the resulting deflections, the midspan deflection of the
uniformly loaded cable is noticeably less than that of the cable without
uniform loading. This demonstrates that the deflection due to a concentrated
load can be reduced by increasing the bridge’s overall weight.
81
9. Bridge Aerodynamics: Galloping Gertie
Roebling’s System
This and other mid-19th-century collapses were so traumatic that they might
have led to the demise of the suspension bridge as a structural idea. But then
came John Roebling, who started building great suspension
bridges—including the Niagara Falls Suspension Bridge
in 1855, the Cincinnati-Covington Bridge in 1866, and
the Brooklyn Bridge, the design of which was still
in progress when Roebling died in 1869. Through
these projects, Roebling developed a highly effective
system for preventing wind-induced vibration.
82
9. Bridge Aerodynamics: Galloping Gertie
Elastic Theory
Meanwhile, proponents of science-based engineering were pursuing new
theoretical approaches to suspension bridge analysis. These efforts came to
fruition in 1888, when Austrian engineer Josef Melan proposed the first
practical science-based analysis method for a parabolic cable structurally
connected to a stiffening truss. Called the elastic theory, it avoided excessive
mathematical complexity by making several simplifying assumptions—most
importantly, that the shape of a stiffened parabolic cable doesn’t change
in response to concentrated loads. As this simplification was conservative,
bridges designed according to this theory tended to have excessively robust
stiffening trusses.
The elastic theory worked and was generally seen as a step forward from
Roebling’s empirical system because it was grounded in scientific principles.
But the ungainly proportions of the Williamsburg Bridge also demonstrated
that the theory’s simplifying assumptions would produce excessively
conservative, uneconomical designs.
Deflection Theory
In response to the need for a more sophisticated analysis method, Josef
Melan developed the deflection theory, which accounts for the load-induced
deflection of both the cable and stiffening truss. Thus, it could predict a
suspension bridge’s response to uniform and concentrated loads with much
greater accuracy. Both Melan’s deflection theory and Navier’s equation led
engineers to essentially the same conclusion—longer, heavier spans require
less stiffening. Thus, 20th-century engineers responded to the deflection
theory by designing a series of suspension bridges with progressively longer
spans and progressively less stiffening, without considering their increasing
susceptibility to wind-induced vibration.
83
9. Bridge Aerodynamics: Galloping Gertie
But Moisseiff had other ideas. Exploiting the deflection theory, he prepared
an independent alternative design proposal with an estimated cost of only
$8 million. Thus, the state had no choice but to hire Moisseiff to design the
bridge. Through further refinements, he reduced the project cost to $6.4
million—58% of the state’s original estimate.
Moisseiff’s Design
The overall configuration of Moisseiff’s design was similar to Eldridge’s
original proposal—two 425-foot-tall steel towers supporting two main
cables, each a 17-inch-diameter bundle of more than 6,000 galvanized
steel wires. Suspended from these cables were a 2,800-foot main span and
two 1,100-foot side spans. Moisseiff achieved his low cost primarily by
replacing Eldridge’s heavy stiffening truss with a pair of slender, 8-foot-
deep girders—large enough to provide the strength and stiffness required
by the deflection theory. These stiffening girders were 39 feet apart, held in
alignment by transverse beams. Stringers spanning between these transverse
84
9. Bridge Aerodynamics: Galloping Gertie
During this era, it was standard practice to idealize wind loading as a static
pressure applied to the structure’s vertical surfaces—and resisted entirely by
the deck structure bending sideways. In this mode, the stiffening girders,
beams, and V braces function essentially as a truss turned on its side. But
for the Tacoma Narrows Bridge, this approach proved problematic. Because
the two-lane deck was so narrow, it didn’t provide adequate lateral bending
strength to resist the wind. Indeed, during a routine review of Moisseiff’s
design, an independent consultant expressed grave concerns about this narrow
width—and recommended that the girders be moved significantly farther
apart. But Moisseiff used the deflection theory to justify the narrow width
specified in his original design.
Recall that Melan developed the deflection theory strictly for predicting
a bridge’s response to gravity loads. But Moisseiff reasoned that just as
deflection theory takes advantage of the cables’ vertical deflection to resist a
concentrated gravity load, it can also take advantage of the cables’ horizontal
deflection to resist wind loads. When applied in this way, deflection theory
predicts the cables will support about half of the total wind load applied to
the stiffening girders. Thus, Moisseiff justified retaining the deck’s original
39-foot width—and not strengthening the wind bracing. The result was a
deck structure of unprecedented slenderness, with a depth-to-span ratio of 1
to 350 and a width-to-span ratio of 1 to 72—much thinner than any other
major bridge. The deck was also significantly more flexible than that of any
long-span bridge in existence.
85
9. Bridge Aerodynamics: Galloping Gertie
86
9. Bridge Aerodynamics: Galloping Gertie
main cables. These measures were partially effective, but the tie-down cables
kept breaking—an indicator that the forces driving these vibrations were
larger than expected.
Vortex Shedding
But was this an adequate basis for exonerating Moisseiff? Granted, since
the time of the Tay Bridge disaster of 1879, bridge design standards had
only considered wind as a static pressure, with no explicit consideration of
the structure’s dynamic response to moving air. But the aerodynamic effect
observed at Tacoma Narrows had been plainly evident in the many wind-
induced failures of 19th-century suspension bridges. And the great flexibility
of Moisseiff’s design was his own choice, motivated primarily by his desire
87
9. Bridge Aerodynamics: Galloping Gertie
Aeroelastic Flutter
Today, most experts agree that vortex shedding caused the benign vertical
bending vibrations the Tacoma Narrows Bridge had been experiencing since
its construction. However, the violent torsional oscillations that destroyed it
resulted from aeroelastic flutter—a complex, dynamic interaction between
moving air and a flexible structure.
When the girders’ elasticity finally stopped this rotation and sent the deck
rebounding back in the opposite direction, the upper vortex detached. As it
moved downwind, its associated force further accelerated the rebound. The
second half of each oscillation was a mirror image of the first. New vortices
88
9. Bridge Aerodynamics: Galloping Gertie
formed behind the upwind girder, reinforcing its rotation, and then broke free
and reinforced the rebound. These self-excited oscillations continued to grow
until the structure broke apart.
This is aeroelastic flutter. When the wind speed is just so, the forces caused by
the moving vortices are perfectly synchronized with the motion of the girder
system in a way that reinforces the structure’s natural torsional oscillations.
But the most fundamental cause of the disaster was not an aerodynamic
effect; rather, it was Moisseiff’s decision to use stiffening girders of
unprecedented slenderness—a decision that relied too heavily on an unproven
science-based analysis tool and failed to consider ample historical evidence of
past wind-induced failures.
Lessons Learned
Fortunately, Moisseiff’s failure had a positive impact on subsequent
engineering practice. By the time of the Tacoma Narrows collapse, many
other bridges designed using deflection theory were also experiencing
unexpected wind-induced oscillations. The collapse prompted substantial
structural modifications to the Golden Gate Bridge, Bronx-Whitestone
Bridge, and other spans—all of which are performing well today.
The first major American suspension bridge built after the Tacoma Narrows
disaster was a new Tacoma Narrows Bridge, completed in 1950. With its
robust 33-foot-deep stiffening truss and several research-based mechanisms
for reducing wind-induced vibrations, this structure clearly reflects the lessons
learned from the failure of its predecessor.
89
9. Bridge Aerodynamics: Galloping Gertie
Reading
Billah and Scanlan, “Resonance, Tacoma Narrows Bridge Failure, and
Undergraduate Physic Textbooks.”
Buobopane and Billington, “Theory and History of Suspension Bridge
Design.”
Griggs, “Tacoma Narrows Bridge Failure 1940.”
Kawada, History of the Modern Suspension Bridge.
Morgenthal, “Fluid-Structure Interaction in Bluff-Body Aerodynamics and
Long-Span Bridge Design.”
Myerscough, “Suspension Bridges.”
Washington State Department of Transportation, “People of the 1940
Narrows Bridge.”
90
10
Dynamic
Response:
London’s
Wobbly Bridge
In June 2000, a new state-of-the-art pedestrian
bridge over the Thames was opened to the
public, but an unanticipated dynamic response
to pedestrian loads became immediately
apparent. Many aspects of the Millennium
Bridge design presented unprecedented
structural engineering challenges. This lesson
explores the unique design of the Millennium
Bridge versus conventional suspension bridges
and introduces several phenomena, such as
vibrational modes and synchronous lateral
excitation, to explain why the bridge wobbled—
and how it was fixed.
91
10. Dynamic Response: London’s Wobbly Bridge
92
10. Dynamic Response: London’s Wobbly Bridge
limiting the number of people crossing at any one time, authorities closed
the Millennium Bridge, now dubbed the Wobbly Bridge, and initiated an
investigation of the unexpected vibrations. The crossing would remain closed
for nearly two years.
` In the river, each of the two towers consists of a solid concrete pier
surmounted by a V-shaped tubular steel superstructure.
` At the heart of the structural system are eight main cables, four on each
side, that are clamped to the towers and anchored at the abutments. The
towers and abutments delineate spans of 81, 144, and 108 meters.
` A series of transverse steel frames are clamped to the cables. Because these
frames must accommodate the cables’ sag, each has its own unique shape.
93
10. Dynamic Response: London’s Wobbly Bridge
` Third, the bridge uses no suspenders; rather, the deck is rigidly connected
to the cables by the transverse frames.
` Finally, the main cables’ inward sag provides enough lateral strength and
stiffness that no diagonal bracing is needed to resist wind loading.
Vibrational Modes
After the bridge was closed on June 12, 2000, Arup was called in to
investigate the problem and devise a solution. The firm developed a
comprehensive research program for designing a targeted structural retrofit.
This program began with on-site testing using a mechanical shaker to vibrate
the bridge and measuring its dynamic response with accelerometers mounted
on the structure. These tests were intended to validate the sophisticated
computer model used to design the original structure, ensuring that the same
model could be used to design the retrofit.
These tests also verified the specific modes of vibration that had occurred
on opening day. Recall that a bridge can experience different vibrational
modes—vertical, lateral, and torsional—and that each mode has its own
characteristic natural frequency, measured in cycles per second (or hertz).
Arup’s tests of the Millennium Bridge determined that pedestrians were
exciting the lateral vibrational mode in the south span at a frequency of 0.8
hertz and in the middle span at a frequency of 1 hertz. These frequencies were
94
10. Dynamic Response: London’s Wobbly Bridge
significant because they closely match the average frequency of the human
gait at a normal walking pace. Three left and right steps in three seconds
corresponds to a frequency of 1 hertz.
Since the two bridge spans had natural frequencies nearly equal to the
frequency of the human gait, it seems possible that the structure’s unexpected
dynamic response was caused by resonance. Resonance occurs when a
periodically applied force matches the structure’s natural frequency and causes
the vibrations’ magnitude to increase with each successive cycle. Logically,
the Millennium Bridge could have experienced lateral resonance only if the
pedestrians crossing the bridge were imparting a significant, periodic lateral
force to the deck.
Lateral Force
In 2000, there were no reliable research data on lateral forces imparted by
people walking. Thus, Arup collaborated with two universities to conduct
laboratory tests aimed at quantifying these lateral forces. For example, in
one series of tests, pedestrians walked on a specially instrumented treadmill
operating at a normal walking pace while also being subjected to lateral
vibrations at a controlled frequency and amplitude. These tests produced two
important findings.
95
10. Dynamic Response: London’s Wobbly Bridge
Because of this instinctive response, the pedestrians walking in sync with the
bridge’s motion were also inadvertently applying periodic lateral forces to the
bridge at its natural frequency. These forces caused the oscillation amplitude
to increase, which had two consequences. First, the increasing amplitude
caused the pedestrian-induced lateral forces to increase. Second, as the
oscillations become more perceptible, more people fell into step with them.
These effects caused further increases in the vibrations’ amplitude. This self-
reinforcing process continued until the system reached frequency lock-in, with
nearly everyone walking in step with the ever-increasing oscillations.
97
10. Dynamic Response: London’s Wobbly Bridge
The engineers were left with alternative 3—to increase the structural
system’s damping. Damping is the tendency of vibrations to die out over
time. For example, if you stretch a spring-mass system and then release it,
the oscillations get slightly smaller with each cycle, eventually dying out. In
this case, the damping is caused primarily by air resistance on the moving
mass. Because the damping effect is small, it will take a long time for these
oscillations to die out completely.
Damping
All structures exhibit this sort of intrinsic damping due to air resistance,
friction in the connections, etc. But it’s also possible to add artificial damping
to improve a structure’s dynamic performance. Arup’s analytical studies
demonstrated that adding sufficient artificial damping to the Millennium
Bridge could prevent resonant vibrations from occurring. Furthermore, this
strategy could be applied without compromising the bridge’s function or
drastically altering its appearance.
98
10. Dynamic Response: London’s Wobbly Bridge
Sixteen more dampers were mounted at the piers, and four connected the
deck structure to the ground at the Needle, near the southern abutment.
The retrofit also included 52 tuned mass dampers, intended primarily to
prevent excessive vertical oscillations. The Arup engineers had been concerned
that once the lateral oscillations were suppressed by the dampers, vertical
or torsional vibration modes might manifest themselves. Once they became
perceptible, synchronous excitation might cause them to grow uncontrollably,
just as the lateral oscillations had.
Lessons Learned
Considering the Millennium Bridge case, three important insights come
to mind:
First, this case demonstrates that engineering failures don’t always involve
catastrophic events. The closure of the original Millennium Bridge was a
temporary engineering failure because the structure couldn’t perform its
primary function following the discovery of its unexpected dynamic response.
Thus, an “engineering failure” encompasses not only technological systems
that break but also those that don’t perform as their designers intended.
99
10. Dynamic Response: London’s Wobbly Bridge
Second, this case illustrates why our structural design process doesn’t end with
the completed structure. The engineering process can (and should) continue
through the operation and maintenance phases—both to remedy problems
that have been discovered and to anticipate and prevent future problems.
Reading
Dallard, et al., “The London Millennium Footbridge.”
Newland, “Vibration of the London Millennium Bridge.”
100
11
Dynamic
Response:
Boston’s Plywood
Palace
Welcome to this lesson on the John Hancock
Tower—a case study that incorporates
three epic engineering failures, including
falling window panels, wind-induced sway,
and P-delta-related structural deficiency.
This serves as an important transition point
in this course. The past four lessons have
focused on failures caused primarily by an
unanticipated structural response. But in
the Hancock Tower case, you’ll discover that
the window failures were caused not by an
unanticipated structural response but by
inadequate resistance.
101
11. Dynamic Response: Boston’s Plywood Palace
102
11. Dynamic Response: Boston’s Plywood Palace
Around this time, construction workers began reporting that during high
winds, the structure’s sway was so pronounced that it was causing motion
sickness on the uppermost floors. Everyone immediately drew the only logical
conclusion—that the excessive wind-induced sway was the cause of the
window failures.
To depict the full structural system, replicate this module 61 more times. This
790-foot-tall steel skeleton is clad in a glass curtain wall—a nonstructural
building façade comprising individual panels hung in a way that purposefully
accommodates structural movements caused by loads and temperature
changes. Each of these 10,344 glass panels measures 4.5 feet wide by 11.5 feet
tall and weighs 500 pounds.
As each east-west frame incorporates two diagonal braces, the aggregate effect
of this 62-story stack of bracing is to form a vertically oriented truss that
effectively stabilizes the east-west frames and resists horizontal wind forces in
this direction. These east-west frames that resist lateral forces through the use
of diagonal bracing are called braced frames.
103
11. Dynamic Response: Boston’s Plywood Palace
rigid connections that join the beams and columns together. In a simple
connection, typically used in braced frames, only the web of the I-shaped
beam is fastened to the column. In a rigid connection, the web and both
flanges are rigidly fastened to the column.
104
11. Dynamic Response: Boston’s Plywood Palace
` First, the professors identified the underlying cause of the structure’s wind-
induced vibrations and verified that these vibrations were large enough to
cause the occupants of the upper floors to experience physical discomfort.
` Second, they demonstrated conclusively that the window failures had not
been caused by wind-induced deformation of the tower or by aerodynamic
effects associated with the tower’s unusual geometric shape.
P-Delta
Given its potentially disastrous consequences, this newfound structural
deficiency had to be addressed aggressively and expeditiously. In his analysis,
Thürlimann had discovered that the design of the Hancock Tower failed to
account for the P-delta effect—an interaction between gravity loads and
wind loads that makes their combined effect greater than the sum of its parts.
105
11. Dynamic Response: Boston’s Plywood Palace
the columns. It causes an overturning effect that increases the sway and
increases the structure’s susceptibility to collapse. The P-delta effect tends to
be larger in rigid frames than in braced frames because rigid frames typically
experience more lateral sway.
In the 1960s, when the tower was designed, the P-delta effect wasn’t addressed in
structural design codes because it is typically insignificant in low-rise buildings.
In fact, the Hancock Tower was in full compliance with the Boston building
code in effect at the time. However, its unprecedented combination of great
height, a lightweight glass façade, and a rigid-frame structural system caused the
normally insignificant P-delta effect to become frighteningly significant.
106
11. Dynamic Response: Boston’s Plywood Palace
107
11. Dynamic Response: Boston’s Plywood Palace
This reduction in sway would only be temporary if not for the artificial
damping provided by the TMD. Without this damping effect, the moving
mass would eventually transfer its kinetic energy back into the frame—and
the frame’s motion would again increase. But the damping provided by the
TMD dissipates this energy before it can be transferred back into the frame.
108
11. Dynamic Response: Boston’s Plywood Palace
The tower’s windows were double-glazed. Each window panel comprised two
quarter-inch-thick glass panes, called lights, with a half-inch insulating air
gap in between. The windows’ mirrored appearance was achieved by applying
a metallic coating to the inner face of the outer light. The half-inch gap
between the lights was maintained by a lead spacer fastened to the edges of the
lights with soldered joints running around the panel perimeter. The window
manufacturer intended these joints to be relatively flexible to accommodate the
expansion, contraction, and bending of the glass in response to temperature
changes and wind pressure. The problem was that the soldered joint between
the spacer and the outer light bonded not only to the edge of the glass but also
to the metallic coating on its inner face. Thus, the joint became too rigid. After
repeated thermal and wind loading cycles, the joint cracked. Because the bond
was so tenacious, the crack propagated into the glass, causing the outer light to
fracture and break free from its mountings.
At the time, this type of window was widely used in commercial buildings
and had experienced no major problems. However, it had never been used for
such large window panels. It was the tower windows’ unprecedented size (and
the consequent increase in thermally induced deformations) that brought the
design flaw to the fore. Because this flaw was integral to the window design,
it couldn’t be fixed. All 10,344 panels had to be removed and replaced with
single-pane, heat-treated windows.
Lessons Learned
The three structural engineering issues associated with this case demonstrate
that any departure from established engineering practice incurs a risk that
unforeseen problems will emerge. The Hancock Tower’s departures from
established practice included its narrow east-west dimension, its use of an all-
glass curtain wall with a rigid frame structural system, and the application of a
double-glazed window system to panels of unprecedented size. Each departure
caused a crisis, yet rigorous responses to these crises resulted in a better building.
The tower’s crises also strongly influenced future engineering practice through
revised design code provisions—and validation of TMD technology as a tool
for controlling wind- and earthquake-induced sway in skyscrapers.
109
11. Dynamic Response: Boston’s Plywood Palace
Reading
Campbell, “Builder Faced Bigger Crisis Than Falling Windows.”
Connor, Introduction to Structural Motion Control.
Dupre, Skyscrapers.
Lago, Trabucco, and Wood, Damping Technologies for Tall Buildings.
Schwartz, “When Bad Things Happen to Good Buildings.”
110
12
Stone Masonry:
Beauvais
Cathedral
Major architectural developments usually
happen in an evolutionary, rather than
revolutionary, manner. But a dramatic
exception to this rule occurred with the
consecration of the reconstructed Abbey
Church of Saint-Denis, viewed as the
originator of Gothic architecture. This
lesson focuses on the subsequent evolution
of Gothic architecture and the Beauvais
Cathedral collapse. The case study explores
typical elements of Gothic structures and the
most likely causes of the cathedral collapse,
which were discovered through techniques
such as photoelastic analysis.
111
12. Stone Masonry: Beauvais Cathedral
The Beauvais
Cathedral’s
Design Eugène Viollet-le-Duc
The second story is the triforium, an open gallery that encircles the choir
and apse above the arcade. The third level is the clerestory, in which large
arched windows fill the spaces between the piers. From the tops of these piers,
transverse arches span the choir. They provide structural support for the
ribbed vaults comprising the cathedral’s curved stone ceiling.
113
12. Stone Masonry: Beauvais Cathedral
Groined Vaulting
In a general sense, a vault is an arch extruded into the third dimension to
create a curved surface that encloses space. But this structure, called a barrel
vault, is architecturally problematic because it must be supported on solid
walls and admits light from only two directions. These limitations can be
overcome by intersecting two barrel vaults and removing the unwanted
material to create a groined vault. This allows for natural illumination on all
four sides and can be supported on piers rather than on walls.
` Second, they added diagonal ribs along the intersections between the vaults’
curved surfaces. These ribs enhance structural efficiency because their
strengthening effect allows for thinner, lighter vaulting.
The Arch
In Gothic cathedrals, vaults serve as the ceiling of the interior space but
not the roof of the building. The roof is an elaborate timber truss structure
that supports a wooden deck covered with an outer layer of lead sheeting—
all designed to protect the underlying stonework from weather-related
deterioration and leaks.
Therefore, the arch can span a large horizontal distance with many stones of
relatively small size, making it ideal for masonry construction. But when an
arch is loaded, its outer ends tend to splay outward. This tendency—lateral
thrust—must be rigidly restrained, or the arch won’t be capable of carrying
load. Thus, with two blocks restraining its lateral thrust, an arch can easily
carry thousands of pounds; yet, when you remove one restraint, a slight
application of load is enough to trigger a collapse.
This is how an arch works when supported on a rigid surface, but in a Gothic
cathedral, the arches are perched on top of tall piers. If you erect two piers,
prop the centering on top of the piers, and assemble the arch, even with the
centering in place, the arch’s lateral thrust will cause the piers to tip outward.
If you try to drop the centering, the arch cannot stand.
One solution is to reinforce the piers with external elements called buttresses,
which add width and mass to prevent the piers from tipping outward in
response to the arch’s lateral thrust. Now, when you rebuild the arch and
115
12. Stone Masonry: Beauvais Cathedral
remove the centering, the arch remains stable. This approach was often used
in smaller Gothic churches. In this structural system, the slender interior
piers are integrated with heavy external buttresses that support the arches
and vaults. But this is architecturally unsuitable for a large cathedral because
buttresses wide enough to resist the thrust of a cathedral’s high vaults would
block the aisles on either side of the central space.
