Program : Dana Desa

Jenis Kegiatan : Pemb. Kantor


Ukuran/Dimensi : 12.5 x 9.0 M
Volume : 1 Unit

DATA PERHITUNGAN ( BACK UP DATA )


No
SKET GAMBAR TAKE OFF SHEET
A PEKERJAAN PERSIAPAN 1 Pembersihan Lapangan dan perataan 1 Unit
2 Pas Bouwplank 49.4 M'
3 Papan Nama Proyek 1 Bh
4 Prasasti 1 Bh

B PEKERJAAN TANAH 1. Galian Tanah


Volume Penampang
Pondasi Menerus (RKB)
V.I = T x L x P
V.I = 0.60 x 0.6 x 71.1
V.I = 25.60 M3

Pondasi Selasar Pas. Bata


V.II = T x L x P
V.II = 0.20 x 0.2 x 10.4
V.II = 0.42 M3

V.Tot = V.I+V.II
V.Tot = 26.01 M3

2. Urungan Kembali
V = 1/4 Volume Galian
6.50 M3
3. Tanah Timbun dan Pemadatan bawah lantai

V= T x L x P
V= 0.25 8 11.7
V= 23.40 M3
Selasar
V= T x L x P
V= 0.05 1.2 8
V= 0.48 M3

V.Total = 23.88 M3

4. Urugan Pasir Bawah Pondasi


Ruangan
V= T x L x P
V= 0.05 0.6 71.1
V= 2.13 M3
5. Urugan Pasir Bawah Lantai
V= T x L x P
V= 0.05 8 11.7
V= 4.68 M3

V.Tot = V.RKB+V.Bwh Lt
V.Tot = 6.81 M3

C PEKERJAAN PONDASI 1. Pasangan Batu Kosong /Aanstamping


Ruangan
V= T x L x P
V= 0.10 0.6 71.1
V= 4.266 M3
Selasar
V= T x L x P
V= 0.10 0.2 10.4
V= 0.208 M3
V.Tot = V.RKB+V.TERAS
V.Tot = 4.474 M3

2. Cor Pondasi Cyclope


Pondasi Menerus (RKB)
V.I = T x (La+lb)/2 x P
V.I = 0.60 x 0.45 x 71.1
V.I = 19.20 M3

V.Tot = 19.20 M3

Page 1 of 6
Program : Dana Desa
Jenis Kegiatan : Pemb. Kantor
Ukuran/Dimensi : 12.5 x 9.0 M
Volume : 1 Unit

DATA PERHITUNGAN ( BACK UP DATA )


No
SKET GAMBAR TAKE OFF SHEET

D PEKERJAAN DINDING 1. Pasangan Bata 1:2


RUANGAN
V.I = T x P
V.I = 0.15 x 67.5
V.I = 10.13 M2
2. Pasangan Bata 1:2 (Selasar)
V.I = T x P
V.I = 0.10 x 10.4
V.I = 1.04 M2

Volume Pasangan bata 1:2


V= 0.10 x 11.17 = 1.12 M3

Pasangan Bata 1:4 Ruangan


V.I = T x P
V.I = 3.82 x 49
V.I = 187.18 M2

V.II = T x P
V.II = 1.20 x 5.5
V.II = 6.60 M2

Luas Total Dinding


A= 193.78 M2

LUAS PINTU + JENDELA + KUSEN BLOK


Luas Pintu Unit P (1 Unit) Ptot
P1 = 1.02 x 2.15 x 3 3.32 9.96
6.58 M2
P2 = 3.70 x 2.4 x 1
8.88 M2

Luas Jendela P (1 Unit) Ptot


J1 = 1.38 x 1.10 x 5 5.00 25
7.59 M2

Ptotal = 34.96
Kubik kayu = 0.0078
Kubik Kayu 5/13 = 0.273 M3

Luas Pintu = 14.961 M2


Luas Jendela = 6.34 M2
Kusen Block
V= 0.20 x 0.40 x 34
V= 2.72 M2
LUAS KOLOM a b T x Jlh
Luas Kolom Utama = 0.20 x 0.20 x 3.82 17
= 2.60 M2
Luas Kolom PRAKTIS = 0.15 x 0.15 x 3.82 4
0.15
= 0.34 M2
0.20

