Professional Documents
Culture Documents
There is no such thing as an "International Standard" for estimating piping man hours.
Each company recorded or not has their own unit of measure based on how they are organized and
how they operate.
Below, I have given you some data showing factors for the home office hours to do piping
engineering and design work. Regardless of the type of project, this type of data reflects only part of
the piping cost picture. The other part of the home office hour picture is the hourly rate to do this
work. This hourly rate depends on where you do the work and the level of expertise (training,
experience and supervision) the people have.
Where you have the work done includes the country, the city and the company. If the work is done
by one of the top, first class U.S., U.K. or other European engineering companies in one of their home
engineering offices you will see fewer hours but at a higher cost. This same company might choose
to out-source the work to one of its overseas partners or subsidiaries where the work may need twice
the number of hours to achieve the same level of quality. These hours, however, will be at a rate that
is far below the U.S. rate. So you need to know where the work will be done and adjust the number
of hours and the rates accordingly.
The following data is a summary of the averages of actual data from 4 representative projects
conducted in the late 1990's. The smallest was $9,000,000 and the largest was $60,000,000.
Category Data
Average Total Project Hours = 126,055
Average Total Piping Hours = 33,810
Average Percent Total Piping Hours vs. Total Project Hours = 26.82%
There are still many other factors that will impact the Total Installed Cost (TIC) of the piping for a
project. These other factors include the pipe material, the fabrication, the NDE requirements, the
logistics, the final installation, the testing and any pre-start-up preparation.
• Pipe material: This is a multi-part issue. There is the metallurgy itself (carbon steel vs. alloy. There
is a big difference between the wide ranges of materials that might be used. With-in the given metal
there is then the pipe size which affects the cost and finally there is the pipe schedule (wall thickness)
which not only affects the initial cost of the pipe but it also affects the cost of fabrication.
• Fabrication: The fabrication of the piping systems is either done in a remote “shop†or is
done at the job site. Fabrication at a shop is normally done at a cheaper cost than at the job site. The
cheaper cost is the result of the ability to use the jigs, fixtures and automatic welding capabilities that
are available in the shop. For this reason most projects choose to maximize the shop fabrication of
most piping systems. However shop fabrication is only possible up to a point. You will still have to
install the piping spools and make the final field welds.
• NDE requirements: NDE stands for Non-Destructive Examination. Depending on the applicable
Piping Code requirements different levels of NDE is required for welds in piping systems. NDE is
another cost additive to the overall picture.
• Logistics: This relates to the distance and the ramifications involved in the issue of point of
fabrication-to-point of installation. Everything from distance to politics to weather can and will affect
the logistics issue.
• Final installation: This issue is also complex. It is influenced by the job site location and the
availability of qualified personnel. The job site might be in the arctic or it might be in the middle of
the desert. Both of these bring unique problems and will add to the cost of the final project. Final
installation also includes any heat tracing, insulation and painting. In some projects it may include
dangerous and very costly “Tie-Ins†(Hot-Taps) to active systems.
• Testing: The applicable Piping Code will dictate the testing requirements. The client may also
require additional testing over-and-above the Code that will also increase the cost.
• Pre-start-up preparation: This is a category of costly work that may include special cleaning,
pickling of the pipe or other internal pipe surface preparation.
I would suggest that someone in your company has data on all or most of these categories for at
least 10 past projects. However you will need to determine, ahead of time all or most of the factors. I
recommend that you define a very clear and detailed scope of work on which to base your estimate.
Piping stress analysis is a very important activity in piping design and separate man-hours must
be claimed from the client for this. Normally, on average, piping stress analysis-related activities
require roughly 8-12% of the total piping man-hour. The man-hour estimation is done either
during the project bidding activity or during the initial phase of any project. So hardly any firm
data is available while man-hour estimation is done. So sufficient cushion needs to be added for
rework activity. The following write-up will provide a guideline for the piping stress man-hour
estimation process for any project. Broadly, there are three practices for man-hours calculation
that are followed in established EPC organizations. They are:
P&ID (If not available then man-hour estimation can be done based on preliminary
P&ID or FEED P&ID)
Line List, if available
Equipment list, if available
However, in my opinion, one should look into the exact scope of work (activity-wise) by the
stress department. Then one should consider reasonable man-hour (which normally takes based
on experience) for each activity. And finally, add all the man-hours of each activity together to
get the final man-hour. This way one could get the man-hour close to the actual.
After listing all such activities one needs to decide on actual time factors for each activity based
on experience and then finally combine all those to get the final man-hour.