This arrangement was used because Beauvais Cathedral has two aisles on either
side of the choir. Rather than having each flyer span across both aisles, the
designer added the intermediate buttresses to cut the flyers’ span in half. These
intermediate buttresses are the upward extensions of the interior piers that separate
the two aisles. This structural system is impressive because it was implemented
with a construction material that has essentially zero strength in tension.
Stone does have moderate tensile strength. But in stone masonry, the weak
link is the mortar used to join the stone blocks together. Medieval mortar was
a mixture of lime, sand, and water, used to join stone blocks together in a way
that effectively transmitted compressive forces down through the structure.
But if stone masonry is subjected to any significant internal tension, it pulls
116
12. Stone Masonry: Beauvais Cathedral
The physical evidence also indicates that several original elements of the
structural system were rebuilt after 1284, presumably because they failed or
were damaged during the collapse. Specifically, all six vertical elements in one
transverse frame—two main piers, two intermediate buttresses, and two outer
buttresses—were repaired or reconstructed after the failure. This strongly
suggests that the collapse involved a structural failure somewhere within
this frame. Of the four transverse frames that supported the original choir
vaulting, this is the only one that didn’t receive supplemental lateral support
from either the chevet or transept.
117
12. Stone Masonry: Beauvais Cathedral
The most famous theory on the cause of the Beauvais collapse was proposed
by Viollet-le-Duc. He hypothesized that prior to 1284, the exterior portion of
the clerestory piers had incorporated an open niche located immediately below
the lower flyer. This feature, he claimed, was the point of weakness at which
the collapse originated—because the slender stone columns were too weak
to bear the weight of the statue placed in a similar niche immediately above
the flyer. As proof, Viollet-le-Duc noted that the lower niches had been filled
in with solid stone after the collapse—presumably to correct the structural
weakness that caused the collapse.
` First, Mark could find no clear physical evidence that the proposed niches
ever existed. In other words, the piers are solid stone today because they
have always been solid stone.
` Second, his structural analysis showed that even if the niches had existed,
they wouldn’t have compromised the piers’ stability.
In an attempt to address this final issue, art historian Paul Frankl has
suggested that the collapse might have been caused by settlement of the
cathedral’s foundations. This explanation is plausible because settlement
can occur over a long period of time and cause structural distress in stone
masonry. But Frankl’s theory also fails for lack of physical evidence.
Archaeological investigations have probed the cathedral’s 30-foot-deep
foundations and found no signs of settlement or settlement-induced cracking.
118
12. Stone Masonry: Beauvais Cathedral
Photoelastic Analysis
Mark performed a structural analysis of Beauvais Cathedral using
photoelastic modeling. In this technique, a two-dimensional scale model
of the structure is fabricated from a special type of transparent plastic and
subjected to scaled loads representative of the actual loads applied to the full-
scale structure. Under polarized light, the plastic model displays a pattern of
colors that can be mathematically interpreted to determine the internal forces
in the structure.
Based on these results, Mark proposed that over time, occasional strong
windstorms caused the cracks at these locations to extend progressively farther
inward from both sides. Eventually, the mortar joints of one intermediate
buttress deteriorated so badly that the buttress broke away from its support
and toppled, carrying its four supported flyers along with it. Deprived of
resistance to lateral thrust, the choir vaults collapsed. Four aspects of the
medieval post-collapse reconstruction would be perfectly logical responses to
Mark’s proposed collapse mechanism:
` First, the added piers are now carrying a portion of the vaults’ lateral thrust
and have reduced the horizontal loads applied to the original buttresses.
` Second, the rebuilt intermediate buttresses are significantly wider than the
surviving originals.
119
12. Stone Masonry: Beauvais Cathedral
` Finally, the entire flying buttress system has been reinforced with iron rods
that restrain the buttresses’ tendency to tip outward.
After this second catastrophe, resources ran dry, and construction of the
Beauvais Cathedral stopped forever. However, Beauvais Cathedral is a
monument to the empirical engineering tradition of the medieval master
120
12. Stone Masonry: Beauvais Cathedral
Reading
Courtenay, The Engineering of Medieval Cathedrals.
Eakin, “Cybersleuths Take On the Mystery of the Collapsing Colossus.”
Mark, Experiments in Gothic Structure.
Mark and Clark, “Gothic Structural Experimentation.”
Murray, “The Choir of the Church of St.-Pierre, Cathedral of Beauvais.”
Wolfe and Mark, “The Collapse of the Vaults of Beauvais Cathedral
in 1284.”
121
13
Experiment
in Iron: The
Ashtabula Bridge
Welcome to the second in this course’s series
of case studies involving failures to design
for adequate resistance—phase 4 of the
structural design process. The Ashtabula
Bridge disaster is worth studying as an
important milestone in the ongoing transition
of engineering from a craft-based occupation
to a learned profession. This lesson covers
the bridge’s design, the multiple problems
that occurred in its conception and
construction, and the collapse mechanisms
that led to the disaster.
122
13. Experiment in Iron: The Ashtabula Bridge
Amasa Stone
The central figure in this case is Amasa Stone. At age 21, he started working
for his brother-in-law, William Howe, a construction contractor. The
following year, Howe earned great notoriety for developing and patenting a
123
13. Experiment in Iron: The Ashtabula Bridge
124
13. Experiment in Iron: The Ashtabula Bridge
The only tool Stone had was the Howe truss. Thus,
he decided that the new, all-iron Ashtabula Bridge
would be a Howe truss structure. But he lacked the
fundamental scientific knowledge needed to
adapt a characteristically wooden structural
system to a different structural material.
Squire Whipple
125
13. Experiment in Iron: The Ashtabula Bridge
For the verticals and bottom chords, this configuration was appropriate
because these are tension members. A tension member’s strength is directly
proportional to its total cross-sectional area. Thus, subdividing one tension
member into several parallel elements doesn’t reduce its total strength and has
the advantage of improved redundancy. But for compression members—like
the top chords and diagonals of a Howe truss—strength is controlled by the
buckling failure mode. This depends on both the member’s cross-sectional
area and its geometric shape.
126
13. Experiment in Iron: The Ashtabula Bridge
The Problematic
Top-Chord Connections
Another unorthodox feature of Stone’s design was the configuration of the
top-chord connections. Conventional iron trusses of that era used mechanical
fasteners—pins or rivets—to connect the members and transmit internal
forces between them. But in Stone’s design, internal forces were transmitted
between the top-chord I beams and the remainder of the truss by rectangular
lugs, projecting upward from the cast-iron angle blocks. Each I beam
extended across two panels of the truss. Thus, its internal compression was
transmitted into the truss at every other angle block. The I beams were held
in position only by the post-tensioned verticals, which applied a downward
clamping force through gib plates. These connections relied entirely on
friction between the I beams and angle blocks and were less reliable than
conventional mechanical fasteners.
127
13. Experiment in Iron: The Ashtabula Bridge
bear only on the first, third, and fifth angle blocks. Thus, two additional top-
chord elements, extending between the second and fourth angle blocks, must
be added.
If the falsework was removed right now, the structure would fall apart. To
prevent this, all of the chords, diagonals, and verticals must be tied together
by adding a gib plate on top of each vertical rod and securing these plates with
nuts. Now, the vertical rods must be post-tensioned. As each rod is tightened,
it compresses the adjacent diagonals, as intended. But because the top-chord
angle blocks aren’t locked into the top chord, post-tensioning also causes the
entire truss to arch upward slightly.
This upward bending causes the top-chord angle blocks to move apart—and
this causes the top-chord elements to loosen. A gap forms between the top
chord and its supporting angle block. The only way to bring these top-chord
elements back into bearing on the angle block lugs is to remove the falsework
and allow the bridge’s weight to bend the truss downward. This structure is
now assembled and capable of carrying additional loads. However, there are
three significant issues:
` The truss is held together almost entirely by friction. The only mechanical
connections in the entire structure are the vertical rods passing through
the angle blocks.
the timber falsework that would support the iron trusses as they were
assembled. Initially, assembly of the trusses went well thanks to the high-
quality detailing Tomlinson performed before he was fired. Tomlinson had
specified that the trusses would have a six-inch camber to offset the estimated
six-inch sag that would occur after the falsework was removed and the bridge
began supporting its own weight. To camber the trusses, the top-chord
members had to be fabricated slightly longer than their planned final length.
Tomlinson had worked out the required dimensions before he was fired.
But with Tomlinson gone and the trusses nearly complete, Stone decided that
the planned six-inch camber was too large. He ordered it reduced to three
inches. This reduction should have been accomplished by shortening the top
chords, but instead, the vital angle block lugs were shaved down. This reduced
their thickness by about one-quarter inch—and reduced their strength by
about 15%.
After the trusses were post-tensioned and the falsework removed, the bridge
sagged six inches, just as Tomlinson had predicted. But because Stone had
reduced the camber, the deck was now sagging nearly three inches below
horizontal. Stone ordered the falsework reinstalled and the camber restored
to six inches. But now, because the lugs had been reduced in thickness, iron
shims had to be driven into the gaps between the lugs and top-chord I beams,
guaranteeing that these members would work loose over time.
Post-tensioning Issues
The construction workers also experienced difficulty implementing the post-
tensioning process. Consider the use of a threaded rod with a steel angle at
each end to post-tension four parallel wooden bars, one of which is slightly
shorter than the others. Wood is about 20 times more flexible than iron,
meaning it deforms more in response to a given load. Thus, when a modest
post-tensioning force is applied to the metal rod, the three longer wooden
bars shorten enough to close the gap. The shorter bar is brought into bearing
against the end angles to create a tight joint. But with four iron bars, one of
which is slightly too short, it is physically impossible to apply enough post-
tensioning force to close the gap and bring the shorter member into bearing.
In a truss, either the slightly short element would remain loose and eventually
129
13. Experiment in Iron: The Ashtabula Bridge
fall out, or an ironworker would keep tightening until the three longer
elements buckled under compressive loading. Both problems occurred during
the Ashtabula Bridge’s construction.
Moreover, when the falsework was removed for the second time, several
diagonals buckled under the bridge’s own weight. Stone restored the falsework
again and increased the number of diagonal I beams from four to six in the
trusses’ outermost panels. To accommodate this change, the I beams had to be
rotated 90 degrees to allow for closer spacing. Portions of their flanges had to
be cut away to prevent interference with the vertical rods. More importantly,
the small lugs—which had been cast into the angle blocks to hold the I beams
in position—had to be chiseled off to accommodate the 90-degree rotation.
The diagonals would now be held in position by friction alone.
However, the successful load test masked deep structural flaws. As the years
passed, there were warning signs. A railroad inspector discovered that a
diagonal brace had worked loose. Locomotive operators reported hearing
snapping sounds while crossing the bridge. But these warnings went unheeded
until the bridge collapsed.
130
13. Experiment in Iron: The Ashtabula Bridge
sheared off. Based on its position within the wreckage, he identified it as the
second block from the western end of the southern truss. And on the failure
surface, he noted a large internal air void—a common defect in cast iron.
On this particular angle block, it was a fatal flaw. The two lugs on the
second angle block from the end of each truss were the most heavily loaded
in the entire structural system. The large internal shear force, casting defect,
and thickness reduction during construction caused extreme stresses in
this structurally critical lug. These stresses inevitably initiated a fatigue
crack that elongated slightly with each passing locomotive until it reached
a critical length and fractured. The extremely low temperature on the night
of the disaster made the cast iron even more brittle than usual, increasing its
susceptibility to fracture.
When one lug broke off, its associated top-chord element was disconnected
from the truss and could no longer carry load. Consequently, this parallel
element was instantly subjected to twice the compressive force—and buckled.
At this point, the truss might still have survived if not for the fact that the
lateral bracing system was only connected to every other angle block. Thus,
the block with the failed lug was laterally unbraced. Because it was now
asymmetrically loaded, it displaced violently outward as its overloaded I beam
buckled. Once the angle block displaced sideways under the weight of two
locomotives, the southern truss folded up, came apart at the joints, and spilled
the remainder of the structure into the gorge.
Inquiry Results
The Ashtabula disaster was triggered by a set of circumstances for which
Stone cannot legitimately be blamed. An internal, undetectable fabrication
defect caused a single cast-iron lug to fail by fatigue, which no one fully
understood at the time. Yet Stone certainly was responsible for the bridge’s
inadequate margin of safety, ill-conceived structural concept and connection
configurations, poorly designed bracing system, ad hoc modifications during
construction, and consequent inability to survive the loss of a single lug.
The coroner’s jury reached a similar conclusion—that the bridge was poorly
designed and poorly built and that Stone was principally responsible for
its collapse. But MacDonald wrote that Stone shouldn’t be vilified because
131
13. Experiment in Iron: The Ashtabula Bridge
knowledge about iron bridges was limited at the time he designed the
structure. Furthermore, Stone had responded decisively to the many problems
encountered during construction, and his completed bridge passed its load
test and all subsequent inspections.
Lessons Learned
The Ashtabula disaster had little impact on subsequent engineering practice.
Stone’s design was so uniquely and obviously flawed that contemporary
engineers could learn little from its failure, nor were government bodies
willing to enact legislation to prevent future failures of this sort. The Ohio
legislative committee that investigated the collapse drafted a bill that
specified bridge design standards, required an expert review of all designs,
and mandated periodic inspections of in-service bridges. But the Ohio
legislature declined to take it up. Meanwhile, within a year of the disaster, the
Lake Shore and Michigan Southern Railway had designed and constructed
a replacement bridge at Ashtabula. Stone’s iron bridge was replaced with a
wooden Howe truss structure.
Reading
Gasparini and Fields, “Collapse of Ashtabula Bridge on December
29, 1876.”
Griggs, “Charles Macdonald.”
Macdonald, “The Failure of the Ashtabula Bridge.”
132
14
Shear in
Concrete: The FIU
Pedestrian Bridge
It seems that even as engineered systems
have changed over time, their underlying
causes of failure tend to recur. Today’s
powerful tools imbue engineers with the
confidence to try unorthodox design
concepts, which exposes unexpected
vulnerabilities. Addressing these challenges
requires the most sophisticated engineering
tool of all—human judgment. And as
the Florida International University (FIU)
Pedestrian Bridge case demonstrates, this
tool remains as fallible as ever. This lesson
concerns the various engineering and
organizational oversights that led to the FIU
Bridge collapse.
133
14. Shear in Concrete: The FIU Pedestrian Bridge
At 1:46 pm on March 15, the truss collapsed without warning, crushing five
vehicles beneath it and seriously damaging three more. One construction
worker and 5 vehicle occupants were killed, and 10 others were injured.
Project Organization
This project was organized using the design-build system. FIU hired MCM (a
Miami-based construction management firm) to implement the entire project
from concept through completion. MCM contracted with FIGG to design
the structure. FIGG selected Louis Berger, a large engineering company, to
perform a peer review of the final design. FIU didn’t have any engineers on
staff and hired another engineering consultant—Bolton Perez & Associates—
to provide construction oversight and inspections. Because the bridge would
cross a public highway, the Florida Department of Transportation (DOT) and
the Federal Highway Administration provided governmental oversight.
134
14. Shear in Concrete: The FIU Pedestrian Bridge
Finally, the landings, stairways, and elevators were constructed. The spans
were completed with the installation of curbs, expansion joints, and drainage
fixtures. The drainage system included catch basins. These channeled
rainwater into a drainpipe running along the bottom of the deck, through the
diaphragms, and into the local storm sewer.
135
14. Shear in Concrete: The FIU Pedestrian Bridge
Post-tensioning
The most challenging design aspect was the use of long-span trusses made of
reinforced concrete. Concrete is strong in compression but has zero strength
in tension. Thus, in modern structures, concrete is always strengthened with
rebars. If you load a reinforced-concrete member in tension, it carries the
load—but the rebar does all the work. As the steel stretches, the concrete
cracks and can no longer participate in load-carrying. Thus, in a reinforced-
concrete tension member, the concrete is structurally superfluous. This
issue can be overcome using post-tensioning to prevent the cracking. When
the rod is tensioned, the concrete is compressed. Now, when the member is
loaded, both materials participate in load-carrying. As long as the applied load
doesn’t exceed the initial post-tensioning force, the concrete will remain in
compression—and won’t crack. This is what made the FIU bridge’s innovative
concrete trusses possible.
Post-tensioning
Members 2 and 11
As a general principle, any member that will experience internal tension
under any circumstance must be post-tensioned. Because of the FIU Bridge’s
complex construction sequence, four different circumstances determined
which members required post-tensioning. First, with the main truss
supporting its own weight, tension would occur in the bottom chord and in
the members numbered 3, 5, 8, and 10 on the engineering drawings. Second,
while the truss was being moved into position, members 2 and 11 would
temporarily experience tension due to the outer panels of the truss extending
out beyond the transporters. Third, when the two spans were subsequently
136
14. Shear in Concrete: The FIU Pedestrian Bridge
The cylindrical caps on the outer ends of the span and the angular blisters
on top of the canopy were anchorage points for post-tensioning tendons
in the deck and canopy and post-tensioning rods in the diagonals. All
diagonals would also receive three types of conventional steel reinforcement—
longitudinal and transverse rebars and shear reinforcement at the interfaces
between the diagonals and chords. In the truss, the most severe internal
shear force occurred at the ends of the span, where the vertical and diagonal
members joined the deck.
137
14. Shear in Concrete: The FIU Pedestrian Bridge
By mid-February 2018, all pours were complete, and the concrete had cured
sufficiently for the post-tensioning to be applied. Then, on February 24,
the supporting falsework was removed. As the truss began carrying its own
weight for the first time, workers heard a loud noise and discovered that large
cracks had developed along the cold joint at node 11/12 and at the equivalent
location on the opposite end of the truss. Bolton Perez reported the problem
to MCM. MCM emailed photos of the cracks to FIGG’s Tallahassee office
and requested guidance. FIGG responded that the cracking wasn’t significant
and could be patched up later.
On March 10, immediately after the main span was transported to the bridge
site, members 2 and 11 were de-tensioned as planned. During this operation,
the existing cracks along node 11/12 opened significantly wider, and a
network of finer cracks developed on the outer faces of member 12 and the
diaphragm. The cracking was particularly severe at five penetrations through
the concrete—a drainpipe, which passed horizontally through the diaphragm,
and the two vertical ducts on each side of member 12.
MCM didn’t report these issues to FIGG for two full days. But after receiving
the MCM report on March 13, the engineers assured the contractor that the
cracking was “not a safety issue.” Indeed, some cracking is to be expected in
reinforced concrete. Steel reinforcement must elongate in tension, which often
causes small cracks in the adjoining concrete. Design codes specify that such
cracks are permissible if small. A typical standard is a maximum permissible
crack width of 0.016 inches. But by this time, the cracks in the FIU Bridge
were 40 times larger than this standard.
138
14. Shear in Concrete: The FIU Pedestrian Bridge
Ill-Advised Re-tensioning
On the evening of March 13, FIGG’s engineers recommended to MCM that
member 11 be re-tensioned—even though it had been de-tensioned three
days earlier. The reasoning was that de-tensioning member 11 had made
the cracking worse. Thus, re-tensioning should restore the member to its
previous, less dangerous condition. But it wasn’t reasonable to expect that
the application of a large post-tensioning force would have the same effect as
it did when the concrete was in pristine condition and the bridge was fully
supported on falsework.
Inquiry Results
The National Transportation Safety Board (NTSB) was immediately called
in to investigate and released its final report in October 2019. Thanks to a
dashcam video that captured the entire incident, the investigators confirmed
that the collapse was triggered by a catastrophic shear failure in the node
11/12 region of the truss. The cause of this failure was equally clear—the
design of the shear reinforcement in the node’s cold joint was inadequate.
As the NTSB’s analysis demonstrated, the internal shear force predicted
by FIGG’s structural analysis was too low. Moreover, due to a subtle
misinterpretation of the governing bridge design code, FIGG’s prediction
139
14. Shear in Concrete: The FIU Pedestrian Bridge
of the shear strength was too high. Both the structural response and node
resistance were incorrectly calculated. Consequently, the joint was overloaded
by about 60%. This was exacerbated by poor detailing of the critical node.
The node’s strength was also compromised by flawed construction of the cold
joint. Design codes specify that the lower surface of the joint should have
been artificially roughened before the concrete above it was cast to improve
the mechanical bond between the two layers of concrete and help resist
shearing. But investigators found that the cold joint at node 11/12 hadn’t been
roughened. FIGG blamed MCM for this error. However, as the NTSB report
noted, the engineering drawings didn’t specify that roughening was required
at this joint, and FIGG must also bear some responsibility for this deficiency.
Also, the failure sheared off only three of the four rebar loops. The fourth
loop was contained within a small wedge of concrete that remained attached
to the deck. Cracks are adept at exploiting weaknesses—and this one found a
trajectory that bypassed 25% of the vital shear reinforcement. Better detailing
of the rebar would have prevented this issue too.
The Florida DOT policy requires an independent peer review of all new,
complex, or nonstandard bridge types. Fulfillment of this requirement should
have averted the disaster, but this opportunity was squandered though flawed
implementation of the peer-review process.
Contributing Factors
MCM was required by contract to provide verification of the design at its own
expense. To minimize this expense, MCM and FIGG agreed that FIGG would
do the peer review in-house, achieving the required independence by assigning
the task to a FIGG office other than the one designing the bridge. However,
Florida DOT informed FIGG that the independent review had to be done by
an outside engineering firm with no project involvement. Neither MCM nor
FIGG had included the cost of an outside consultant in their project planning.
FIGG requested bids for the job and received proposals from three different
firms. Louis Berger initially submitted a bid to perform the work in 10 weeks
for $110,000 but agreed to a reduced fee of $61,000 and a project time frame
of 7 weeks. Faced with these significant constraints on their compensation and
time, Berger’s engineers reviewed only the design of the completed structure
140
14. Shear in Concrete: The FIU Pedestrian Bridge
Although the NTSB found FIGG primarily responsible for the collapse, it
also faulted MCM, Bolton Perez, FIU, and the Florida DOT for continuing
construction activities and failing to stop traffic as soon as the unexplained
cracking reached unacceptable levels. Despite having eyes on the developing
crisis—and the authority to make independent judgments about public safety—
they repeatedly deferred to the structural engineer. In this sense, the FIU Bridge
disaster was as much an organizational failure as an engineering failure.
` Like the Millennium Bridge, the FIU case featured a daring structural
concept from which unanticipated problems emerged.
` Like the Ashtabula Bridge, the FIU Bridge was an unorthodox, post-
tensioned truss made of a material ill-suited to the structural configuration.
` Like the Cypress Structure, the FIU Bridge had serious deficiencies in the
shear reinforcement of a concrete connection.
` Like the Tay and Ashtabula bridges, the FIU case involved a construction
flaw at which the collapse originated.
` Like the Kansas City Hyatt case, structural distress was observed and
reported by construction workers—to no avail.
141
14. Shear in Concrete: The FIU Pedestrian Bridge
Reading
National Transportation Safety Board, Pedestrian Bridge Collapse over SW
8th Street, Miami, Florida.
US Department of Labor, Investigation of March 15, 2018 Pedestrian Bridge
Collapse at Florida International University.
142
15
House of Cards:
Ronan Point
Modular building systems comprising
reinforced concrete were popularized in
post–World War II Europe as a low-cost
solution to a severe housing shortage. The
use of one such system in the UK led to the
next epic engineering failure studied in this
course—the Ronan Point tower collapse. This
lesson introduces the Larsen-Nielsen system
and discusses how its various construction
discontinuities and vulnerabilities, such as
lack of redundancy, led to the May 1968
collapse of Ronan Point.
143
15. House of Cards: Ronan Point
Modular Buildings
The Larsen-Nielsen system was used extensively in the UK through the 1960s.
Its modular reinforced-concrete components were manufactured in a factory,
transported to the project site, and assembled into complete building structures.
Wall panels were fastened to floor slabs using various mechanical connectors.
These modules were then stacked to create multistory buildings. The system’s
most distinctive aspect was its lack of a traditional structural frame. It used no
beams or columns—only walls and floor slabs joined edge to edge.
Ronan Point was a typical late-1960s application of this system. The 22-story
tower housed 110 compact apartment units, 5 per floor. On each floor, two
reinforced-concrete walls formed a north-south corridor that also served as a
structural spine. Perpendicular walls extended outward from the spine to create
interior partitions, exterior walls on the building’s north and south faces, and
enclosures for the elevators and stairwell. These walls were all load-bearing. Each
story also included secondary non-load-bearing partition walls and non-structural
east and west façades, composed largely of windows and balconies. When these
modules were stacked, the load-bearing walls
formed uninterrupted vertical load paths for
the transmission of gravity loads down to the
ground-floor podium and foundation.
144
15. House of Cards: Ronan Point
load-bearing south wall. With its structural support compromised, the floor
slab immediately above her flat—the 19th floor—failed along this line and
collapsed. This initiated a chain reaction that propagated all the way to
the roof.
The five failed slabs pancaked onto Hodge’s living room floor in rapid
succession, initiating a second chain reaction in the opposite direction.
The impact of the falling slabs collapsed the 18th-floor slab, sending six
slabs crashing down onto the 17th floor, seven slabs onto the 16th, etc. The
destruction continued down to ground level. In the end, the entire southeast
corner of Ronan Point lay in a heap of rubble.
The Griffiths inquiry also determined that Ronan Point’s design was in full
compliance with the governing building code, Building Regulations. But the
code was out of date in several ways that contributed directly to the disaster.
One indicator of its inadequacy was that the gas explosion that brought down
Ronan Point wasn’t particularly powerful. The blast overpressure in Hodge’s
kitchen was less than 10 psi. Several pieces of physical evidence helped
characterize the explosion’s nature and severity. Three biscuit tins, which had
been stored in Hodge’s kitchen cupboard, were found to be buckled inward.
Laboratory experiments demonstrated that an overpressure of 3 to 9 psi would
have been required to cause this damage. A fuse box cover in the hallway
was also severely buckled. This level of damage was found to have required a
pressure of 12 psi—the highest blast overpressure generated by the explosion.
145
15. House of Cards: Ronan Point
By the time Hodge got out of bed, the gas concentration at the hallway ceiling
had reached about 5%—high enough to be ignitable. When Hodge struck
her match, the resulting burst of flame followed the same path as the gas into
the hall. As the flame front advanced, the combustion process accelerated,
and the blast overpressure increased. Thus, initially, the explosion was mostly
flame and relatively less blast pressure. The pressure didn’t reach its peak of 12
psi until the flame front was well into the hallway.
The exterior walls on the opposite side of the apartment were completely
dislodged from the structure. But the interior wall between the kitchen and
living room wasn’t damaged by the blast that originated only a few feet away
because the explosion was centered in the hallway. As the blast propagated
outward from this location, it produced nearly equal overpressures in the
kitchen and living room. These pressures counterbalanced each other; thus,
the net lateral force on the interior wall was small. But the overpressure
was applied to only one side of the exterior wall panels, more easily
dislodging them.
Indeed, testing demonstrated that the exterior walls of Hodge’s flat would
have been blown out by an internal overpressure of less than 3 psi. Force
equals pressure times area. The load-bearing south wall measured 8 feet tall
and 27 feet wide. Thus, the outward force due to a pressure of 3 psi acting on
this wall would have been more than 93,000 pounds. But from a structural
engineering perspective, it shouldn’t be possible for a minor gas explosion to
dislodge a load-bearing wall on which an entire high-rise structural system
depends. It happened at Ronan Point because of a design flaw in the Larsen-
Nielsen system—an inadequate connection between the exterior wall panels
and floor slabs.
146
15. House of Cards: Ronan Point
Story Construction
To erect each story of the tower, the nine-foot-wide wall panels were first
lifted into position, suspended from two embedded steel lifting rods. Adjacent
wall panels were joined by inserting a steel rebar through steel loops and
filling the gap between the panels with cast-in-place concrete. The floors
comprised hollow-core slabs—so named because cylindrical cavities were
cast into each unit to reduce its weight. These slabs were positioned on a shelf
at the top of the wall panels and joined edge to edge with rebar and concrete.
Each slab was mechanically fastened to its supporting wall panel by two
factory-installed steel ties. The ties were anchored to the lifting rods within
each wall panel and secured to the slab with a bolt driven into an embedded
metal sleeve.
147
15. House of Cards: Ronan Point
outward, this thin concrete layer burst, allowing the rods to bend inward and
rendering the ties largely ineffective. Second, the upper ends of the lifting
rods extended into the bottom of the upper wall panels, creating a mechanical
connection that should also have resisted the wall’s outward displacement. But
the rods’ inward bending compromised this mechanism too. Thus, the only
remaining source of resistance was friction along these two horizontal surfaces.
But friction is a highly unreliable source of structural resistance.
The interface at which frictional resistance might have prevented the blowout
comprised two horizontal surfaces—one between the 18th- and 19th-floor
wall panels and one between the 18th-floor wall panel and the 19th-floor
slab. In general, frictional resistance at the interface between two surfaces
depends on the compressive force applied perpendicular to the surfaces.
More compression causes more frictional resistance. The compressive force
transmitted across this interface resulted from the gravity loads applied above
that level—the weight of wall panels and slabs on these four stories, plus
all associated occupancy loads. Thus, you might expect that the resulting
frictional resistance to outward movement of the wall panel would have been
large enough to prevent a blowout.
Unfortunately, the blast in Flat 90 didn’t only push Hodge’s living room
wall outward—it also pushed her ceiling upward. And an upward force on
the ceiling at any given level effectively lifts the entire structure above that
level, causing a corresponding reduction in the compressive force across this
interface. Consequently, in the Larsen-Nielsen structural system, frictional
resistance to a blowout varies with elevation. On the 18th floor, the weight
of only four higher-level floors wasn’t sufficient to generate enough frictional
resistance to prevent a wall panel blowout.
Lack of Continuity
and Redundancy
The investigators recognized that the entire tower was highly vulnerable not
just to internal blast loading but also to the effects of wind and fire. When a
tower is subjected to wind loading, it bends—resulting in compression on the
148
15. House of Cards: Ronan Point
downwind side and tension on the upwind side. And if the tower is made of
discrete elements, these elements tend to pull apart on the upwind face and
along the sides.
To some extent, this tendency is offset by the building’s weight. Yet, even
if wind loading doesn’t cause a net tension force at the interfaces between
segments, it does reduce the gravity-induced compression across these
interfaces. Reduced compression causes a corresponding reduction in
frictional resistance along the slab-to-wall connections. This is worrisome
for two reasons: First, as wind flows around a building, it can create a strong
outward suction force on some wall surfaces. Second, at that time, the
governing 1952 edition of the UK Building Regulations specified design wind
loads that were far too low. It failed to consider that wind speed increases
significantly at higher elevations.
Therefore, even though Ronan Point’s design complied fully with the
regulations, an extreme windstorm could create the same conditions that
caused the wall panel blowout of May 1968—an outward force (caused by
wind-induced suction) and reduced frictional resistance at the slab-to-wall
connections (caused by wind-induced bending of the tower). As the blast-
induced failure demonstrated, loss of a few wall panels could easily bring
down the entire structure.
The investigators also found that the slab-to-wall connection was similarly
vulnerable to fire. In an intense fire, the interior faces of concrete walls and
floor slabs heat up and expand; the surfaces oriented away from the fire
remain cooler. This differential heating causes an arching effect, which could
cause enough rotation at the ends of the walls and slabs to compromise the
connections. In this condition, the structure would also be vulnerable to a
wind-induced wall panel blowout—also triggering a global structural collapse.
These issues suggest that beyond the details of its connections, Ronan Point
suffered from two fundamental design deficiencies—lack of continuity
and lack of redundancy. The Larsen-Nielsen system was characterized by
discontinuities at the joints between the floor slabs and wall panels. This
could have been addressed by robust steel interconnections, but the existing
ties were inadequate. The discontinuities inevitably became points of failure.
Furthermore, a single connection failure propagated into a large-scale collapse
149
15. House of Cards: Ronan Point
Webb’s Campaign
After the disaster, the collapsed portion of the tower was rebuilt. In response
to a recommendation by the Griffiths inquiry, steel blast angles were added to
the floor-to-wall connections throughout the building. By providing greater
continuity at these joints, this retrofit improved structural safety. The inquiry
also prompted a major revision to the Building Regulations, which incorporated
improved wind-load provisions and new requirements for blast resistance and
structural redundancy. Furthermore, as these new regulations wouldn’t affect
existing structures, the government also prohibited the use of natural gas in all
Larsen-Nielsen structures and similar modular building systems.
However, an architect named Sam Webb, who had testified in the Griffiths
inquiry, believed many of the tower’s structural inadequacies still hadn’t been
addressed. He embarked upon a campaign to convince the building’s owner—
the Newham Council—that Ronan Point remained a disaster waiting to
happen. In 1986, the council decided to condemn the tower.
The council directed that Ronan Point would be disassembled piece by piece.
Webb witnessed and documented this entire “forensic demolition.” As he
reported, not a single connection in the entire structure had been built in
full compliance with the design specifications. Most of the steel ties hadn’t
been bolted to the floor slabs—and in those that were connected, the bolts
were loose. The concrete fill between the slabs and wall panels was full of
construction debris and air voids. Most seriously, the leveling nuts used to
position the wall panels during construction had never been screwed down
after the mortar fill had hardened. Consequently, each wall panel was
supported on the two leveling nuts. The resulting concentrations of internal
force had caused severe cracking—particularly in the lower-story wall
panels—and compromised the entire structure’s safety.
150
15. House of Cards: Ronan Point
Many structures using similar modular systems were evaluated, and some
were also demolished. Most importantly, research programs were initiated
in the UK and elsewhere to study redundancy, progressive collapse, and
internal blast effects. This yielded improved building-code provisions
worldwide. Today, a major section of the UK Building Regulations is devoted
to specifications for reducing the sensitivity of buildings to “disproportionate
collapse in the event of an accident.”
Lessons Learned
First, this is another cautionary tale about the inherent risk in structural
engineering innovation, where it’s often not feasible to validate new ideas
by testing full-sized prototypes. In trying to solve a severe housing shortage
quickly and inexpensively, the developers inadvertently created a unique
vulnerability to internal blast loading. Imagine how different the case would
have been if the structural system had been a traditional steel or reinforced-
concrete frame, clad with a lightweight curtain wall. Moreover, the Larsen-
Nielsen system was originally developed for buildings no more than six stories
tall. Thus, its use in high-rise towers like Ronan Point was an extrapolation of
an extrapolation.
Reading
Griffiths, Pugsley, and Saunders, Report of the Inquiry into the Collapse of
Flats at Ronan Point.
151
16
Brittle Fracture:
The Great
Molasses Flood
One of the most bizarre structural failures
in history, the Great Boston Molasses
Flood, occurred on January 15, 1919, on the
waterfront of Boston’s North End. The rupture
of a storage tank caused a powerful wave of
more than 2 million gallons of molasses to
rapidly take out at least two city blocks. This
lesson discusses the various phenomena that
led to the tank’s structural failure, including
fatigue, fracture, stress, and strain, as well as
fracture mechanics.
152
16. Brittle Fracture: The Great Molasses Flood
153
16. Brittle Fracture: The Great Molasses Flood
But beyond this elastic region, the curve changes dramatically. A horizontal
plateau indicates that the bar is experiencing substantial elongation with no
increase in load. The steel is stretching like taffy—a phenomenon called yielding,
which marks the onset of material failure. When yielding begins, the specimen’s
154
16. Brittle Fracture: The Great Molasses Flood
By doing these calculations for each data point in the load-deformation curve
and plotting the results, the stress-strain curve is created. Although the shape
of this curve is identical to that of the load-elongation curve, the numerical
values on the axes characterize the generalized mechanical properties of the
material rather than the properties of a specific test specimen. Two properties
are vital for the understanding of this case study:
` First, the stress at which a material yields is called the yield strength—
which, for this type of steel, is 36,000 psi.
155
16. Brittle Fracture: The Great Molasses Flood
Brittleness
The opposite of ductility is brittleness. A brittle material—like cast iron—
never yields. It elongates elastically and fractures suddenly. The fracture strain
of cast iron is in the order of 0.1%—250 times smaller than that of structural
steel. The concept of ductility is important to this case study because brittle
fracture—which doomed the Boston molasses tank—is defined as the non-
ductile failure of a material subjected to tension. In structural engineering,
non-ductile failure is anathema because it occurs without the large plastic
deformations that should provide warning of impending failure.
Under certain conditions, a ductile material like steel can also fail in a brittle
manner—often at a level of stress significantly below the material’s yield
strength. The most important condition under which an otherwise ductile
material might experience a brittle fracture is the presence of an internal
defect or crack. Fracture mechanics was developed to predict the strength of
materials that have preexisting defects.
Fracture Mechanics
The basic principles of fracture mechanics are embodied in a mathematical
model developed by Alan Griffith. The mathematical derivation of Griffith’s
model is based on this idealization—a metal plate that’s subjected to a uniform
tension stress (sigma) and has a through-thickness crack with a length of 2a.
This equation defines the stress intensity factor, K, which equals sigma
times the square root of pi times a. It also defines a material property called
fracture toughness, KC . This is determined by experimental measurement and
represents the critical value of K at which fracture will occur.
Griffith’s criterion states that any time K exceeds KC , the material can
be expected to fail by brittle fracture. We can also apply this equation
qualitatively to identify the three main factors that directly influence a
structural element’s susceptibility to brittle fracture—the tension stress in the
element, the maximum size of a crack or defect, and the material’s fracture
toughness. Griffith’s criterion predicts that the presence of a preexisting
crack will cause a member to fracture at a substantially lower stress than an
156
16. Brittle Fracture: The Great Molasses Flood
157
16. Brittle Fracture: The Great Molasses Flood
Mayville’s Analysis
Consider a plastic bag filled with molasses to simulate the cylindrical tank.
The liquid exerts outward pressure on its container, and the container stretches.
Because this tension is causing the cylinder’s circumference to increase, it’s
called circumferential stress. The container also stretches more on the bottom
than on top. This indicates that the circumferential stress is highest at the
bottom of the cylinder due to the accumulated weight of all the fluid above.
The quality of the steel used to build the tank was probably consistent with
early-20th-century standards, with a chemical composition low in manganese.
Consequently, the steel would have had a relatively high transition
temperature—possibly more than 50°F. The temperature in Boston at the
time of the disaster was about 40°F. Thus, the tank’s fracture toughness
would have been dangerously low at that moment.
158
16. Brittle Fracture: The Great Molasses Flood
Fatigue-Related Cracking:
Shipbuilding
In the shipbuilding industry, the wake-up call came during World War II,
when mass-produced welded steel cargo vessels began experiencing structural
failures at an alarming rate. At least 16 of these ships broke in half and sank,
and more than 1,000 developed serious fatigue-related cracking problems.
` Repetitive stresses were caused by the hulls flexing as they moved across
rough seas.
` Welding embrittled the steel, and these same welded joints also allowed
cracks to propagate easily from one hull component into the next.
` The frigid North Atlantic waters lowered the steel’s fracture toughness to
perilously low levels.
159
16. Brittle Fracture: The Great Molasses Flood
Fatigue-Related
Cracking: Airliners
The aerospace industry had its wake-up call in the case of the de Havilland
Comet, the world’s first jet-propelled commercial airliner—and also one of
the first to use a pressurized cabin. Within two years of its debut, five Comets
crashed, three under circumstances that suggested in-flight structural failures.
Consequently, the entire fleet was grounded.
Reading
Brown, “Details of the Failure of a 90-Foot Molasses Tank.”
Mayville, “The Great Boston Molasses Tank Failure of 1919.”
Puleo, Dark Tide.
Schworm, “Nearly a Century Later, Structural Flaw in Molasses Tank
Revealed.”
160
17
Stress Corrosion:
The Silver Bridge
Welcome to the sixth in this course’s series
of case studies involving failures caused by
inadequate structural resistance. The Silver
Bridge collapse is an especially fascinating
case because the structure was so unique,
the failure investigation was so challenging,
and the long-term consequences were so
profound. In this lesson, you will explore
the bridge’s unconventional design and
the National Transportation Safety Board’s
(NTSB) analysis of the incident, which found
that mechanisms such as chain failure and
corrosion contributed to the collapse.
161
17. Stress Corrosion: The Silver Bridge
162
17. Stress Corrosion: The Silver Bridge
the approach ramps by two short girder spans at each end of the bridge. The
truss spans were suspended from two steel chains secured at anchorages on
both shores and draped between two steel towers.
These chains comprised eyebars, each about 50 feet long, arranged in pairs,
and interconnected with massive steel pins to which the vertical suspenders
were also connected. The eyebars were secured by steel caps, fastened to both
ends of each pin with a bolt. The American Bridge engineers could use so
little material because their eyebar chains were made of a new type of heat-
treated steel that was more than twice as strong as conventional structural
steel. This product had been used in only one previous bridge—Steinman’s
bridge in Florianópolis.
When the Silver Bridge was built in 1928, it was regarded as an engineering
triumph. The design was so successful that an identical bridge was built in St.
Marys, West Virginia. But 39 years later, its acclaimed innovations became its
fatal flaws. Uncovering these flaws was the job of the NTSB, which initiated
its investigation immediately after the collapse.
163
17. Stress Corrosion: The Silver Bridge
First, a failure in the foundation category could have been caused by scour—
the undermining of a foundation by flowing water—or by movement of the
piers or anchorages. However, divers and surveyors found no evidence of scour
or movement. Second, neither the NTSB’s examination of the wreckage nor
eyewitness testimony found any evidence that an external event—a vehicle
collision or sabotage—could have initiated the collapse.
Third, local weather data indicated that at the time of the disaster, the wind
was blowing parallel to the bridge at only 6 mph. This couldn’t have caused
a wind-load failure or wind-induced vibration. Fourth, overstress could have
resulted from several different causes. A design error seemed unlikely because
the bridge had stood for 39 years. Nonetheless, the NTSB reviewed American
Bridge’s original design calculations and found no significant errors or
omissions. The design was in full compliance with the standards of the 1920s.
Failure due to excessive load seemed more likely because the average weights
of automobiles had nearly tripled in the four decades since the bridge
was designed. However, the NTSB’s structural analysis revealed that the
stresses caused by the actual vehicles on the bridge when it collapsed were
significantly less than the stresses for which it had been designed. In short,
there wasn’t enough traffic on the bridge to have caused an overload. The
investigators also noted that the original design hadn’t accounted for the
dynamic effects of moving traffic—for example, the jolt caused by vehicles
crossing an expansion joint. Thus, the NTSB conducted dynamic testing
of St. Marys Bridge. These tests demonstrated that the dynamic structural
response wasn’t large enough to have triggered the collapse.
Chain Failure
Finally, the NTSB focused on the remaining category—a superstructure
defect. The term superstructure refers to the portion of a bridge above its
foundations—in this case, the towers, eyebar chains, suspenders, and trusses.
Each possible cause listed in this category corresponded to a failed component
found in the salvaged wreckage. For example, a suspender designated as
member 17N was found to have fractured; thus, this was considered a possible
cause of the collapse in the logic framework.
164
17. Stress Corrosion: The Silver Bridge
The challenge was distinguishing between the one component failure that
caused the collapse and the many caused by the collapse. The investigators
used the physical evidence and eyewitness accounts to reconstruct the collapse
sequence and trace this sequence back to its point of origin. They discovered
that both towers had fallen toward the east. The Silver Bridge towers were
mounted on pivoting supports designed to accommodate unbalanced loads.
As such, they were held erect entirely by the eyebar chains. Any chain failure
would have caused both towers to fall.
The failure of a truss member or suspender couldn’t have toppled both towers,
suggesting that a chain failure was the culprit. But a chain failure in the
center span would have caused the towers to fall in opposite directions. Only
a chain failure within the western side span could have caused both towers to
fall toward the east. This insight was a significant breakthrough—especially
because there was only one broken eyebar within the entire western side span.
Designated as eyebar 330 on the design drawings, it had fractured through its
outer pin hole.
Eyebar 330
The emerging hypothesis—that the fracture of eyebar 330 had initiated the
collapse—was confirmed by the NTSB’s analysis of the collapsed structure.
It demonstrated that the positions, deformations, and local failures of all
structural components were fully consistent with a collapse sequence that
began with the fracture of eyebar 330. To determine what had caused the
fracture, the NTSB retained five testing laboratories to perform mechanical
and metallurgical tests on the eyebar material. The results were conclusive.
Eyebar 330 failed when a tiny existing crack, located on the inner surface
of the pin hole, became critical and initiated a brittle fracture. The crack
was only one-quarter inch long and one-eighth inch deep. According to the
principles of fracture mechanics, a crack with such a short length, a, could
only become critical if the stress, sigma, was extremely high, or the fracture
toughness, KC , was extremely low. Eyebar 330 had both of these conditions.
165
17. Stress Corrosion: The Silver Bridge
The stress at the crack location was high because of a severe stress
concentration caused by the hole in the eyebar. Its effect was seen in large
distortions along the sides of the hole. More importantly, the innovative steel
used for these eyebars had dangerously low fracture toughness—especially at
the subfreezing temperatures the structure experienced on December 15, 1967.
Corrosion
The NTSB’s structural analysis showed that the stress in eyebar 330 was
caused primarily by the bridge’s unchanging weight. Ultimately, metallurgical
testing revealed that the crack in eyebar 330 was caused by stress corrosion
cracking. Corrosion—often encountered as rust—is the gradual destruction
of metal by a chemical reaction with its environment. In steel structures, the
resulting destruction of intact material can severely weaken a member.
Stress corrosion requires not only corrosion but also sustained tension stress.
At the microscopic level, metals are composed of crystals, called grains.
When a metal is subjected to tension, the grain boundaries pull apart slightly.
Under certain environmental conditions, corrosion can develop within the
voids between the grains. As the by-products of corrosion accumulate, they
force the grain boundaries farther apart, creating tiny cracks. Corrosion can
also promote the long-term growth of the cracks, even under low levels of
repetitive stress.
166
17. Stress Corrosion: The Silver Bridge
the asymmetrically loaded pin rotated sideways, the pin cap broke off, and
the remaining eyebar slipped off the pin. With the chain now broken, a
progressive collapse of the entire structure was inevitable.
The NTSB’s final report also cited two additional factors that contributed
significantly to the disaster. First, the eyebar connection configuration was
deeply flawed. The narrow gaps between the eyebars and pin were breeding
grounds for corrosion—and their interior surfaces were inaccessible and
hidden from view. Thus, neither corrosion nor cracking could have been
detected without disassembling the connection. Under these conditions, a
connection failure was inevitable. Second, with its pivoting tower supports,
hybrid truss configuration, and use of eyebar chains with only two eyebars per
link, the structural system was nonredundant for no reason. Steinman’s bridge
at Florianópolis used four eyebars per link rather than two. Thus, it would
almost certainly survive the failure of one eyebar.
As such a beam bends, the abrupt termination of the cover plate causes a
major stress concentration at the transverse weld. This stress concentration—
combined with internal defects and residual tension in the weld itself—
practically guaranteed that fatigue cracks would develop at this location. In
the Yellow Mill Pond Bridge, one of these cracks was so severe that it fractured
and nearly severed the beam. But the span didn’t collapse because its multi-
beam structural system was highly redundant. When one beam fractured, the
adjacent beams had enough reserve capacity to continue supporting the concrete
deck and traffic loads safely. Thanks to routine inspections, the cracks in the
bridge were discovered and repaired using methods developed through the
research programs spawned by the Silver Bridge collapse. This research has also
contributed enormously to improved bridge design codes, which now specify
effective provisions for designing fatigue-resistant steel bridges.
168
17. Stress Corrosion: The Silver Bridge
Reading
Fisher and Roy, “Fatigue Damage in Steel Bridges and Extending
Their Life.”
Kwon and Frangopol, “Bridge Fatigue Assessment and Management.”
National Transportation Safety Board, Collapse of U.S. 35 Highway Bridge,
Point Pleasant, West Virginia.
Passaglia, A Unique Institution.
169
18
Soil and
Settlement:
The Leaning
Tower of Pisa
The past six lessons have examined
engineering failures caused by inadequate
structural resistance in many different
forms—from unstable vaulting in a medieval
cathedral to an inadequately reinforced
connection in a 21st-century pedestrian
bridge. This lesson continues with this
theme but shifts the focus below ground—to
failures associated with foundations and the
structural resistance provided by soil. You
will explore the construction of the Tower of
Pisa and discover the mechanisms behind its
characteristic lean.
170
18. Soil and Settlement: The Leaning Tower of Pisa
Foundation Types
A foundation transmits the weight of a structure (and the loads applied to
it) safely down into the earth. The most structurally desirable foundation
is one constructed directly on bedrock. If no bedrock is within reach, piers
can be built on a firm stratum of soil. This requires larger foundations and
a lighter bridge to reduce the downward pressure exerted on the soil. If no
firm stratum of soil is within reach, a pile foundation is the most common
alternative. Piles are long shafts of steel, concrete, or wood driven deep
into the ground. A point-bearing pile foundation reaches the bedrock and
supports the structure through a concentrated bearing force at the lower tip
of each pile. If the bedrock is too deep for point-bearing piles, friction piles
are used instead. This foundation type supports a structure by the friction
force developed at the interface between the outer surface of the piles and the
surrounding soil.
171
18. Soil and Settlement: The Leaning Tower of Pisa
172
18. Soil and Settlement: The Leaning Tower of Pisa
belfry to bring its axis closer to vertical. However, this realignment couldn’t
compensate for the belfry’s substantial weight—which caused the tower’s lean
to increase from about 2.5 degrees to 4.5 degrees over the following century.
The tower was sinking too. By the 19th century, even the high side of the
foundation had settled more than six feet. Thus, in 1838, the Pisans decided
that visitors to the tower should be able to view the substantial portion of the
structure that had sunk below ground level. They excavated a trench around
the tower’s base and built a below-ground walkway—called the catino, or
basin. This nearly destroyed the tower.
Burland’s Committee
In the early 20th century, the Italian government established several
commissions to study the problem and monitor the tower’s movement. In
1935, convinced that the perpetual flooding of the catino was destabilizing
the tower, government engineers attempted to stop the water infiltration
by injecting concrete grout into the foundation and surrounding soil. This
slowed the infiltration—but caused the tower’s rate of tilt to increase again.
The period from the 1960s through 1990 saw a succession of new government
commissions, which proposed a series of bizarre solutions that were rejected because
they were too architecturally intrusive. By the late 1980s, the tower’s increasing
lean was also causing structural distress. There was a severe stress concentration
where the structural core was already weakened by the doorway connecting the
second-level gallery to the internal stairway. The stone in this area was dangerously
close to crushing in compression—a local failure that would surely have triggered a
catastrophic collapse. By this time, the tower’s lean had reached 5.5 degrees.
173
18. Soil and Settlement: The Leaning Tower of Pisa
Soil Mechanics
Soil is a granular material in which individual particles interact with each
other at discrete points of contact. This structure is conceptualized as a soil
skeleton. It carries load by transmitting internal forces—compression and
friction—between the particles at their points of contact. The larger these
internal forces, the stronger the soil. The friction between particles prevents
them from sliding with respect to each other.
Within the soil skeleton, the voids between the particles can be filled with
either air or water. When completely filled with water—called porewater—
the soil is saturated. In general, the presence of porewater makes a soil weaker
because the water causes buoyancy, which reduces the friction forces between
the particles. With less friction, the particles slide more easily across each
other, and the soil fails at a lower stress.
Of the four main soil types—sand, gravel, silt, and clay—clay is the most affected
by porewater. Clay is composed of fine, plate-shaped grains, which bond together
in the presence of water. Thus, saturated clay is uniquely cohesive and practically
impermeable to water. When saturated clay is subjected to long-term compressive
174
18. Soil and Settlement: The Leaning Tower of Pisa
loading, the soil’s low permeability initially prevents the porewater from being
squeezed out. Because water is essentially incompressible, the water initially carries
most of the applied load with no significant change in the volume of the soil mass.
But the resulting increase in porewater pressure eventually causes the water to
diffuse away to surrounding regions under less pressure. As the water is squeezed
out, the clay particles carry an ever-increasing share of the load. As they compress,
the voids get smaller, and the soil decreases in volume.
Leaning Instability
In analyzing the implications of this pattern, Burland’s committee concluded that
if construction had not been interrupted multiple times, the tower would have
collapsed. At the time of each interruption, the downward pressure exerted by the
incomplete structure was nearly equal to the clay’s undrained strength. Thus, if
construction hadn’t paused, the continued increase in the tower’s weight would
have caused a soil bearing capacity failure—and the tower would have toppled.
But in each case, the long pause allowed the clay to drain, resulting in a significant
increase in its strength prior to the resumption of construction.
175
18. Soil and Settlement: The Leaning Tower of Pisa
The committee’s analysis demonstrated that the Tower of Pisa and its
underlying soil were dangerously close to the theoretical threshold of leaning
instability. A 6% increase in the tower’s height and weight would render
it physically incapable of standing erect. In short, the Leaning Tower was
leaning because a tall, heavy tower standing on a flexible base has an inherent
tendency to lean. As of 1990, it had reached a state of equilibrium. Under static
conditions, the angle of tilt was no longer increasing. However, occasional
natural events—like fluctuations in the level of the local water table—were
still causing small, discrete increases in the angle. If this process continued, the
tower would inevitably reach its point of instability and collapse.
Under-Excavation
The committee determined that reducing the angle of tilt would greatly enhance
the tower’s stability. The first phase of the committee’s strategy was to pile stacks
of lead weights around the north side of the tower’s base. This would ensure
that the angle of tilt wouldn’t increase while the team was developing a more
permanent solution. Also, it had the advantage of being easily reversible. For the
long-term solution, the committee decided on under-excavation, which involved
extracting soil from underneath the tower foundation’s north side, causing localized
settlement that would decrease the tower’s lean. The under-excavation would be
performed with an auger rotating within a tubular casing. This can bore into a
soil stratum and extract soil in carefully controlled quantities. The strategy was to
remove enough soil to reduce the tower’s angle of inclination by one-half degree—
enough to stabilize the structure without significantly altering its appearance.
176
18. Soil and Settlement: The Leaning Tower of Pisa
Reading
Burland, et al., “The Leaning Tower of Pisa.”
Burland, Jamiolkowski, and Viggiani, “The Stabilisation of the Leaning
Tower of Pisa.”
177
19
Water in Soil:
Teton Dam
and Niigata
Welcome to this exploration of engineering
disasters caused primarily by inadequate
resistance to the adverse effects of water
in soil. This lesson will primarily concern the
Teton Dam catastrophe, where the decision
to build on geologically flawed ground led
inexorably to disaster. In this case study, you
will explore the design of the Teton Dam,
which was influenced by the site geology,
and the mechanism that led to its failure—
liquefaction, which then led to piping and
dam failure.
178
19. Water in Soil: Teton Dam and Niigata
179
19. Water in Soil: Teton Dam and Niigata
small springs of water emerging from the canyon wall a few hundred feet
downstream from the dam. But all dams experience some seepage—and the
water was clear, indicating it wasn’t carrying any sediment eroded from the
dam’s core. Thus, the engineers weren’t concerned.
But at around 7:00 am on June 5, a survey crew noticed two new leaks—one
about 130 feet below the crest, near the western canyon wall, and another
emerging from the base of the embankment down below. This time, the
water was muddy. Both leaks were small, but over the next three hours,
their flow rate increased steadily. Around 10:30 am, the upper leak quickly
developed into a large sinkhole, which started eroding upward, toward the
crest. Bulldozers were dispatched to plug the leak but were quickly swallowed
up by the expanding sinkhole. As the sinkhole continued to erode upward,
a whirlpool appeared in the reservoir. This indicated that water was being
drawn into an opening in the embankment’s upstream face, below the
reservoir’s surface.
At 11:55 am, the sinkhole reached the crest—which collapsed, opening a major
breach. Within two minutes, the entire reservoir had poured through the
breach, carrying much of the embankment with it—and sending an 80-billion-
gallon tidal wave thundering down the valley. Overall, 11 people were killed,
thousands of cattle were swept away, 300 square miles were inundated, and the
towns of Wilford and Sugar City were wiped from the map.
Liquefaction
In general, moving water exerts a drag force on individual soil particles. If
the flow is downward, this drag force acts in the same direction as gravity.
Thus, it pushes the particles into a denser configuration, increasing the
friction between them and strengthening the soil. But if the flow is upward,
the drag force works against gravity—lifting the particles, reducing the
friction between them, and making the soil weaker. If the upward flow is
strong enough, the soil loses its strength and effectively becomes liquid—a
phenomenon called liquefaction.
180
19. Water in Soil: Teton Dam and Niigata
container connected to two water tanks. When one tank is filled with fluid,
the resulting difference in pressure, delta-p, causes water to seep through the
soil at flow rate Q, measured in units of volume per time. The term Q is also a
function of four additional factors:
` the cross-sectional area of the material through which the fluid is moving
The flow of water through soil increases with pressure and the permeability
of the soil and decreases with the length of the flow path. Consider a
floodwall holding back water. Raising the water level on the upstream side
of the floodwall creates a pressure difference on opposite sides of the wall.
As Darcy’s law predicts, this pressure difference drives seepage beneath the
floodwall. As the water advances beyond the base, it turns upward. Thus,
liquefaction occurs at the downstream end of the flow path. Once liquefaction
begins, piping leads to failure of the floodwall.
Piping
When liquefaction begins, it shortens the flow path, which causes the
flow rate to increase. A higher flow rate causes more liquefaction, which
further shortens the path. This cycle continues until the entire flow path
has liquified. At this point, the water is flowing freely and carrying the soil
particles along with it. This is piping, or internal erosion—the transport
of soil particles by water flowing under pressure along an internal pathway
through soil or rock. Seepage-induced piping caused the Teton Dam’s failure.
According to Darcy’s law, increasing the length of the flow path and reducing
the cross-sectional area of soil through which seepage can pass substantially
reduces the seepage flow rate and ensures that the upward seepage pressure
181
19. Water in Soil: Teton Dam and Niigata
Embankment Dams
A major embankment dam is a sophisticated technological system, composed
of four major components:
182
19. Water in Soil: Teton Dam and Niigata
The bedrock at this site is also excessively permeable. Thus, the designers
sought to reduce its permeability by incorporating a grout curtain into their
design. A grout curtain is constructed by cutting a small trench into the rock
surface, drilling a series of closely spaced bore holes deep into the rock mass,
setting steel pipes into the tops of these holes, sealing them in position with a
concrete cap, and injecting grout into the bore holes at high pressure. Thanks
to this pressure, any subterranean cracks that intersect with the bore holes are
supposed to be filled by the grout.
The Teton Dam’s design called for the construction of a grout curtain beneath
the foundation and both abutments to create a seepage barrier along the dam’s
full length. The Bureau of Reclamation conducted an on-site grouting test in
1969, while the design was still in progress. The rhyolitic tuff within 70 feet
of the surface proved to be so deeply fractured and permeable that it couldn’t
be effectively sealed, even with an excessive quantity of grout. However, the
bureau’s engineers simply modified their design, adding 70-foot-deep key
trenches beneath both abutments. The purpose of these trenches was to
remove the badly fractured rock near the surface and to relocate the grout
curtain to the less-fractured rock at the bottom of the trenches.
The design of the rest of the Teton Dam was mostly conventional. The
embankment was configured with shallow slopes to enhance its stability. Like
most earth dams, its internal structure consisted of well-defined zones—each
built from a different type of soil or rock and performing a distinct function.
The most important zone was the core—the dam’s principal water barrier.
To achieve its purpose, the core extended through the dam’s full height
and would need to be constructed of a low-permeability material. The ideal
soil for this purpose is clay. However, the economics of dam construction
typically dictate the use of locally available materials. In eastern Idaho, the
only suitable soil available in sufficient quantities was a fine-grained silt
called loess. When properly placed and compacted, loess has good strength
and relatively low permeability; however, it lacks the plasticity of clay and is
susceptible to erosion and cracking.
In the Teton embankment design, this fragile core material was protected
on both sides by a casing of well-compacted sand and gravel quarried from
the Teton riverbed. The casing was also vital for controlling seepage through
the dam. The irregularly shaped zone of permeable sand and gravel on the
183
19. Water in Soil: Teton Dam and Niigata
downstream side of the core was designed to capture any water that seeped
through the core and channel it safely out of the embankment through a
horizontal sand-and-gravel bed called a blanket drain. The downstream
casing also functioned as a filter. It allowed porewater to pass easily from the
core into the casing but prevented the fine-grained core material from being
transported along with the seepage.
First, the number and placement of the bore holes specified for the grout curtain
were inadequate to seal the highly fractured rhyolitic tuff beneath the dam’s
abutments. Thus, the grout curtain was ineffective as a seepage barrier. Second,
the key trenches’ walls were too steeply sloped. Thus, the soil near the top of
the trenches probably experienced arching. That is, the weight of the overlying
material was transmitted laterally to the trenches’ rigid stone walls, leaving the
underlying soil more lightly loaded. As the soil at the bottom of the trenches
settled, cracks opened up, providing pathways for internal erosion.
Most importantly, even though the embankment design included a casing and
filter to protect the fragile core material, the key trenches received no such
protection. Thus, water could enter and exit these trenches through fissures in
184
19. Water in Soil: Teton Dam and Niigata
the stone walls—with nothing to prevent the soil particles from being carried
off by the moving water. Had the key trenches been provided with sand-and-
gravel filters to protect the loess core material, the failure would probably
never have happened.
In loose, sandy soil, the ground motions associated with an earthquake can
compress the soil particles—causing a reduction in their volume. But if that
soil is saturated, the porewater can’t undergo a similar volume reduction
because water is essentially incompressible. As a result, the pore pressure
185
19. Water in Soil: Teton Dam and Niigata
increases. If the ground motion is strong and the water can’t quickly diffuse
away to an area of lower pressure, the pore pressure can increase to the point
where the porewater is carrying all the applied stress. As a result, the friction
between soil particles drops to zero—and liquefaction occurs.
Reading
King, “Tuff.”
Seed and Duncan, “The Teton Dam Failure.”
US Department of the Interior, Failure of Teton Dam.
186
20
Construction
Engineering: Two
Failed Lifts
In the US, more than 1,000 construction
workers die on the job in a typical year. Many
of these incidents involve operational or
procedural issues on the job site; therefore,
they shouldn’t be classified as engineering
failures. But some of the worst construction
disasters have indeed been engineering
failures, where some aspect of the
construction process was addressed by an
engineered solution that went badly awry. In
this lesson, you’ll learn about two such cases.
187
20. Construction Engineering: Two Failed Lifts
The three key participants in the Senior Road Tower project were
188
20. Construction Engineering: Two Failed Lifts
The process of erecting the Senior Road Tower went smoothly until the final
task—lifting and installing the two antenna modules on top of the completed
mast. The six-ton antenna modules had been fitted with lifting lugs—fittings at
which a crane’s hoist cable could be attached to lift each module off the bed of a
truck in a horizontal orientation. However, the modules would then need to be
rotated into a vertical orientation for installation on the mast. In this orientation,
the cable would interfere with—and damage—several of the antenna baskets.
189
20. Construction Engineering: Two Failed Lifts
snapped. The combined effect of this instantaneous release of energy and the
unbalanced tension in the two remaining intact guy lines caused the mast to
displace violently away from the point of impact. This lateral deflection was
large enough to buckle the mast—and the entire structure collapsed. All five
riggers from the Worldwide crew were killed in the fall. Amid the wreckage,
investigators found the mangled outrigger, with all four U-bolts sheared off.
The failure of these bolts was pinpointed as the event that initiated the collapse.
The riggers likely reasoned that to lift six tons, four U-bolts
would work because each had a manufacturer-specified
capacity of two tons. This would have been a reasonable
solution if all four U-bolts had been carrying an equal share
of the antenna’s six-ton weight. Unfortunately, they weren’t.
This assumption would have been correct if the lift point
were equidistant between the two columns, but the load line was
actually attached at the end of the outrigger. From this point, the outrigger
effectively became a lever. The purpose of a lever is to magnify an applied force,
and that’s exactly what this one did. Indeed, the force in the two U-bolts was more
than four times higher than the riggers’ simplistic assumption predicted.
Liability
There’s no doubt that the riggers’ faulty outrigger design caused the
failure. However, it seems unfair to blame Worldwide, which identified a
construction issue, notified the design engineer, got rebuffed, developed a
solution, asked the engineer to review it, got rebuffed again, and then decided
to assume the risk and proceed with the lift. It feels more satisfying to blame
the engineers at Harris for refusing to allow removal of the antenna baskets
or even to look at the riggers’ proposed outrigger design. However, Harris’s
refusal to help resolve a construction-related issue was consistent with the
company’s contractual obligations as the project’s design professional.
190
20. Construction Engineering: Two Failed Lifts
L’Ambiance Plaza
The structural design of L’Ambiance Plaza, an apartment building in
Bridgeport, Connecticut, included a foundation consisting of concrete
footings, which supported the basement walls, and a forest of steel columns,
which supported 17 reinforced-concrete slabs, 3 floors of the underground
parking garage, 13 residential floors, and the roof. The structural system was
configured as two independent towers, linked together at a shared elevator
shaft. Because this structural system consisted of only columns and slabs—
with no supporting beams—it was called flat slab construction. Reinforced-
concrete shear walls stabilized the frame and provided lateral resistance to
wind and earthquake loading.
We’ll start with a steel column supported on its concrete footing. The
concrete slabs cast in this position at ground level have a rectangular opening
through which the column passes. Within this opening is an integrally cast
steel fixture called a shearhead. The hydraulic jack comprises a base, which
sits on top of the column, and a hydraulic ram, which pushes upward on
the crossarm. The crossarm will lift the slab by pulling upward on a pair of
threaded rods—called lifting rods—each of which has a nut at its lower end.
The lifting rods are inserted into slots in the shearhead.
191
20. Construction Engineering: Two Failed Lifts
Lifting a massive concrete slab is a slow process. In the actual system, the hydraulic
rams have a stroke of only one-half inch—meaning they can lift a slab only
one-half inch before they need to be reset back down to their retracted position.
Thus, a lift of 40 feet is actually performed as 960 individual lifts of one-half inch
each. After each half-inch lift, two nuts are screwed down to hold the lifting rods
in place; then, the ram is lowered for the next stroke. The upper nuts are screwed
down to bring the rods back into bearing on the crossarm, and the cycle begins
again. Through this process, the slab is raised slowly—typically at about five inches
per hour. In an actual lifting operation, multiple jacks are working simultaneously
to lift one large, continuous package of slabs. These jacks must operate at precisely
the same rate to minimize bending of the slabs as they’re being lifted.
When the first package of slabs reaches the top of the lower-level columns, it’s
temporarily “parked” there by inserting steel wedges between the bottom slab
and bearing blocks, which were previously welded to the column flanges. At
this time, the wedges are temporarily fastened in position with light welds.
The lifting rods are then lowered, and the remaining package is lifted in the
same way. But this time, the individual slabs are dropped off and secured at
the second- and third-floor levels. With these slabs in their final positions, the
first-story shear walls can be constructed.
Next, the jacks are removed, the upper-level column segments are erected, and
the jacks are repositioned for the next lift. As the three-slab package is raised,
individual slabs are again dropped off and wedged into position at their final
locations. To preserve the frame’s stability, shear wall construction follows
one or two levels below the highest slabs. Once the roof slab is in position,
the jacks are removed. The slab-to-column connections are strengthened by
permanently welding the wedges to the bottom of the shearheads and filling
the gaps between the slabs and columns with concrete.
slabs were in position from the parking garage through the third floor, six
slabs were parked at the fourth floor, and five were parked at the seventh. The
shear wall construction was lagging five to six stories behind the highest slabs,
which placed both towers at increased risk of instability.
At 11:30 am, workers in the west tower had raised the package of three slabs
from the fifth- to the seventh-floor level and were adjusting its position and
installing wedges. Other crews were working several levels below. At that
moment, a worker installing wedges at this location heard a loud bang and saw
the slab above him shatter like glass. The entire package of slabs then sagged
and dropped onto the floors below, initiating a chain-reaction collapse. As the
west tower fell, the east tower was dragged down with it. Within five seconds,
the entire structure had been reduced to rubble. Twenty-eight workers died.
Shearhead Failure
The likely plaintiffs and defendants immediately hired consultants to
investigate the collapse on their behalf. The Occupational Safety and Health
Administration also requested an independent investigation by the National
Bureau of Standards. In their final report, the National Bureau of Standards
investigators identified seven possible causes of the collapse and concluded
that the most probable cause was the failure of a shearhead.
The shearheads were rectangular steel collars embedded within the concrete
slabs—one at each column location—to serve as points of attachment
between the slabs and lifting rods. Each shearhead comprised four steel
channels with two stiffened angles welded to their inner faces. To raise the
slab, the two lifting rods—each with a heavy nut threaded onto its lower
end—were inserted into slots in these angles. As the hydraulic jack pulled the
rods upward, these lifting nuts transmitted the slab’s weight into the rods.
193
20. Construction Engineering: Two Failed Lifts
shearheads were excessively flexible. As a result, the lifting angles had flexed
upward enough to allow the lifting rods to slip out of their slots. The loud
bang that workers heard immediately prior to the collapse was probably a
lifting nut striking the column—with sufficient force to leave a visible dent.
The investigators corroborated their theory by replicating this failure mode in the
laboratory. They demonstrated that the loss of support at one shearhead caused
the lifting rods at the adjacent shearheads to break loose as well. Deprived of
support across several consecutive spans, the entire package of slabs then failed
in bending. Its impact with the slabs below triggered the chain-reaction collapse
of the west tower. The east tower was either dragged down by its interconnection
with the west tower or knocked down by falling debris. In either case, the tower’s
marginal stability—resulting from the slow pace of shear wall construction—
probably contributed to the speed and totality of the collapse.
Reading
Culver, et al., Investigation of L’Ambiance Plaza Building Collapse.
US District Court for the Southern District of Texas, “Channel 20, Inc. v.
World Wide Towers Services, Inc.”
194
21
Maintenance
Malpractice:
The Mianus
River Bridge
This case study of the Mianus River Bridge
collapse concludes this course’s wide-ranging
exploration of structural failures. In this
lesson, you’ll examine a tragic failure caused
primarily by poorly managed inspection and
maintenance of a major highway bridge.
Phase 6 of the engineering design process—
operation and maintenance—can be heavily
dependent on policy and on resource
allocation. This case also shows that there’s
an interdependence between maintenance
and the preceding phases of the process.
195
21. Maintenance Malpractice: The Mianus River Bridge
Although the number of deaths was small, the impact of the Mianus River
Bridge collapse was immense. Locally, it created a traffic nightmare, as tens of
thousands of vehicles per day were diverted onto local streets. This traffic jam
196
21. Maintenance Malpractice: The Mianus River Bridge
lasted for six months until construction of a temporary span finally allowed
the interstate to reopen. The permanent replacement bridge wasn’t completed
until nine years later.
There are three ways to build a girder bridge across four supports. First, it
can use three individual spans—a configuration called simply supported.
Because each span is supported only at its two ends, mathematical analysis of
this structure is relatively easy. But this structure is also relatively inefficient.
Under load, each independent span bends sharply in the middle but less so at
the ends. The deflected shape is concave upward along the full length of each
individual girder.
197
21. Maintenance Malpractice: The Mianus River Bridge
The third alternative is the cantilever configuration. Here, two anchor spans
extend across the intermediate supports to form cantilever arms from which
the center span is suspended. This bridge is composed of three discrete
spans, each supported at only two points. Thus, mathematical analysis of
this structure is comparable to that of a simply supported bridge. Yet when
it’s loaded, it bends in double curvature—and thus has structural efficiency
comparable to that of a continuous bridge.
Cantilever Systems
The bridge’s five principal spans constituted two cantilever systems. It
consisted of a center span that functioned as two symmetrical anchor spans,
plus two additional anchor spans, four cantilever arms, and two suspended
spans. The main load-carrying members were plate girders. Girders are
large beams with an I-shaped cross section fabricated by welding steel plates
together to form the web and two flanges. Each girder had a curved profile.
This improved structural efficiency by providing greater depth over the
intermediate piers, where the tendency to bend was greatest.
One end of each suspended span was seated upon its cantilever arm, mounted
such that it was free to pivot on a heavy steel pin. The opposite end was
suspended from the cantilever arm by a pin-and-hanger assembly. This
comprised two steel hangers connected to the girder webs with seven-inch-
diameter pins and held in position by spacer washers, pin caps, and a one-inch
bolt—all made of steel. These connection configurations satisfied the key
structural requirements for a cantilever bridge.
In each bridge, the two main girders were interconnected with heavy,
diagonally oriented beams and trusses to create a parallelogram-shaped frame.
This geometric configuration—called a skewed structural system—was
198
21. Maintenance Malpractice: The Mianus River Bridge
necessary because I-95 crossed the Mianus River at an oblique angle. The
supporting piers had to be aligned with the river flow. Within this skewed
frame, additional transverse beams and longitudinal stringers were provided
to support the concrete deck, composed of parallelogram-shaped panels
separated by expansion joints. The Mianus Bridge was skewed at an unusually
large angle—54 degrees. This feature would play an important role in the
failure investigation, which began immediately after the span collapsed.
In probing this issue, the investigators noted that all four of the bridge’s pin-
and-hanger assemblies were severely corroded. Recall that corrosion is the
gradual destruction of a metal by a chemical reaction with water and oxygen.
It’s also greatly accelerated by the presence of salt. In the Mianus River Bridge,
the chemical preconditions for severe corrosion were provided by rainwater
and melted snow flowing through the expansion joints and washing over the
pin-and-hanger assemblies. This runoff was laden with salt, which was used
extensively for deicing in the wintertime and was present year-round in the
marine environment of Long Island Sound. As moisture and salt accumulated
between the pins, hangers, washers, and pin caps, the narrow gaps became
breeding grounds for corrosion.
The designers had foreseen this problem and equipped the bridge with a
drainage system that should have prevented storm runoff from ever touching
the pin-and-hanger assemblies. Because the deck surface was slightly crowned
and sloped longitudinally, stormwater flowed first outward and then along
the curbs, until it was captured by regularly spaced curb drains and routed
199
21. Maintenance Malpractice: The Mianus River Bridge
into drainpipes that emptied into the river. These curb drains ensured that
only a small proportion of the storm runoff could reach the expansion joints.
Any water that flowed through these joints was captured by a copper gutter
mounted beneath each expansion joint and channeled to another downspout.
This system was well designed, but it required frequent cleaning to keep the
drains and gutters from clogging with debris. This task fell to the Connecticut
Department of Transportation (ConnDOT), which was responsible for
bridge maintenance throughout the state. But because of repeated budget
cuts, ConnDOT found it increasingly difficult to fulfill this responsibility. In
1973, the department initiated a project to repave the Mianus River Bridge.
During this project, the curb drains were covered with steel plates, and the
deck was paved with asphalt. The drains were never uncovered. Thus, for
the next 10 years, 100% of the precipitation falling on a 10,000-square-
foot section of the deck flowed through the expansion joints, overflowed
the copper gutters, and poured onto the structural components below. The
gutters overflowed because they were too small to handle this increased flow
and were nearly always clogged with sand and debris.
Rust occupies more physical space than the steel from which it formed. If
rust accumulates within a confined space, it can exert thousands of pounds
per square inch in outward pressure. Thus, in the Mianus River Bridge, the
rust buildup in the gaps between the girders, washers, hangers, and pin caps
generated enough outward pressure to force the joint apart—a phenomenon
called corrosion pack-out. The investigators found that several of the steel
pin caps had dished outward by as much as an inch—even on pin-and-hanger
assemblies that hadn’t failed.
The Hypothesized
Failure Mechanism
Having determined that corrosion pack-out could easily push a hanger off its
supporting pin, the NTSB formulated a comprehensive failure hypothesis.
Over the years, the inside hanger at the southeast corner of the suspended
span was displaced about 1.25 inches by corrosion pack-out. At this point, the
stress on the narrow contact surface between the hanger and pin was so severe
that the steel yielded, the bolt fractured, and the hanger broke free. Instantly,
200
21. Maintenance Malpractice: The Mianus River Bridge
Every aspect of the NTSB’s proposed failure sequence was consistent with all
the available evidence. Yet an engineering consultant hired by ConnDOT
advanced a competing failure hypothesis. Based on a three-dimensional
structural analysis, the consultant determined that the unusually large skew
of the structural system had subjected the pin-and-hanger assemblies to lateral
forces large enough to push a hanger off its pin.
Inquiry Results
If the cause was corrosion, the blame would fall on ConnDOT. But if the
structure collapsed because of its skewed configuration, the designer would
be primarily responsible. The ConnDOT consultant’s theory was plausible.
Consider a simplified model of a two-girder bridge. An applied load causes
both girders to bend equally. But if the bridge is skewed, the same loading
causes significantly more bending in one girder than in the other. The result
is a global twisting of the entire structural system. In a cantilever bridge, this
twist would cause significant lateral forces at the pin-and-hanger assemblies.
201
21. Maintenance Malpractice: The Mianus River Bridge
Ultimately, the NTSB dismissed this failure hypothesis and attributed the
collapse to “corrosion-induced forces, due to deficiencies in the State of
Connecticut’s bridge safety inspection and bridge maintenance program.”
The board acknowledged that the bridge’s skewed configuration had caused
unanticipated lateral forces that might have contributed to the collapse.
However, these forces weren’t large enough to have been its primary cause.
Nonetheless, the NTSB did find one significant design flaw in the bridge.
The pin caps meant to hold the hangers in place were only about half as
thick as the relevant code required. Thus, corrosion pack-out caused them
to deform excessively, which might have accelerated the failure. But the
board concluded that thicker pin caps wouldn’t have prevented the pin-
and-hanger assemblies from failing. The accumulating corrosion product
would eventually have broken the retaining bolt, even if the pin cap hadn’t
deformed. However, the thin pin caps’ large deformations could have
provided a visible indicator of the impending failure. Had the dished pin caps
been noticed during the state’s routine bridge inspections, the catastrophe
might have been averted.
ConnDOT
For two decades prior to the collapse, ConnDOT had inspected the Mianus
Bridge every two years, as required by the National Bridge Inspection
Standards. The most recent inspection was in September 1982. This 12-hour
inspection was performed by an experienced technician and a well-qualified
assistant—yet both failed to discern any condition that would have justified
closing the bridge or initiating emergency repairs.
202
21. Maintenance Malpractice: The Mianus River Bridge
The NTSB also noted various ConnDOT management issues, including the
following:
The two best ways to prevent a steel bridge from corroding are to keep it
clean and to give it a fresh coat of paint every few years. But, because of
budget shortfalls, the Mianus Bridge was neither washed nor painted for
many years prior to the collapse. Clearly, ConnDOT’s lack of funding
contributed substantially to the Mianus Bridge disaster. To a large extent, this
situation resulted from two questionable policy decisions. First, Connecticut
chose to charge tolls on this segment of I-95, making it ineligible for federal
maintenance funds. Second, Connecticut had decided not to set aside its toll
revenues exclusively for highway and bridge maintenance; rather, this money
went into the state’s general fund, where it was used for other purposes.
Lessons Learned
The disaster provided a wake-up call for the state of Connecticut—and for
the nation. The state embarked upon a 10-year, $5.5-billion program of
bridge inspection, maintenance, and rehabilitation. The cantilever spans
of the Mianus River Bridge were replaced with a continuous multi-girder
configuration that eliminated the problematic pin-and-hanger assemblies
while increasing structural redundancy. The state also removed its tolls
on I-95 and became eligible for more than $10 million per year in federal
maintenance funds. Additionally, Connecticut initiated an immediate retrofit
of more than 60 pin-and-hanger spans; other states implemented similar
203
21. Maintenance Malpractice: The Mianus River Bridge
In this case, a seemingly trivial change to the catwalk design could have
prevented a catastrophic collapse 25 years later by providing inspectors with
better access to the pin-and-hanger assemblies. From the perspective of civil
infrastructure, the case also reminds us that “you can pay me now or pay me
later.” In 1982, ConnDOT couldn’t afford to wash the pigeon dung off a
major interstate highway bridge. But a year later, the state legislature was eager
to spend $5.5 billion to prevent another failure like the one at Mianus River.
Reading
Balakrishna and Linzell, “Examination of Steel Pin and Hanger Options.”
National Transportation Safety Board, Highway Accident Report.
204
22
Decision-Making:
The Challenger
Disaster
This course now turns to a series of case
studies involving mechanical, aerospace,
electrical, and nuclear systems. Because
these systems are often developed and
operated by large organizations, these cases
provide new opportunities to explore the
complex relationships between organizational
decision-making and engineering failures.
This lesson focuses on the Challenger
disaster, which killed seven astronauts. Here,
you’ll learn that the disaster was as much a
failure of organizational decision-making as it
was an engineering failure.
205
22. Decision-Making: The Challenger Disaster
206
22. Decision-Making: The Challenger Disaster
` the external tank, which held 1.6 million pounds of liquid hydrogen and
liquid oxygen to power the orbiter’s engines
On a typical mission, the orbiter’s main engines and both SRBs were used to
propel the vehicle off the launchpad. After the SRBs expended most of their
propellant, they were jettisoned, returned to the earth by parachute, and
recovered for reuse. Then, about eight minutes into the flight, the orbiter’s
main engines were shut down, and the external tank was jettisoned. The
orbiter’s two small maneuvering engines were then fired to insert the vehicle
into orbit. Finally, upon completion of its mission, the orbiter reentered
Earth’s atmosphere and landed at either Kennedy Space Center, Florida, or
Edwards Air Force Base, California.
` the nose cap and frustum, which enclosed the booster’s parachutes;
` the aft skirt, which was bolted to the launchpad to hold the shuttle in
position as its engines were powered up prior to liftoff;
` the solid rocket motor, consisting of four cylindrical steel cases filled with
solid propellant; and
` a bell-shaped nozzle, which was integral with the motor’s aft segment.
The motor segments were fabricated at Thiokol’s factory in Utah. Then, they
were shipped by rail to the Vertical Assembly Building at Kennedy Space
Center, where they were stacked and connected together at three field joints.
These field joints connected the steel case segments together structurally and
prevented hot, high-pressure propellant gases from leaking out of the motor
during its two-minute burn. A failure of either function would likely cause a
catastrophic loss of the entire shuttle.
208
22. Decision-Making: The Challenger Disaster
The O-rings (and the grooves in which they were mounted) were designed to
provide a redundant pressure-actuated seal. When the rocket motor ignited,
the resulting internal pressure would be transmitted through the putty. Then,
it would force the primary O-ring across its groove and flatten it against the
groove’s downstream face. This would cause the O-ring to extrude into the
gap between the tang and clevis, creating a robust seal. The O-ring was also
sealed by this same internal pressure. If the primary O-ring failed to seal, the
secondary O-ring would seal by the same dynamic process.
209
22. Decision-Making: The Challenger Disaster
Both Thiokol and NASA ultimately concluded that this could be managed
by using slightly larger O-rings and inserting metal shims between the tang
and clevis to reduce joint rotation. Subsequent testing demonstrated that
the primary O-ring could be expected to seal within 0.2 seconds of ignition.
Maximum joint rotation didn’t occur until 0.6 seconds after ignition. As long
as the joint sealed before it rotated, the seal would be maintained. On this
basis, NASA approved Thiokol’s SRB design in 1980.
The first shuttle mission, STS-1 Columbia, launched in April 1981, and the
field joints performed well. But when Columbia flew again seven months later,
the post-flight examination of the recovered boosters revealed that one of the
primary O-rings had been partially burned through. This phenomenon—
called O-ring erosion—was eventually attributed to a jet of propellant gas
passing through a tiny blowhole in the zinc chromate putty and impinging
upon the primary O-ring. The blowhole had probably formed during the pre-
launch assembly process, when air was trapped within the putty as the rocket
motor segments were being joined.
Thiokol determined that the resulting risk was minimal. A gas jet capable
of causing O-ring erosion could occur only during the fraction of a second
between ignition and the establishment of a pressure seal. The jet wouldn’t
have enough energy to burn completely through an O-ring. Consistent with
this finding, three of the next nine shuttle missions experienced some O-ring
erosion, but the field joints functioned normally in all cases.
O-Ring Blow-By
In September 1984, the recovered boosters from STS-41D Discovery revealed
a phenomenon called O-ring blow-by. In one of the factory-assembled nozzle
joints, a small deposit of black soot was discovered between the primary and
secondary O-rings. This meant that the primary O-ring had initially failed to
seal and that hot propellant gases had blown by it. Fortunately, the secondary
O-ring had sealed properly and prevented a catastrophe. But had the same
incident occurred in a field joint, the delay in attaining a primary O-ring seal
might have allowed enough joint rotation to prevent the secondary O-ring
from sealing.
210
22. Decision-Making: The Challenger Disaster
Both NASA and Thiokol recognized the dire implications of this new
problem. But there was a schedule to meet, and this blow-by seemed like
another manageable risk. Thus, the launches continued while Thiokol’s
engineers studied the problem. After three trouble-free missions, STS-51C
Discovery launched on January 24, 1985. In the post-flight examination of
the recovered boosters, one field joint in each SRB showed evidence of both
erosion and blow-by. This was the first instance of blow-by in a field joint,
the first time thermal distress had occurred in two different field joints on the
same flight, and the first occurrence of blow-by and joint erosion at the same
location.
After eliminating all other possibilities, the engineers determined that low
temperature was the culprit. This launch from the Kennedy Space Center
had been preceded by the coldest three-day period ever recorded in Florida.
At ignition, the O-ring temperature was estimated to have been 53°F—10°F
lower than on any previous launch. The low temperature had several adverse
effects on the field joint, but the most important was a significant reduction
in the O-ring’s resilience. During the launch, this loss of resilience slowed the
sealing process. This allowed hot propellant gases to blow past the primary
O-ring for such an extended period that a substantial portion of the O-ring
was burned away. Again, the secondary O-ring had prevented a disaster.
211
22. Decision-Making: The Challenger Disaster
212
22. Decision-Making: The Challenger Disaster
The caucus lasted more than half an hour. The teleconference then resumed,
and Kilminster stated that they’d decided the temperature effects were
inconclusive. Therefore, Thiokol recommended going ahead with the launch.
But this rationale made no sense. If the data were inconclusive, the effects of
low temperature were uncertain, which should have dictated a postponement.
But the NASA team approved the decision with no further discussion.
McDonald remained convinced that the launch should be postponed. As
Thiokol’s senior on-site representative, he would have been the appropriate
official to sign the launch recommendation, but he refused to do so. But
Kilminster had no such reservations. He faxed the signed document to
NASA, and the fate of Challenger was sealed.
Organizational Dysfunction
McDonald would later testify that NASA’s conduct during this teleconference
was out of character. In all previous launch decisions, NASA would
challenge a contractor’s recommendation to launch if there were unresolved
technical issues. But NASA had never previously challenged a contractor’s
recommendation not to launch. Evidently, there was pressure to maintain
NASA’s ambitious launch schedule. There’s also evidence that Marshall Space
Flight Center was suffering from a dysfunctional organizational culture, in
which senior management had come to view no-fly recommendations as
admissions of failure.
213
22. Decision-Making: The Challenger Disaster
Failure Investigation
No one saw it at the time, but films of the launch would later reveal puffs of
black smoke emerging from the aft field joint on the right SRB, within one
second after ignition. We now know that both O-rings in this joint had failed
to seal and were being incinerated by hot propellant gas streaming through
the joint. This failure should have caused an immediate explosion. But when
the hot gas contacted the cold steel of the field joint, molten aluminum oxide
in the gas solidified and temporarily sealed the joint.
214
22. Decision-Making: The Challenger Disaster
Lessons Learned
After the Challenger accident, NASA’s entire shuttle fleet was grounded for
nearly three years, McDonald led a Thiokol team that redesigned the SRB
with robust triple-O-ring joints that enabled the shuttle program to resume,
and NASA implemented improvements to its decision-making processes.
Unfortunately, a similarly flawed decision led to the loss of Columbia during
reentry on February 1, 2003.
Reading
McDonald, Truth, Lies, and O-Rings.
Rogers, et al., Report to the President by the Presidential Commission on the
Space Shuttle Challenger Accident.
215
23
Nuclear Meltdown:
Chernobyl
The Chernobyl disaster, the world’s worst
nuclear accident, was a complex, multifaceted
event. This lesson focuses primarily on its
scientific and engineering aspects. However,
you’ll also see that this technological
catastrophe was profoundly influenced by
human and organizational failures. As this
case study shows, the design flaws in the
RBMK nuclear reactor that led to the disaster
were the product of a dysfunctional Soviet
bureaucracy that was willing to prioritize low
cost, military utility, and propaganda ahead of
public safety.
216
23. Nuclear Meltdown: Chernobyl
Chernobyl
In the 1970s, the Soviet Union developed a major nuclear power complex near
Chernobyl. Construction of the Vladimir Ilyich Lenin Nuclear Power Station
began in 1972, and by 1986, four 1,000-megawatt RBMK reactor units were
in operation and two more under construction. At the time of its design, the
RBMK nuclear reactor dwarfed its Western counterparts in both physical
size and power output and could also produce weapons-grade plutonium for
nuclear warheads. The Soviet nuclear establishment had serious concerns
about the design. But even after two RBMKs experienced partial meltdowns,
the reactor’s design flaws were concealed even from the power plant operators
and managers. The cost of this secrecy became apparent on April 26, 1986,
when Chernobyl reactor number 4 exploded during a routine safety test.
Although the explosion killed only two workers, hundreds of plant personnel,
firefighters, and residents of nearby Pripyat were exposed to intense radiation—
and 28 died of acute radiation poisoning within weeks. Ultimately, 40,000
square miles were contaminated by radioactive fallout, and thousands of cancer
cases were attributed to its effects. The area within a 30-kilometer radius of the
Chernobyl plant was declared unfit for human habitation.
217
23. Nuclear Meltdown: Chernobyl
Nuclear Physics
The word nuclear refers to the nucleus—the center of an atom, composed
of positively charged particles called protons and uncharged particles called
neutrons. The number of protons in an atomic nucleus defines what that
element is. For example, the nucleus of a hydrogen atom always has one
proton. But the number of neutrons in a given element’s atomic nucleus can
vary. The most common form of carbon has 6 neutrons, but alternative forms
can have 2 to 16. These alternative forms of the same element are called
isotopes. An isotope is identified by its atomic mass number, which equals
the number of protons plus the number of neutrons in the nucleus. Thus, the
uranium isotope with 92 protons and 143 neutrons is uranium-235 (U-235).
An isotope can be stable or unstable. Those that have too many or too few neutrons
must emit particles to attain a more stable form—and thus are unstable. This
process of emitting particles is known as radioactive decay. The rate at which an
unstable isotope undergoes radioactive decay is its half-life, defined as the time
required for half of a quantity of the substance to decay into a different element.
Radioactive decay is one type of nuclear reaction. The others are fusion and
fission. Nuclear fission occurs when one atom splits into two or more pieces,
called fission products. When an atom splits, the total mass of the fission
products is slightly less than the mass of the original atom because a tiny bit
of mass has been converted into energy. The amount of energy associated with
this lost mass is substantial—the mass times the speed of light squared. This
energy is the basis for nuclear power.
The fuel used to generate nuclear power must be a fissile material, or a material
capable of self-sustaining fission, such as U-235. When the nucleus of a U-235
atom is struck by a neutron, it breaks apart, releases energy, and emits several
free neutrons. If there are other U-235 atoms nearby, the neutrons emitted
by one nucleus can strike adjacent nuclei, causing them to become unstable,
split apart, release energy, and emit more neutrons. As this process repeats
itself, progressively more free neutrons cause the fission of progressively more
nuclei. The resulting chain reaction is self-sustaining nuclear fission, which can
provide an abundant source of usable energy if properly controlled. The most
fundamental aspect of controlling nuclear fission is controlling the number of
free neutrons available to sustain the nuclear chain reaction.
218
23. Nuclear Meltdown: Chernobyl
Controlled Fission
To achieve controlled fission, a nuclear reactor must have nuclear fuel, coolant,
control rods, and a moderator. Nuclear fuel is prepared by molding uranium into
small pellets, which are sealed inside a tube made of zirconium. Large numbers
of these fuel rods are loaded into the reactor core in sufficiently close proximity
for self-sustaining fission to occur. The resulting heat would quickly melt the fuel
rods if not for the coolant—usually water. It is continuously circulated through
the reactor core to remove heat and transfer the associated thermal energy to
turbogenerators that convert thermal energy into electrical power.
Finally, the moderator is a substance that surrounds the fuel rods and facilitates
self-sustaining fission by slowing down neutrons. Moderation is necessary because
the fission of U-235 emits neutrons at such high speeds that they can’t be captured
by other uranium nuclei. This is why neutrons emitted by fission must be slowed
down. The moderator performs this function through elastic collisions between
fast-moving neutrons and the nuclei of the moderator atoms. This process is most
effective if the moderator’s atomic mass is comparable to that of a neutron.
such reactors can use a single water circulation system for both moderation
and cooling. Water-cooled, water-moderated reactors are safe in the sense
that any accident involving a catastrophic loss of coolant will also remove the
moderator from the reactor core—and stop the fission process instantly.
Note that the purpose of the moderator is to slow down the motion of
neutrons and therefore increase reactivity. Thus, the moderator doesn’t
moderate nuclear fission; it promotes nuclear fission by moderating neutrons.
Unfortunately, water has a relatively high tendency to absorb neutrons,
which reduces reactivity. In a water-moderated reactor, even as the water
enables fission by slowing down neutrons, it also inhibits fission by absorbing
neutrons. Thus, water-moderated reactors can’t use natural uranium for fuel.
Alternative Moderators
Natural uranium is primarily a mixture of two isotopes. Fissile U-235 constitutes
less than 1% of this mixture, and the remainder is mostly U-238, a non-fissile
isotope. In a water-moderated reactor, this small proportion of U-235 can’t supply
enough free neutrons to offset neutron absorption by the water. Thus, water-
moderated reactors must be fueled with enriched uranium, processed to increase
its proportion of U-235, which is expensive. Thus, to facilitate the use of cheaper
natural uranium, two alternative moderators are also in common use.
The first is heavy water. Each hydrogen atom in a heavy water molecule
has one proton and one neutron in its nucleus. That is, heavy water uses the
hydrogen isotope H-2. Because of these added neutrons, heavy water is about
500 times less likely than ordinary water to absorb free neutrons. Thus,
heavy-water reactors can use natural uranium fuel and avoid the high cost of
enrichment. Unfortunately, producing heavy water is itself quite expensive.
The other alternative moderator, and the one the Soviets chose for the RBMK
reactor, is graphite. A crystalline form of pure carbon, graphite has a larger
atomic mass than hydrogen and provides less effective moderation than
water. However, it is less expensive than heavy water, and its tendency to
absorb neutrons is much lower than that of ordinary water. Thus, a graphite-
moderated reactor can run on natural (or slightly enriched) uranium fuel,
220
23. Nuclear Meltdown: Chernobyl
As the water flows upward through these channels, it’s heated by the fissioning
fuel rods. Near the top of the core, the water starts boiling. The resulting mixture
of high-pressure steam and hot water then flows through another maze of 900
pipes to two steam separators—large cylindrical drums in which the steam rises
to the top and the water collects at the bottom. The water is piped down to the
main pumps to complete the cooling circuit. The high-pressure steam is fed to the
adjacent machine hall, where it drives a pair of turbogenerators—each comprising
a three-stage steam turbine spinning an electrical generator. The total electrical
221
23. Nuclear Meltdown: Chernobyl
The second flaw resulted from the RBMK designers’ decision to use graphite
moderation. The elevation at which the reactor’s coolant begins boiling is
controlled by the pressure in the cooling circuit and the temperature of the
water entering the core. If the pressure gets too low or the water temperature
gets too high, boiling can begin at a lower elevation. Because steam absorbs
fewer neutrons than water, this premature boiling causes decreased neutron
absorption and increased reactivity. Higher reactivity generates more heat,
which causes more boiling, more neutron absorption, and even higher
reactivity. This can quickly provoke an uncontrollable spike in reactor power.
This is the principal reason Western engineers considered graphite moderation
too dangerous and opted for water instead. When water changes to steam,
it becomes ineffective as a moderator; thus, the unexpected formation of
steam reduces reactivity. In a graphite-moderated reactor, steam increases
reactivity—and too much can easily trigger a power spike.
222
23. Nuclear Meltdown: Chernobyl
The RBMK’s third design flaw was its control rod configuration. The rods were
made of boron carbide, which has a strong tendency to absorb neutrons. But
the lower end of each rod was extended with an open sleeve and a 15-foot-long
cylinder of graphite. This extension—called a displacer—was configured such
that the graphite segment was centered within the reactor when the control rod
was fully withdrawn. Without it, whenever a control rod was withdrawn, its
channel would fill with water, reducing the rod’s effectiveness. The displacer
addressed this issue by replacing most of the water in the channel with graphite.
Because graphite enhances reactivity, the displacer ensured that withdrawing a
control rod would achieve the largest possible effect.
however, the first three attempts to run the test failed. The fourth attempt
was scheduled for 2:15 pm on April 25, 1986, in conjunction with a planned
maintenance shutdown of Chernobyl reactor number 4.
The test protocol also required the operators to disable the Emergency Core
Cooling System (ECCS). When activated, it would dump thousands of gallons
of cold water from a storage tank directly into the core. Because the safety test
might inadvertently trigger the ECCS, the system had to be manually disabled.
Implementation of the test protocol began around 1:00 am on April 25. Over the
next 12 hours, the reactor operators reduced power by half, then shut down one
of the two turbogenerators. At 2:00 pm, they disabled the ECCS. But minutes
before the scheduled shutdown, the regional grid controller in Kiev requested a
delay. The test resumed after 11:00 pm, but within an hour, it was interrupted
again by the midnight shift change at Chernobyl. The newly arrived reactor
operator was Leonid Toptunov, who had served in this position for only three
months. His shift supervisor was Aleksandr Akimov, a mechanical engineer whose
prior experience at Chernobyl had been with turbines, not reactors. And the senior
man was Anatoly Dyatlov, Chernobyl’s deputy chief engineer. Dyatlov’s only prior
nuclear experience had been with the small reactors on nuclear submarines.
224
23. Nuclear Meltdown: Chernobyl
` First, with all eight pumps now operating, the increased coolant pressure
reduced the steam formation in the fuel channels. This caused reactivity to
decrease, forcing the operators to withdraw even more control rods to keep
the power level steady.
225
23. Nuclear Meltdown: Chernobyl
` Second, the increased rate of coolant flow caused the temperature of the
water entering the reactor core to rise. The faster-moving water now had
less opportunity to lose heat as it flowed through the cooling circuit.
These unintended effects placed the reactor into a dangerously unstable state.
The operators struggled to maintain the coolant flow and steam pressure
within acceptable limits. To ensure that these fluctuations didn’t trigger an
automatic reactor scram, they disabled another emergency shutdown system.
By now, more than 200 of the 211 control rods had been fully withdrawn
from the core, which prompted the computer control system to recommend
an immediate shutdown. At this point, the reactor was still producing only
200 megawatts, and the test was guaranteed to fail. But Dyatlov directed his
subordinates to initiate the final phase.
This response might have saved the day if not for the flawed control rod
design. As the 200-plus control rods started downward, they displaced the
neutron-absorbing water at the bottom of the channels, causing a significant
spike in reactivity. Reactor power was now more than 30,000 megawatts and
climbing. Overheated fuel rod and control rod channels started rupturing,
and the control rods jammed before most of the neutron-absorbing boron
entered the core. Less than a minute later, a steam explosion blew the
pyatachok through the roof of the reactor building, severing all coolant pipes.
The remaining coolant instantly flashed to steam, and the core got even
hotter. Seconds later, a more powerful explosion blew the reactor apart.
226
23. Nuclear Meltdown: Chernobyl
This latter blast dispersed the nuclear fuel, terminated the fission reaction, and
ejected immense quantities of uranium, fission products, and graphite into the air.
Within the ruined reactor pit, the heat generated by the continuing radioactive
decay started a fire so intense that it could only be extinguished by helicopters
dropping thousands of tons of sand, lead, and boron directly into the pit. Because
the RBMK had no containment vessel, the smoke billowing from this inferno
spread radioactive contamination across the continent for two weeks.
Radiation claimed the lives of Toptunov, Akimov, and several other members
of the Chernobyl operating staff. Dyatlov suffered from radiation effects but
survived. He was subsequently tried, convicted, and imprisoned by the Soviet
authorities for failure to follow regulations, although he repeatedly claimed
that the explosion had been caused entirely by the flawed design of the
RBMK reactor and thus was the fault of the Soviet nuclear establishment.
The RBMK design was indeed flawed, and these flaws were indeed the
product of a dysfunctional Soviet bureaucracy that was willing to prioritize
low cost, military utility, and propaganda ahead of public safety. But the
RBMK’s design flaws only created vulnerabilities. It was Dyatlov who pushed
reactor number 4 into the dangerously unstable state that caused these
vulnerabilities to become the world’s worst nuclear accident. A stubborn,
narrow-minded authoritarian, Dyatlov was very much a reflection of the
bureaucracy he served—so in this sense, there was some truth to his claim
that the Chernobyl disaster was a failure of the Soviet system.
Reading
International Nuclear Safety Advisory Group, INSAG-7.
Mahaffey, Atomic Accidents.
Plokhy, Chernobyl.
227
24
Blowout:
Deepwater
Horizon
Welcome to this analysis of the Macondo
blowout—one of the most devastating
engineering failures of the 21st century
and the worst environmental disaster in
US history. As this case study shows, the
disaster was caused by corporate decisions
that prioritized profits over well-established
safety procedures, engineering judgment, and
the laws of physics. This lesson explores the
technological system used to drill an offshore
well like Macondo and then discusses the
various issues that led to the blowout.
228
24. Blowout: Deepwater Horizon
On the evening of April 20, 2010, the Horizon’s crew was engaged in
securing the well, transferring leftover drilling fluid to their support vessel,
and preparing for their next job at the Kaskida Prospect. But at 9:45 pm,
crew members felt a sharp jolt and noticed an inexplicable shower of seawater
falling onto the rig floor. Nearly an hour earlier, three miles below the
rig, highly compressed liquid hydrocarbons had started leaking from the
surrounding rock formation, through a recently installed cement seal, and
into the bottom of
the well shaft. As this
volatile liquid moved
upward through the
shaft, the resulting
decrease in pressure
allowed dissolved
methane to start
boiling out of the
liquid. Now a free
gas, the methane
expanded violently
upward, pushing a
column of seawater
and drilling fluid
ahead of it. The
229
24. Blowout: Deepwater Horizon
resulting uplift force jolted the entire rig. But only when crew members saw
the geyser of drilling fluid jetting above the derrick did they finally realize
that a massive blowout was underway.
Seconds later, methane blanketed the rig. Two massive explosions then knocked
out power and engulfed the rig in a 300-foot fireball. After burning for 36
hours, the Horizon capsized, sank, and ruptured the mile-long pipe that
connected the rig to the well—initiating the world’s largest marine oil spill. The
well wasn’t successfully sealed until September 19, 86 days after the blowout. By
then, Macondo had discharged more than 200 million gallons of oil.
230
24. Blowout: Deepwater Horizon
Below the rig, the drill pipe is enclosed within a segmented pipe called the
riser. The bottom of the riser is attached by a flexible joint to the blowout
preventer (BOP). The BOP is mounted on a steel fixture called the wellhead,
which is supported on a structural foundation composed of three concentric
large-diameter steel pipes—called casing—sealed with cement. The drill pipe
is lowered through the wellhead. As it grinds through virgin rock, it creates a
hole called the wellbore.
Drilling Mud
The drilling mud used at Macondo was a synthetic oil mixed with varying
quantities of barite—a powdered mineral used to control the mixture’s
density. Drilling mud lubricates the bit, carries the rock cuttings out of the
wellbore, and serves as an essential tool for well control. Any fluid held
within a container exerts outward pressure on the container. At any given
point, the magnitude of this hydrostatic pressure is equal to the density of the
fluid times the depth of that point below the surface of the fluid.
231
24. Blowout: Deepwater Horizon
Fluid naturally flows from higher to lower pressure; thus, the 13,000-psi
hydrocarbons will flow into the 12,500-psi wellbore when the bit encounters
the pay zone. This well is said to be underbalanced. The flow of hydrocarbons
into an underbalanced well is called a kick. If a kick isn’t detected and brought
under control, the hydrocarbons will flow at ever-increasing speed upward
through the well. When an uncontrolled kick reaches the surface, it becomes a
blowout. Using the formation pressure to assist with bringing hydrocarbons up
to the surface is the job of the production well—which is established after the
exploratory well has been completed.
Controlling Kicks
Because the geology of a well site is always uncertain, kicks can’t always be
prevented. The principal tool for controlling kicks is the BOP—a vertical
stack of controllable barriers individually operated from the drilling rig’s
control room. Only two of the Deepwater Horizon’s BOP barriers are
relevant here:
232
24. Blowout: Deepwater Horizon
` Second, the blind shear ram uses a hydraulically powered blade to slice
through the drill pipe and disconnect the riser from the wellhead. By
closing off the annulus and pinching the lower portion of the drill pipe
shut, the ram also seals the well.
However, the use of dense mud as a tool for well control is subject to an
important limitation. Every type of rock has a characteristic pressure at which
it will fracture. In our hypothetical Macondo well, a fragile stratum with a
fracture strength of 5,000 psi is located at a depth of 8,000 feet. At this depth,
our 110-pound-per-cubic-foot mud exerts a hydrostatic pressure of more than
6,000 psi—more than enough to fracture the rock. This would cause large
quantities of mud to flow into the fractured formation rather than returning
to the rig. These lost returns present a major challenge.
Lost Returns
Operators attempt to minimize lost returns by pumping a viscous substance
called lost circulation material (LCM) into the well to plug the fractured
rock. However, a more effective approach is to keep the mud density low
enough that its hydrostatic pressure won’t damage fragile formations. In our
hypothetical well, a reduction in mud density sufficient to prevent fracturing
at 8,000 feet would also cause the well to be dangerously underbalanced
down at 18,000 feet. The solution is to drill the well in intervals and use steel
casing and cement to isolate the intervals from each other. This strategy was
reflected in BP’s design for the Macondo well. The well would be drilled in
four intervals (below the wellhead foundation)—with a smaller-diameter
wellbore and casing at each successively lower level.
233
24. Blowout: Deepwater Horizon
In the cementing process, a rubber plug is inserted into the casing, followed
by a carefully calculated quantity of cement and a second plug. This
“package” must be pumped down through the casing—with the plugs above
and below the cement protecting it from contamination. At the bottom
of the casing, the lower plug collides with a float collar, which ruptures a
membrane in the lower plug. This creates an opening that allows the cement
to flow through the float collar, down into the shoe track at the bottom of
the casing, and back up into the annulus.
When the pumping stops, a one-way valve in the float collar prevents
backflow up into the casing, and the cement is allowed to harden. This seals
the bottom of the casing into the bore hole. The casing will now protect any
fragile rock strata located within this entire interval. Thus, higher-density
mud can be used to drill subsequent intervals. The lower-level intervals are
constructed in the same way but with progressively smaller casing diameters.
Therefore, each new string of casing can be lowered through the one above
it. The final element of this design is the production casing, which forms
a continuous conduit through which oil will flow upward in the future
production well.
Deepwater Horizon
Built in 2001 by Hyundai, the Horizon was classified as a dynamically
positioned semisubmersible rig.
` The term dynamically positioned means the rig can maintain its position
over a well using only its own thrusters, guided by a computer system that
receives input from GPS satellites, sensors, and gyrocompasses.
234
24. Blowout: Deepwater Horizon
` The term semisubmersible indicates that the rig floats on variably ballasted
pontoons, which can change the rig’s elevation with respect to sea level.
On the Horizon, four heavy columns extended up from these pontoons to the
business end of the rig—the derrick and top drive; the drill floor and control
room; storage racks for the drill pipe, riser, and casing; two large cranes; a
helipad; and the captain’s bridge. Below the main deck were the mud pits, a
cement plant, pumps, crew accommodations, and six diesel engines driving
electrical generators that powered the rig.
Drilling Struggles
The Horizon arrived at Macondo in January 2010, and after several days of
preparations, lowered its BOP and 5,000-foot riser to the seafloor and latched
up with the previously installed wellhead. On April 9, after many difficulties,
drilling was halted at a depth of 18,360 feet. The design had called for a final
depth of 19,650 feet—but in the final interval, the sandstone pay zone was so
fragile that the heavy mud required to prevent kicks was disappearing into the
porous formation.
235
24. Blowout: Deepwater Horizon
` and another normal-weight cap sealing the bottom of the annulus and the
shoe track.
Consistent with this plan, on April 19, precise quantities of these cements
were pumped into the well—and an equal quantity of mud emerged from
the riser. Because there were no lost returns, it was clear that the pumping
pressure hadn’t caused any fracturing in the pay zone. BP’s two onboard
representatives—the Company Men—concluded that the cement job had
been successful and directed that the temporary abandonment should
proceed. But the lack of lost returns didn’t guarantee that the cement
job had no voids or defects. This determination could only be made by
lowering a sensitive sonic instrument into the well to scan for voids in the
cement. However, this would have been expensive, and the Company Men
shortsightedly decided it was unnecessary. Today, there’s broad agreement that
flaws in this cement job permitted hydrocarbons to enter the well, initiating a
chain of events that ended in catastrophe.
Cement Flaws
First, upon the completion of drilling, the 56-foot space at the bottom of
the wellbore was full of mud less dense than normal-weight cement. During
cementing, some of the heavier cement would have sunk down into this space,
while the lighter mud rose up to replace it. The intermingling of cement and
mud created channels through the hardened cement. This could have been
avoided by pumping extra-heavy mud into the bottom of the wellbore prior to
the cementing operation.
236
24. Blowout: Deepwater Horizon
riddled with possible pathways for hydrocarbons to leak into the well. On
April 20, there were numerous squandered opportunities for BP and the
Horizon’s crew to discern the well’s vulnerability and take corrective action.
The Temporary
Abandonment Procedure
As designed, the temporary abandonment procedure would include the
following four tasks:
4 disconnecting the BOP from the wellhead, then hauling the BOP and
riser aboard the rig
The first task began with a successful positive pressure test. The BOP was closed,
and the production casing was pressurized to 2,700 psi. When the pressure held
steady for 30 minutes, it was clear that the production casing had no leaks. Thus,
BP’s Company Men tried to cancel the planned negative pressure test—but were
overruled by the Horizon’s senior drilling manager. A positive pressure test can
verify that the casing is leak-free. However, it doesn’t test the cement job because
the bottom of the casing is already sealed from the inside by rubber plugs.
The cement job can only be leak-checked with a negative pressure test. This
procedure simulates the hydrostatic conditions the well will experience after
abandonment, when removal of the mud-filled riser will also remove the
beneficial effect of the mud’s weight. First, the drill pipe is pumped full of
seawater, displacing the heavier mud down to the elevation where the final
cement plug will be installed. Next, the BOP’s annular preventer is closed to
seal off the riser’s mud-filled annulus. The pumps are shut off, and the top of
the drill pipe is opened. As the column of fluid adjusts to its new equilibrium
state, a small amount of seawater should be discharged from the top of the
drill pipe—then, all flow should stop.
237
24. Blowout: Deepwater Horizon
At this point, the hydrostatic pressure throughout the well is identical to the
pressure it will feel after the riser has been disconnected—when the entire
8,000-foot space above the top plug is occupied by seawater. Under these
conditions, the well is significantly underbalanced. Its sole defense against a
kick is the cement seal at the bottom of the production casing. Thus, if there’s
no additional outflow from the top of the open drill pipe, the cement must be
providing an effective barrier, with no leaks.
After this false start, the closing pressure was increased, the mud in the riser
was topped off, and the test was repeated. This time, the annular preventer
held. But when the drill pipe was opened, seawater flowed continuously
from it, even though the flow should have stopped after a few gallons. Then,
when the drill pipe was valved shut, its internal pressure rose to 1,400 psi
even though it should have remained at 0 psi. The underbalance induced by
the negative test had clearly allowed hydrocarbons to start flowing into the
well. Yet the Company Men and drilling supervisors declared these results
“anomalous” and decided to repeat the test.
Because the drill pipe was still valved shut (and experiencing a 1,400-psi pressure),
they decided to use the kill line for this second attempt. This was a legitimate
decision, as the kill line and drill pipe run parallel to each other and should be
hydrostatically identical under the test conditions. With the kill line pumped full
of seawater, the BOP closed, and the pumps stopped, there was no flow from the
opened kill line. Based on this result, the negative pressure test was proclaimed
a success. But because the kill line and drill pipe were interconnected and
measuring the same column of fluid, it would be physically impossible for one line
to be open and experiencing zero flow while the other was closed and experiencing
238
24. Blowout: Deepwater Horizon
1,400 psi. The kill line must have been blocked at its connection to the BOP,
most likely by the LCM. Clearly, this second attempt had produced an anomalous
result; yet no one attempted to reconcile these conflicting results.
As soon as hydrocarbons began flowing into the well, the quantity of mud
flowing out of the riser would have increased noticeably—which should have
prompted the operator to close the BOP and reassess the situation. But the
increased flow went unnoticed. In their haste to finish the job, the crew had
started transferring the Horizon’s stockpile of mud from the rig to the support
vessel—and no one was tracking the outflow. The kick became evident only
when the methane arrived at the drill floor. Shortly after the explosions, crew
members attempted an emergency disconnect by activating the BOP’s blind
shear ram. The ram closed partially but failed to sever the drill pipe—the
upward force of the blowout had buckled the pipe inside the BOP.
Yet, even if the ram had operated perfectly, the Horizon was already doomed. At
that moment, there were 63,000 gallons of hydrocarbons in the riser, above the
BOP, flowing upward to feed the inferno. The blowout was caused by flawed
design decisions, careless oversights, and deliberate procedural shortcuts. The
BOP malfunction was only the final link in a long, ugly chain of events.
Reading
Boebert and Blossom, Deepwater Horizon.
Shroder and Konrad, Fire on the Horizon.
Turley, From the Podium.
239
25
Corporate
Culture: The
Boeing 737 MAX
This case study considers the troubled
history of the world’s most controversial
airliner—the Boeing 737 MAX. A few years
ago, within months of each other, two 737
MAX flights, one in Indonesia and one in
Ethiopia, inexplicably dove into the ground,
killing everyone on board. This lesson primarily
focuses on the former flight, Lion Air Flight
610. Here, you will explore the conception of
the 737 MAX and discover the circumstances
that led to the aforementioned tragedies.
240
25. Corporate Culture: The Boeing 737 MAX
After climbing normally for a few more seconds, the aircraft abruptly entered
a violent 700-foot dive but then recovered and resumed its ascent. At 5,000
feet, it leveled off but began erratic altitude changes. Although the first officer
requested to return to the airport, the aircraft continued its erratic flight path
and never turned back toward Jakarta. Soon after, it disappeared from radar.
Seconds later, workers on an offshore oil rig saw the jet hit the water in a near-
vertical dive.
241
25. Corporate Culture: The Boeing 737 MAX
The crash was tentatively attributed to a sensor failure and a flaw in the
airplane’s flight control system. Boeing and the US Federal Aviation
Administration (FAA) issued worldwide advisories describing a simple
procedure pilots should use if a similar sensor failure occurred. But five
months later, another 737 MAX crashed under similar circumstances. Six
minutes after a normal takeoff from Addis Ababa, Ethiopian Airlines Flight
302 began flying erratically and then dove into the ground at 600 miles per
hour. Within a week, the entire 737 MAX fleet was grounded indefinitely.
Boeing 737
The original Boeing 737 was conceived in 1964 in response to market
demand for a small twin-engine jet. Because Boeing’s main domestic
competitor was already producing the twin-engine DC-9, Boeing engineers
sought to distinguish the 737 through three innovative design features:
` First, the 737 would use the same cabin cross section as the 707 and 727,
allowing all three models to use many of the same parts while providing
more seating capacity.
` Third, the engines would be positioned close to the ground for ease of
engine maintenance.
The 737 program was formally launched in 1965. The original model, the 737-
100, was completed in 1966 and type-certified by the FAA the following year. But
Boeing was already developing a new “stretched” version in response to a request
from United Airlines for more seating capacity. This 737-200 was 76 inches longer
and could seat up to 130 passengers—27 more than the Dash-100.
Over the next 30 years, this process of design evolution continued with three
new generations of 737s—the Classic, Next Generation (NG), and MAX. Each
generation included three to five individual models or variants. Improvements
such as a longer range and larger seating capacity were enabled by enhanced
aerodynamic features and advances in the power and fuel efficiency of jet
engines developed during this period. The engines used on the Dash-900
produce more than twice as much thrust as their Dash-100 ancestors.
242
25. Corporate Culture: The Boeing 737 MAX
Lengthening the landing gear wouldn’t solve the problem. The main landing
gear was mounted on the wings and had to retract inward. If the landing
gear legs were any longer, the wheels would interfere with each other in the
retracted position. The landing gear couldn’t be repositioned farther outward
because the engines were in the way. And the engines couldn’t be repositioned
outward without a major structural redesign of the wings. The engineers’ only
243
25. Corporate Culture: The Boeing 737 MAX
Boeing’s Rival
Because airlines invest heavily in maintenance infrastructure and pilot
training systems, they prefer to buy airplanes that retain a high degree of
commonality with existing fleets. Thus, a variant that uses many of the same
parts as its predecessor and has similar flight characteristics is often preferred
over a new type. More importantly, the process of attaining an FAA-type
certification for a variant of a previously certified type is simpler and quicker.
Thus, aircraft manufacturers have a strong regulatory incentive to update
their existing models.
Boeing’s need for frequent product improvements has also been driven by
intense competition with its principal European rival, Airbus. Airbus built its
first airliner, the A300, in 1972 and slowly gained market share. The A300
and A310 were wide-body airplanes that competed with larger Boeing models
like the 767. But in 1982, Airbus announced that it would design a new 150-
seat jet—the A320—aimed directly at the 737. Boeing was already working
on the 737-300 and didn’t expect the A320 to be a serious competitive threat.
244
25. Corporate Culture: The Boeing 737 MAX
that Boeing hadn’t even committed to developing. Boeing had to move forward
with a new generation of 737s—called the 737 MAX—which would use the
same high-efficiency CFM LEAP engine as the A320neo.
Stalling
Boeing quickly designed the 737 MAX but was hindered by the challenge of
fitting modern engines to a nearly five-decade-old airframe. The CFM LEAP
engine had a 14% larger fan diameter than the engine used in the earlier
737NG. Thus, the engines had to be repositioned even farther forward and
upward. Nonetheless, Boeing predicted that the MAX would equal or exceed
the A320neo’s range while improving upon its fuel efficiency by about 4%.
Flight testing began in January 2016. However, because of its repositioned
engines, the aircraft exhibited unexpected performance characteristics when
flying at a high angle of attack with the wing flaps retracted.
The purpose of the wing is to produce an upward force, called lift, which
supports the airplane’s weight while in flight. The angle of attack is the angle
between the wing and the oncoming air. As the angle of attack increases, lift
also increases—but only to a point. Every wing has a characteristic angle of
attack at which an aerodynamic stall occurs. A stall is a sudden loss of lift
that occurs when an excessive angle of attack causes the airflow to separate
from the wing’s upper surface. When a wing stalls, it stops flying.
Commercial aircraft are equipped with a stall warning system, which receives
input from two angle-of-attack sensors, mounted on the airplane’s nose.
The sensors operate independently to provide redundancy. If both sensors are
working properly, both stall warnings occur simultaneously. An airplane’s
susceptibility to stalling can be controlled with flaps—movable panels along
the wing’s aft edge. When the flaps are extended, they increase the wing’s
curvature and area, allowing the airplane to fly more slowly without stalling.
Flaps are typically extended during takeoff and landing but retracted during
normal flight.
During 737 MAX flight testing, at high angles of attack and with the flaps
retracted, the aircraft tended to pitch upward to a greater degree than the
737NG. This placed Boeing’s plan for expedited certification of the 737
MAX at risk. Under the FAA rules, expedited certification is permissible
245
25. Corporate Culture: The Boeing 737 MAX
Aircraft Control
An airplane in flight can rotate in any of three directions—pitch, roll, and
yaw. In Boeing airliners, the pilots control the airplane’s pitch by moving a
control yoke forward or backward. The yoke moves the elevators—hinged
surfaces mounted on the aft side of a winglike element called the horizontal
stabilizer. A rearward pull on the yoke raises the elevators, forcing the tail
downward and causing a climb. A forward push on the yoke lowers the
elevators, which raises the tail and causes a dive.
The elevators are typically used for short-term changes in pitch—for example,
during takeoff. But if the elevators are used to maintain a constant rate
of ascent or descent for a long period of time, the pilot must apply steady
pressure on the control yoke—which can be quite fatiguing. Thus, long-term
pitch adjustments are typically made by repositioning the entire horizontal
stabilizer. This is called trimming, and it has the same aerodynamic effect as
moving the elevators but doesn’t require any pressure on the control yoke.
Boeing 737 pilots can trim the airplane in either of two ways—with a thumb
switch located on each control yoke and with large manual trim wheels. The
thumb switches activate powerful electric motors that move the horizontal
stabilizer to the desired position. The manual trim wheels achieve the same
effect through a direct mechanical linkage. However, the electric trim-
control system is susceptible to runaway trim, which can occur if an electrical
malfunction activates a trim motor without input from the pilot. This causes a
sudden, unexpected climb or dive. Given this danger, all aircraft are equipped
with cutout switches that will instantly disable the electric trim motors. Pilots
are trained to use these switches immediately in the event of a runaway trim—
and then to use the manual trim wheels for subsequent pitch adjustments.
246
25. Corporate Culture: The Boeing 737 MAX
The MCAS
The MCAS receives its input from the same angle-of-attack sensors that
support the stall warning system. In the original MCAS implementation, any
time either sensor measured an excessive angle of attack while the flaps were
retracted and the autopilot was disengaged, the MCAS would command an
automatic 10-second application of nose-down trim. This would counteract
the 737 MAX’s tendency to pitch upward as it approached a stall—and
achieve the desired equivalence with the 737NG.
The 737 MAX entered service in May 2017. During the following year,
130 were delivered to 28 customers. But then the Lion Air and Ethiopian
Airlines accidents occurred. Given the erratic flight path that preceded both
crashes, investigators and Boeing engineers suspected the MCAS. Information
obtained from the flight data recorders and cockpit voice recorders confirmed
this suspicion. In both incidents, a malfunctioning angle-of-attack sensor
had erroneously signaled an excessive angle of attack to the airplane’s flight
control computer. The MCAS then activated, causing repeated applications
of nose-down trim, which the pilots were unable to overcome. Post-accident
investigations confirmed that the system was deficient in three main respects:
` First, the logic of the MCAS software allowed input from either of the two
angle-of-attack sensors to activate the system. Thus, a malfunction of a
single sensor could cause the system to activate erroneously.
` Second, the system logic allowed for repetitive MCAS activations. Thus,
even though the pilots regained control after the initial MCAS activation,
the system relentlessly reasserted control in response to continuing inputs
from the faulty sensor.
Boeing had justified this decision to the FAA by claiming that the MCAS
was an internal element of the airplane’s flight control system; thus, pilots
didn’t need to know about it. More importantly, if the MCAS ever activated
247
25. Corporate Culture: The Boeing 737 MAX
The next morning, Captain Suneja took command of the aircraft for the
flight to Pangkalpinang. Immediately after takeoff, the faulty sensor triggered
a stall warning, but neither pilot recognized the cause. The first officer,
Harvino, requested a holding point at 5,000 feet to diagnose the problem. As
the aircraft climbed past 2,000 feet, Harvino retracted the flaps, triggering a
248
25. Corporate Culture: The Boeing 737 MAX
burst of nose-down trim from the MCAS. Suneja reasoned that retracting the
flaps had initiated the problem—and ordered Harvino to extend the flaps.
This disabled the MCAS and allowed the pilots to regain control.
Resulting Conclusions
Based on this sequence of events, three main conclusions can be drawn. First,
Boeing’s claim that pilots had no need to know about the MCAS was false.
Ignorance of the MCAS clearly contributed to the pilots’ flawed response to
the crisis. Second, although Boeing’s implementation of the MCAS is often
criticized for its lack of redundancy, this isn’t precisely correct. The system
logic was designed such that if one angle-of-attack sensor had stopped sending
data, the MCAS would continue operating normally based on input from the
second sensor. In this sense, the MCAS was redundant—with respect to false
negative inputs.
But this logic also caused the MCAS to be nonredundant regarding false
positive inputs. If either sensor provided erroneous input indicating an
excessively high angle of attack, the MCAS would activate. Thus, Boeing
provided the wrong sort of redundancy. An MCAS failure due to false negative
input would cause a slight change in the airplane’s performance characteristics,
but an MCAS failure due to false positive input caused the system to seize
control of the aircraft and fly it into the ground. Clearly, the MCAS should
have been programmed to respond only when both sensors agreed.
Third, pilot error played an important role in the 737 MAX debacle.
Aviation writer William Langewiesche has argued that any well-trained
pilot should have been able to respond effectively to the circumstances that
caused the crashes. He stated that the pilots’ confusion and repeated failures
249
25. Corporate Culture: The Boeing 737 MAX
Aftermath
After the crashes, Boeing fixed the MCAS relatively quickly, and the MAX
was finally recertified in November 2020. But more than 100 airplanes
worldwide still had to be repaired, tested, and returned to service; flight crews
required additional training; the production line had to be restarted; and an
inventory of 400 aircraft had to be cleared—all during a global pandemic.
Meanwhile, Boeing was charged with fraud and ordered to pay $2.5 billion
in criminal penalties and damages. Moreover, 1,200 737 MAX orders were
canceled, and the company posted its largest-ever annual loss for 2020.
` In 2005, Boeing hired a CEO and several other senior executives with no
background in engineering or aviation.
250
25. Corporate Culture: The Boeing 737 MAX
The Boeing 737 MAX crisis began with this strategic shift in focus—
from building great airplanes to cutting costs and increasing share price.
Prioritizing the corporate bottom line over technological excellence proved
disastrous.
Reading
Langewiesche, “What Really Brought Down the Boeing 737 Max?”
Robinson, Flying Blind.
Simons, Boeing 737.
251
26
Learning from
Failure: Hurricane
Katrina
Welcome to the final lesson of this course—a
case study that tries to find cause for hope
despite unimaginable tragedy. The flooding
of New Orleans during Hurricane Katrina
on August 29, 2005, was the costliest
engineering failure in American history and
involved systematic failures by the US Army
Corps of Engineers. Yet the lessons learned
from this tragedy led to a paradigm shift from
controlling nature to accommodating nature,
providing an excellent example of learning
from failure.
252
26. Learning from Failure: Hurricane Katrina
Hurricane Katrina
When Katrina’s storm surge poured through the floodwalls of the New
Orleans hurricane protection system, 80% of the city was inundated. More
than 1,000 people died. Tens of thousands more waited for a promised
evacuation that took six days to complete.
The flooding caused $70 billion in property
damage. And although President George
W. Bush had declared a state of emergency
two days before Katrina made landfall,
the federal disaster response was slow and
poorly managed. Katrina caused so much
devastation that two years later, New
Orleans’ population was still only about half
of its pre-storm level.
253
26. Learning from Failure: Hurricane Katrina
Consider a piece of sandy coastal terrain, with high ground that gradually
slopes down to the ocean. Water percolates down through the sand, picking
up sediment along the way, and emerges as a sediment-laden river. The river
initially flows at a relatively high speed but slows down as it reaches the
flatter ground along the coastline. It stops entirely as it flows out into the
ocean. Soon, two distinctive landforms begin to emerge. First, as particles
of relatively coarse alluvium are deposited along the riverbanks, they create
low ridges, or natural levees. Second, as the entire flow slows down near the
ocean, a large quantity of alluvium accumulates near the river mouth. This is
the beginning of a delta. As this alluvium piles up, it increasingly restricts the
river’s flow. Eventually, when the volume of flow is high, the river will break
out of its channel to find a less-restricted path to the sea. This new channel
is called a distributary. This process eventually creates a fan-shaped web of
distributaries that constitute one lobe of a delta.
But as alluvium deposition continues at the river mouth, the delta lobe
extends progressively farther into the ocean. This causes a continual reduction
in the channel’s slope. Eventually, the slope becomes so shallow that during a
flood event, the river abandons its main channel and finds a shorter, steeper
path to the sea. This new channel starts building a new delta lobe, while the
old lobe gradually subsides beneath the sea. In the Mississippi River Delta,
this dynamic process over the past 5,000 years created the bays, estuaries,
barrier islands, and wetlands of the Louisiana coastline. It also built up the
strata of alluvial sand, silt, clay, and organic marsh soil on which New Orleans
was built.
254
26. Learning from Failure: Hurricane Katrina
The city was built more than 100 miles upriver from the mouth of the
Mississippi on the Gulf of Mexico because this location was better suited
for waterborne commerce. Goods shipped down the Mississippi could be
offloaded at New Orleans, hauled overland to Bayou St. John, and shipped
across Lakes Pontchartrain and Borgne to the Gulf. From here, ships could
sail to other Gulf ports behind the barrier islands, protected from storms.
This route was so advantageous that it would later be extended, deepened, and
named the Gulf Intracoastal Waterway.
Storm Surge
If New Orleans had been located at the mouth of the Mississippi, the sailing
route to the eastern Gulf ports would have been longer and more treacherous.
More importantly, if the city had been located on the coast, it would have
been extremely vulnerable to hurricanes. The most dangerous aspect of a
hurricane is its storm surge. As a hurricane moves across a body of water, its
counterclockwise winds cause water to pile up ahead of the storm. The storm’s
low atmospheric pressure raises the water level even further. The resulting
water surge resembles an abnormally high tide, which can exceed 20 feet
255
26. Learning from Failure: Hurricane Katrina
above sea level in a large Gulf Coast hurricane. In low-lying regions like the
Mississippi Delta, a surge of this magnitude can reach far inland, swallowing
everything in its path.
Because New Orleans was built on a natural levee only about 10 feet above
sea level, the city was theoretically vulnerable to large storm surges from the
Gulf. In practice, however, it enjoyed an effective natural form of storm surge
protection—its surrounding wetlands. Experts estimate that a one-mile-wide
band of cypress trees can reduce the height of a storm surge by about one
foot. In the 18th century, the 40-mile expanse of delta lowlands between New
Orleans and the Gulf Coast was a vast cypress swamp. During the 18th and
19th centuries, the only significant storm surges experienced by New Orleans
were from Lake Pontchartrain. These were effectively attenuated by the
cypress swamps and low ridges between the lake and the city. But by the 20th
century, the city’s vulnerability to hurricane-induced flooding had increased
significantly due to three major infrastructure development initiatives.
In 1918, New Orleans built the Industrial Canal, which provided the
first direct connection between Lake Pontchartrain and the Mississippi
River. It also served as an inner harbor for the city. The elevation of Lake
Pontchartrain is about one foot above sea level, while the river’s elevation is
significantly higher and more variable. Thus, the Industrial Canal required
a large lock to accommodate the elevation change between these two bodies
of water. With its completion in 1923, the Industrial Canal became part of
the Gulf Intracoastal Waterway. Its use by oceangoing ships was initially
256
26. Learning from Failure: Hurricane Katrina
For decades, the city’s business leaders had been advocating for a canal
connecting the Port of New Orleans directly to the Gulf. Louisiana’s political
leaders lobbied for its construction by the Corps of Engineers, using federal
funds. In 1936, the Corps rejected this proposal as economically unjustified.
However, after World War II, a revised benefit-cost analysis convinced both
Congress and the Corps that the project should proceed. The resulting
waterway was named the Mississippi River Gulf Outlet (MRGO).
Wetland Loss
The second infrastructure initiative that increased New Orleans’ vulnerability
was the hardening of the Mississippi River channel. In 1927, prolonged heavy
rainfall caused a destructive flood of the Mississippi. Congress responded
by directing the Corps of Engineers to construct an expanded system
of enhanced artificial levees and channel improvements along the lower
Mississippi River. In succeeding years, this system was generally successful at
reducing flood damage, but it also substantially altered the natural processes
associated with delta formation.
257
26. Learning from Failure: Hurricane Katrina
Northward Expansion
The third initiative that increased New Orleans’ vulnerability was the city’s
northward expansion. In the mid-19th century, yellow fever outbreaks
prompted the city to initiate a long-term program of increasingly sophisticated
drainage improvements. The 17th Street, Orleans, and London Avenue
Canals were excavated to facilitate the flow of surface water into Lake
Pontchartrain. Steam-powered pumps were built to lift water over the
Metairie and Gentilly Ridges, permitting the low-lying areas south of the
ridges to be pumped dry. Around 1900, the city built a six-foot-high artificial
levee along the shore of Lake Pontchartrain to improve protection against
storm surges.
This levee sealed off the swampland north of the Metairie and Gentilly
Ridges from the lake, allowing this land to be pumped dry for the first time.
In 1913, a new high-capacity electric pump was integrated into an ever-
expanding network of drainpipes, canals, and pumping stations. This system
was intended only to improve drainage. But by the mid-20th century, the
wetlands were gone, and dense residential developments had taken their place.
As the former wetland dried out, the ground started sinking. Because the
entire urban area was now enclosed within protective levees, there was no
flooding to replenish the soil. By the time of Katrina, about half of New
Orleans had subsided below sea level. Moreover, because New Orleans had
become a bowl, the rain falling on the city had to be captured, routed to
pumping stations, and pumped up into the canals or into Lake Pontchartrain.
Finally, the extreme subsidence of many residential neighborhoods created a
new vulnerability. If any of the city’s levees were breached, the bowl would fill
rapidly with water to a depth of nine feet or more in some areas.
canals, encircling New Orleans East, along the Intracoastal Waterway and the
MRGO in St. Bernard Parish, and interconnected with the Mississippi River
flood-protection levees at four points.
Floodwall Failure
On August 28, 2005, Hurricane Katrina became the strongest storm ever
recorded in the Gulf of Mexico as it reached Category 5 status, with sustained
winds of 175 mph. At 6:10 the following morning, Katrina made landfall
about 55 miles southeast of New Orleans. It would eventually pass 20 miles
259
26. Learning from Failure: Hurricane Katrina
east of the city. By this time, its intensity had dropped to Category 3, but
it was still generating a 28-foot surge that destroyed many towns along the
Gulf Coast.
But the floodwall system began failing even before Katrina made landfall.
Around 5:00 am, levees along the upper MRGO and Intracoastal Waterway
were overtopped and breached, flooding St. Bernard Parish and New Orleans
East. One segment of the Industrial Canal I-wall toppled while the water level
was still several feet below the top of the wall. This initiated the flooding of
New Orleans’ Lower 9th Ward. By 7:00 am, I-walls along the 17th Street and
London Avenue Canals also failed—again with the water level well below the
top of the walls. And shortly thereafter, the growing surge in the Industrial
Canal overtopped the entire floodwall and collapsed a substantial portion of it
along the Lower 9th Ward.
Shear Failure
The initial breaches on the Industrial and 17th Street Canals exhibited the
same failure mechanism. In both cases, the sheet piling had been driven
through the existing levee and a thin stratum of marsh soil into an underlying
layer of soft clay. This type of structure is designed by assuming its most likely
mode of failure and ensuring that the design provides adequate resistance
to this failure mode under the expected loading conditions. In the Corps
of Engineers’ design, I-walls built on clay soil were assumed to fail like this:
When the canal filled with water, hydrostatic pressure applied to the wall
and levee would cause an entire block of soil to slide outward along a curved
failure surface. This is classified as a shear failure because it involves sliding
along a failure surface. The structure’s resistance to this failure mode is
provided primarily by the clay’s shear strength.
260
26. Learning from Failure: Hurricane Katrina
But as the floodwater rose, the I-wall deflected outward, and a gap opened
at its base. When this gap filled with water, the hydrostatic pressure on the
wall increased substantially. Shear failure occurred. Because the actual failure
surface was much shorter than the assumed failure surface, the structure’s
actual strength was about 30% less than the designers had estimated—and
the I-wall toppled.
This failure could have been prevented by driving the sheet piling deeper
into the ground—or using a T-wall. This alternative configuration eliminates
any possibility of a water-filled gap forming at the base of the wall. Thus, it
isn’t susceptible to the failure mode that caused the initial breaches on the
Industrial and 17th Street Canals. The London Avenue I-wall failed in a
distinctly different way because it was built on sand rather than clay. The
pressure difference on opposite sides of the I-wall caused seepage into the
sand, beneath the sheet-piling, and back up to the surface. This resulted in a
liquefaction failure that eliminated the wall’s lateral support. This could also
have been prevented by driving the sheet piling deeper into the ground.
Overtopping
In contrast, the other breaches began with overtopping because many of the
MRGO levees had been constructed of poor-quality soil. When the storm
surge poured over these weak embankments, they washed away. When the
storm surge overtopped the Industrial Canal I-walls along the Lower 9th
Ward, the resulting waterfall gouged a trench on the wall’s downstream side,
causing a loss of lateral support. Under intense horizontal pressure, the walls
displaced violently outward. This could have been prevented by armoring the
downstream face of the levee with rock.
In the 1960s, the engineers who designed the system failed to consider
that New Orleans was (and is) continuously sinking. The levees along the
Industrial Canal were built three decades prior to Katrina—and, during that
period, they settled about two feet. Moreover, there’s compelling evidence that
the confluence of the MRGO and the Gulf Intracoastal Waterway acted like a
funnel, channeling the storm surge from Lake Borgne into the western reach
of the Intracoastal Waterway and then into the Industrial Canal. This funnel
effect significantly amplified the surge height.
261
26. Learning from Failure: Hurricane Katrina
This unexpectedly high storm surge was probably also influenced by the
long-term loss of the wetlands throughout the region and the environmental
degradation attributed to the MRGO project. Soon after this waterway
was opened to the Gulf of Mexico in the 1960s, saltwater intrusion began
destroying the freshwater marshes along its length. As the cypress trees died
off, their roots no longer stabilized the soft marsh soil. The banks of the
MRGO excavation began collapsing into the channel. As a result, near-
continuous dredging was required to keep the channel open. By 2005, the
600-foot-wide waterway had grown to nearly half a mile wide. This ruptured
the natural storm surge buffer provided by the cypress swamp.
Lessons Learned
After the storm, the Corps of Engineers rebuilt the New Orleans hurricane
protection system to a significantly higher technical standard—and added
impressive new features. These include the Lake Borgne Surge Barrier, which
closes off the funnel that caused so much trouble during Katrina.
This case teaches us that we must reassess the relationship between our built
environment and the natural world. Well-meaning but shortsighted attempts
to control nature have disrupted beneficial natural processes in ways that
proved to be self-destructive over the long term. In the future, as we grapple
with climate change, the need to accommodate nature rather than trying to
dominate it will become ever greater. Luckily, the imperative for sustainable
engineering has gained considerable traction in the past few years.
262
26. Learning from Failure: Hurricane Katrina
Reading
Andersen, et al., The New Orleans Hurricane Protection System.
Brinkley, The Great Deluge.
Freudenburg, Catastrophe in the Making.
Link, et al., Performance Evaluation of the New Orleans and Southeast
Louisiana Hurricane Protection System.
Mlakar, “The Behavior of Hurricane Protection Infrastructure in New
Orleans.”
Rogers, “History of the New Orleans Flood Protection System.”
263
Quiz
a 1.25 d 0.80
b 2.08 e none of the above
c 3.13
2 In the Dee Bridge case study, what was the fundamental flaw in Robert
Stephenson’s design concept?
3 Which of the following was not a cause of the Tay Bridge collapse?
264
Quiz
4 Which of the following was not a cause of the Kemper Arena roof
collapse?
a fatigue in the hanger rods from which the roof was suspended
b ponding of rainwater on the roof
c an inadequate roof drainage system
d the effect of wind in causing an excessive accumulation of
rainwater at one end of the roof
e lack of redundancy
5 Given that the Cypress Street Viaduct failed over three decades after
it was built, for which of the following decisions can the designer
legitimately be faulted?
6 How have the collapses of the original Sunshine Skyway Bridge and the
Skagit River Bridge influenced the subsequent practice of engineering?
265
Quiz
7 Which of the following was not a lesson learned from the Murrah
Federal Building collapse?
8 Who are the three principal participants in the planning and delivery of
a construction project?
266
Quiz
10 Which of the following was not a lesson learned from the Tacoma
Narrows Bridge collapse?
267
Quiz
268
Quiz
15 Which of the following did not contribute to the loss of life caused by
the Florida International University Pedestrian Bridge collapse?
16 What was the most important takeaway from the Ronan Point collapse?
17 According to Griffith’s criterion, what are the three main factors that
directly influence the susceptibility of a structural element to brittle
fracture?
269
Quiz
a The design engineers should have used a type of steel that was
not vulnerable to stress-corrosion cracking.
b The design engineers should have used a more redundant
configuration for the eyebar chains.
c The bridge should have been more scrupulously maintained.
d The bridge should have been inspected more frequently.
e A weight restriction should have been placed on vehicles crossing
the bridge.
19 Which of the following was not part of the project to save the Tower of
Pisa from collapse?
20 According to Darcy’s law, which of the following would cause the rate
of seepage through soil to increase?
270
Quiz
21 Which party to the Senior Road Tower project was held legally
responsible for the collapse—and why?
22 Which of the following did not contribute to the Mianus River Bridge
failure?
a fuel rods
b control rods
c coolant
d moderator
e all of the above
271
Quiz
25 Which statement does not apply to both the Deepwater Horizon and
Chernobyl disasters?
Answer Key
1.a, 2.c, 3.c, 4.a, 5.d, 6.d, 7.c, 8.b, 9.e, 10.d, 11.e, 12.b, 13.d, 14.e, 15.c, 16.d,
17.c, 18.b, 19.c, 20.d, 21.e, 22.a, 23.e, 24.a, 25.c
272
Glossary
273
Glossary
angle of attack: The angle between the wing of an aircraft and the
oncoming air.
arcade: A series of arches supported on piers and forming the lower story of a
Gothic cathedral interior.
274
Glossary
blast wave: A layer of highly compressed air that propagates outward from
the point at which an explosive detonates.
boron: An element that is often used in nuclear control rods because of its
strong tendency to absorb neutrons.
braced frame: A structural frame that uses diagonal braces as its principal
means of carrying lateral loads.
275
Glossary
camber: A slight upward arc, built into a truss or beam during construction
and designed to offset the estimated deflection that will occur after the
structural element begins carrying load.
cantilever: Any structural element that is fixed at one end and unsupported
at the other.
casing: A pipe inserted into an oil or natural gas well to prevent the walls of
the wellbore from collapsing.
cast iron: An alloy of iron and carbon that is heated to a molten state, then
poured into a mold. Because of its relatively high carbon content, cast iron is
more brittle and weaker in tension than wrought iron.
276
Glossary
277
Glossary
cold shut: An internal casting defect caused by the failure of two streams of
molten metal to join fully.
deck: A structural element that forms the floor of a bridge, on which vehicles
and pedestrians are supported.
deck truss: A truss bridge on which the deck and roadway are located at the
top chord of the truss.
279
Glossary
distributary: A branch of a river or stream that splits away from the main
channel.
distributed load: A load that is applied over an area (rather than at a single
point), typically expressed in units of force per length or force per area.
drain: A basin, covered with a grating, which captures storm runoff and
routes it into a storm drainage system or downspout.
drilling mud: In well-drilling, a fluid used to lubricate the drilling bit and to
carry rock cuttings back up to the surface.
280
Glossary
drilling rig: A complex technological system used to drill deep into the
earth’s crust to extract hydrocarbons (oil and natural gas).
fission: A process in which an atomic nucleus splits into lighter nuclei and
releases energy.
flange: (1) One of two horizontal elements forming the top and bottom of an
I-shaped structural member; (2) the raised edge on the wheel of a locomotive
or railcar.
flap: On an aircraft, a movable panel mounted along the aft edge of a wing.
When the flaps are extended, they increase the curvature and area of the
wing, thus allowing the aircraft to fly more slowly without stalling.
282
Glossary
formwork: Temporary supports used to contain fluid concrete and hold its
shape until it hardens.
283
Glossary
generator: A device that converts the kinetic energy of a rotating shaft into
electrical energy.
gin pole: A portable device that uses a pulley on its upper end to lift loads.
grout: A mortar made from Portland cement, used for filling crevices.
284
Glossary
header: A large pipe that is used to collect fluid flowing from many smaller
pipes, or to distribute fluid to many smaller pipes.
heavy water: Water in which each hydrogen atom in the molecule has one
proton and one neutron in its nucleus. Heavy water is more effective than
normal water as a nuclear moderator, because it has significantly less tendency
to absorb free neutrons.
hollow-core slab: A concrete slab with cylindrical cavities that reduce its
weight.
285
Glossary
joist: One of a series of parallel beams that directly support a floor or deck.
286
Glossary
287
Glossary
load path: A pathway through which internal forces are transmitted. The
path begins where the load is applied, passes through the elements of the
structural system, and ends at the structural foundation.
lost returns: In well-drilling, the loss of drilling mud through porous strata
or fractures in a rock formation.
mechanics: A branch of science that deals with the effects of forces acting
on physical bodies.
meltdown: A nuclear reactor failure that occurs when nuclear fuel rods
are heated beyond their melting temperature, usually due to a failure of the
reactor cooling system.
288
Glossary
mud: In well-drilling, a fluid used to lubricate the drilling bit and to carry
rock cuttings back up to the surface.
Newton’s first law: A body at rest remains at rest, and a body in motion at
a constant velocity remains in motion at a constant velocity, unless acted upon
by an external force.
Newton’s second law: The total force acting on a body is equal to its mass
times its acceleration.
nuclear energy: A form of energy associated with the bonds between the
particles that constitute the atomic nucleus.
289
Glossary
O-ring: A gasket in the form of a ring with a circular cross section, typically
made of a pliable material and used to seal a connection.
outrigger: A beam that is anchored to, and extends outward from, an object
to provide a point of attachment for lifting with a crane or other device.
P-delta effect: An interaction between gravity loads and lateral loads that
makes their combined effect on a structural system greater than the sum of
its parts.
290
Glossary
pier: (1) An intermediate bridge support, located between the two abutments;
(2) a main load-bearing column in a monumental building.
pile: A long shaft of steel, concrete, or wood that is driven deep into the
ground to increase the load-bearing capacity of a structural foundation.
pin: A structural connector that permits rotation but restrains both horizontal
and vertical movement of the connected elements.
291
Glossary
pylon: The tower on which the diagonal cables of a cable-stayed bridge are
mounted.
292
Glossary
reactor core: In a nuclear reactor, the vessel in which the nuclear reaction
takes place. The reactor core contains nuclear fuel rods, control rods, coolant,
and a moderator.
rigid frame: A structural frame that uses rigid connections between the
beams and columns as its principal means of carrying lateral loads.
riser: In offshore drilling, a segmented pipe that connects the drilling rig to
the wellhead and encloses the drill pipe.
293
Glossary
sag: (1) For a cable suspended between two supports, the difference in
elevation between the supports and the lowest point along the cable; (2) the
deflection of a beam or truss.
saturated soil: Soil in which the voids between soil particles are completely
filled with porewater.
seismic wave: An elastic wave that propagates outward from the epicenter
of an earthquake.
294
Glossary
shear strength: The largest internal shear force a member can carry before
failing.
shear wall: A concrete wall that provides lateral stability and later load-
carrying capacity to a structural frame.
sheet piling: A wall formed by driving a row of steel elements (sheet piles)
into the ground edge to edge; used for retaining walls, floodwalls, and similar
structures.
shoe track: In well-drilling, a length of casing that extends below the float
collar and is filled with cement during the cementing process.
shop drawings: Detailed plans that show precisely how each piece of steel
will be cut, shaped, and drilled for a project.
295
Glossary
stall: In aerodynamics, the rapid loss of lift that occurs when an excessive
angle of attack causes the separation of airflow on the top of a wing.
storm surge: A rise in sea level resulting from the wind and low
atmospheric pressure associated with a storm.
296
Glossary
297
Glossary
sway brace: A structural element that connects the top chords of two
parallel main trusses in a truss bridge.
tectonic plate: A discrete component of the earth’s outer shell, which floats
on the earth’s mantle.
through truss: A truss bridge on which the deck and roadway are located at
the bottom chord of the truss.
298
Glossary
top drive: A powerful electric motor used to rotate the drill pipe on an oil
drilling rig.
299
Glossary
uranium-235: The most commonly used fissile material for nuclear power
generation.
vault: An arch extruded into the third dimension to create a curved surface
that encloses space.
welding: A process by which two pieces of metal are fused rigidly together
by melting the metal or by depositing melted metal along the interface
between the pieces.
wellbore: A hole drilled through rock to create an oil or natural gas well.
wellhead: A steel fixture mounted at the top of an oil or natural gas well.
300
Glossary
winglet: A small fin mounted at the tip of an aircraft wing to reduce drag.
301
Bibliography
Barsom, John M., and Stanley T. Rolfe. Fracture & Fatigue Control in
Structures: Applications of Fracture Mechanics. Englewood Cliffs, NJ: Prentice
Hall, 1987.
Dally, James W., and William F. Riley. Experimental Stress Analysis. New
York: McGraw-Hill, 1978.
Fisher, John W. Fatigue and Fracture in Steel Bridges. New York: John
Wiley, 1984.
———. Statics & Dynamics. Upper Saddle River, NJ: Pearson Prentice
Hall, 2007.
———. Structural Analysis. Upper Saddle River, NJ: Prentice Hall, 1997.
Paz, Mario. Structural Dynamics: Theory & Computation. New York: Van
Nostrand, 1985.
Salvadori, Mario. Why Buildings Stand Up: The Strength of Architecture. New
York: Norton, 1980.
302
Bibliography
Engineering Ethics
Delatte, Norbert J. Beyond Failure: Forensic Case Studies for Civil Engineers.
Reston, VA: ASCE Press, 2009.
Levy, Matthys, and Mario Salvadori. Why Buildings Fall Down. New York:
Norton, 1992.
303
Bibliography
Gagg, Colin R., and Peter R. Lewis. “The Rise and Fall of Cast Iron in
Victorian Structures: A Case Study Review.” Engineering Failure Analysis 18,
no. 8 (2011): 1963–1980.
Lewis, Peter R., and C. R. Gagg. “Aesthetics versus Function: The Fall of the
Dee Bridge, 1847.” Interdisciplinary Science Reviews 29, no. 2 (2004): 177–191.
Board of Trade. “Report of the Court of Inquiry, and Report of Mr. Rothery,
upon the Circumstances Attending the Fall of a Portion of the Tay Bridge on
the 28th December 1879.” Railways Archive, https://www.railwaysarchive.
co.uk/docsummary.php?docID=107.
Martin, T., and I. A. MacLeod. “The Tay Rail Bridge Disaster Revisited.”
Bridge Engineering 157, no. 4 (2004): 187–192.
Petroski, Henry. Engineers of Dreams: Great Bridge Builders and the Spanning
of America. New York: Knopf, 1995.
304
Bibliography
Goldberger, Paul. “Kansas City Arena Loses Roof in Storm.” The New York
Times, June 6, 1979.
Mlakar, Paul F., et al. “The Oklahoma City Bombing: Analysis of Blast
Damage to the Murrah Building.” Journal of Performance of Constructed
Facilities 12, no. 3 (1998): 113–119.
305
Bibliography
Sozen, Mete A., et al. “The Oklahoma City Bombing: Structure and
Mechanisms of the Murrah Building.” Journal of Performance of Constructed
Facilities 12, no. 3 (1998): 120–136.
Marshall, R. D., et al. Investigation of the Kansas City Hyatt Regency Walkways
Collapse. National Bureau of Standards Building Science Series 143.
Washington DC: NBS, May 1982.
Kawada, Tadaki. History of the Modern Suspension Bridge. Reston, VA: ASCE
Press, 2010.
306
Bibliography
Campbell, Robert. “Builder Faced Bigger Crisis Than Falling Windows.” The
Boston Globe, March 3, 1995.
Dupre, Judith. Skyscrapers. New York: Black Dog & Leventhal, 1996.
Lago, Alberto, Dario Trabucco, and Antony Wood. Damping Technologies for
Tall Buildings. Amsterdam: Elsevier, 2019.
307
Bibliography
Wolfe, Maury I., and Robert Mark. “The Collapse of the Vaults of Beauvais
Cathedral in 1284.” Speculum 51, no. 3 (1976): 462–476.
308
Bibliography
Griffiths, Hugh, Alfred Pugsley, and Owen Saunders. Report of the Inquiry
into the Collapse of Flats at Ronan Point, Canning Town. London: Her
Majesty’s Stationery Office, 1968.
Mayville, Ronald A. “The Great Boston Molasses Tank Failure of 1919.” Civil
+ Structural Engineer Media. September 1, 2014. https://csengineermag.com/
the-great-boston-molasses-tank-failure-of-1919/.
Puleo, Stephen. Dark Tide: The Great Boston Molasses Flood of 1919. Boston:
Beacon Press, 2019.
Fisher, John W., and Sougata Roy. “Fatigue Damage in Steel Bridges and
Extending Their Life.” Advanced Steel Construction 11, no. 3 (2015): 250–268.
309
Bibliography
US District Court for the Southern District of Texas. “Channel 20, Inc.
v. World Wide Towers Services, Inc., 607 F. Supp. 551 (S.D. Tex. 1985).”
Justia. May 6, 1985. https://law.justia.com/cases/federal/district-courts/
FSupp/607/551/2371003/.
310
Bibliography
McDonald, Allan J. Truth, Lies, and O-Rings: Inside the Space Shuttle
Challenger Disaster. Gainesville, FL: University Press of Florida, 2018.
Rogers, William P., et al. Report to the President by the Presidential Commission
on the Space Shuttle Challenger Accident. Washington DC: Presidential
Commission on the Space Shuttle Challenger Accident, 1986.
311
Bibliography
Shroder, Tom, and John Konrad. Fire on the Horizon: The Untold Story of the
Explosion aboard the Deepwater Horizon. New York: Harper Audio, 2011.
Turley, J. A. From the Podium: The Cause of BP’s Macondo Blowout. Littleton,
CO: The Brier Patch, 2012.
Langewiesche, William. “What Really Brought Down the Boeing 737 Max?”
The New York Times Magazine, September 18, 2019.
Robinson, Peter. Flying Blind: The 737 MAX Tragedy and the Fall of Boeing.
New York: Random House Audio, 2021.
Andersen, Christine F., et al. The New Orleans Hurricane Protection System:
What Went Wrong and Why. Reston, VA: ASCE, 2007.
Brinkley, Douglas. The Great Deluge: Hurricane Katrina, New Orleans, and
the Mississippi Gulf Coast. New York: Harper Audio, 2006.
Link, Lewis E., et al. Performance Evaluation of the New Orleans and Southeast
Louisiana Hurricane Protection System: Draft Final Report of the Interagency
Performance Evaluation Task Force. Washington DC: US Army Corps of
Engineers, 2006. https://www.loc.gov/item/2006618548/.
312
Bibliography
Image Credits
iv: Library of Congress, Prints and Photographs Division, Xurzon/iStock/Getty Images
Plus; 4: Federal Emergency Management Agency/Wikimedia Commons/Public Domain;
12: The Illustrated London News (1847)/Wikimedia Commons/Public Domain, Robert
Stephenson. Engraving by D. J. Pound, 1860, after J. Mayall/Wellcome Library, London/
CC BY 4.0; 22: Peterrhyslewis/Wikimedia Commons/Public Domain; 23: National
Library of Scotland/Wikimedia Commons/Public Domain; 26: Illustrated London News
(1877)/Wikimedia Commons/Public Domain; 33: Garrett Fuller/Wikimedia Commons/
CC BY-SA 4.0; 34: Maps Data: Google@2022 Landsat/Copernicus; 41: H.G. Wilshire/
United States Department of the Interior United States Geological Survey; 52: Gary
Leavens/flickr/CC BY-SA 2.0; 56: Martha T/Wikimedia Commons/CC BY 2.0; 61:
FEMA News Photo/Wikimedia Commons/Public Domain; 72: Archaeodontosaurus/
Wikimedia Commons/Public Domain; 80: Danforth, Bald & Co./Wikimedia Commons/
Public Domain; 82: Brooklyn Museum/Public Domain; 92: Tristan Surtel/Wikimedia
Commons/CC BY-SA 4.0; 102: Werner Kunz/Wikimedia Commons/CC BY-SA 2.0;
113: Nadar/Wikimedia Commons/Public Domain; 114: GoodLifeStudio/iStock/Getty
Images Plus; 123: University of Toronto/Internet Archive; 124: Carter, Charles Frederick./
Wikimedia Commons/Public Domain, National Archives and Records Administration;
125: Library of Congress, Prints and Photographs Division; 144: Derek Voller geograph.org.uk/
Wikimedia Commons/CC BY-SA 2.0; 153: Boston Public Library/Wikimedia Commons/
Public Domain; 168: nimis69/E+/Getty Images Plus; 172: Saffron Blaze/Wikimedia
Commons/CC BY-SA 3.0; 174: Deryck Chan/Wikimedia Commons/CC BY-SA 4.0;
179: WaterArchives.org/Wikimedia Commons/CC BY-SA 2.0; 190: Nikonlike/iStock/
Getty Images Plus; 196: Library of Congress, Prints and Photographs Division; 206:
National Aeronautics and Space Administration/KSC; 212: NASA/Wikimedia Commons/
Public Domain; 217: IAEA Imagebank/Wikimedia Commons/CC BY-SA 2.0; 225:
AFS 86/Wikimedia Commons/CC BY-SA 4.0; 229: National Archives and Records
Administration; 230: user/Wikimedia Commons/CC BY; 241: PK-REN/Wikimedia
Commons/CC BY; 253: NASA/Wikimedia Commons/Public Domain
313
Copyright © The Teaching Company, 2022