0.20 0.15

LUAS TOTAL PINTU + JENDELA + KUSEN BLOK+KOLOM UTAMA + KOLOM PRAKTIS


= 28.71 M2
Luas Pas. Bata = Luas Dinding - Luas Pintu, Jendela Kusen Blok, Kolom
165.07 M2
Volume Pasangan bata = 0.10 x 165.07 = 16.51 M3

E PEKERJAAN PLASTERAN
Plesteran Selasar 1 Pc : 2 Ps, tebal 10 mm
V = Luas Selasar x (L/D)
V= 11.17 x 2
V= 22.33 M2
Plesteran Dinding 1 Pc : 4 Ps, tebal 10 mm
V = Luas Dinding x (L/D)
V= 165.07 x 2
V= 330.14 M2

Page 2 of 6
Program : Dana Desa
Jenis Kegiatan : Pemb. Kantor
Ukuran/Dimensi : 12.5 x 9.0 M
Volume : 1 Unit

DATA PERHITUNGAN ( BACK UP DATA )


No
SKET GAMBAR TAKE OFF SHEET
F PEKERJAAN BETON BERTULANG 1. SLOOF 20/25
V= a x b x P
Pembesian Tersendiri V= 0.20 x 0.25 77.9
Sloof Kolom V= 3.90 M3
2. KOLOM UTAMA 20/20
V= a x b x T x Jlh
V= 0.20 x 0.20 x 3.97 17
V= 2.70 M3
.20
25 3. KOLOM PRAKTIS 15/15
.20 V= a x b x T x Jlh
20
V= 0.15 x 0.15 x 3.97 4
V= 0.36 M3

4. Plat Lantai 900/300


V= a x b x t
V= 9.00 x 3.00 x 0.10
Kolom Praktis Balok Pinggang V= 2.70 M3

5. Rink Balk 18/15


0.15 0.15
V= a x b x P
0.15 0.15 V= 0.18 x 0.15 x 77.90
V= 2.10 M3

Ring Balk Balok Talang 6. Balok Pinggang 15/15


V= a x b x P
V= 0.15 x 0.15 x 27.00
V= 0.61 M3
0.15
0.18
7. Balok Pinggang Talang 15/15
0.15
0.15 V= a x b x P
V= 0.15 x 0.15 x 43.80
V= 0.99 M3

8. Talang 45/10
V= a x b x P
V= 0.45 x 0.10 x 43.80
V= 1.97 M3

9. Plat Talang 70/7


V= a x b x P
V= 0.70 x 0.07 x 43.80
V= 2.15 M3

10. Balk Talang 15/15


V= a x b x P x N
V= 0.70 x 0.07 x 0.80 19
V= 0.74 M3
Volume Total Beton Bertulang
V.Tot. = 18.21 M3

F PEKERJAAN ATAP 3. Luas Atap Metal 0.30 (Star room)


A1 = 0.25 x Alas x t
A1 = 0.25 x 4.50 x 2.75
A1 = 3.09 M2
A2 = ((a + b) /2) x t
A2 = 4.00 + 4.00 x 2.75
A2 = 11.00 M2
A2 = ((a + b) /2) x t
A2 = 8.40 + 8.40 x 2.75
A2 = 23.10 M2
A3 = 0.25 x Alas x t
A3 = 0.25 x 5.00 x 2.75
A3 = 3.44 M2
A4 = ((a + b) /2) x t
A4 = 8.40 + 12.30 x 2.75
A4 = 28.46 M2
A5 = ((a + b) /2) x t
A5 = 4.25 + 7.40 x 2.75
A5 = 16.02 M2

Luas Total Atap = 85.11 M2

Luas Seng = 0.75 x 2.20 = 1.65 M2


Jlh Seng = 52.58 ≈ 53.0 Lbr

2. Rabung Seng P atap / P Rabung


V= 26.40 1.8
V= 14.67 ≈ 15.0 Lbr

Page 3 of 6
Program : Dana Desa
Jenis Kegiatan : Pemb. Kantor
Ukuran/Dimensi : 12.5 x 9.0 M
Volume : 1 Unit

DATA PERHITUNGAN ( BACK UP DATA )


No
SKET GAMBAR TAKE OFF SHEET
Kuda-Kuda Rangka Kayu
Kuda-Kuda K
1. Balok Tarik 2x 6/14 cm (2,5/6") Jlh Kuda-kuda
V= 4.8 x 2 x 3.00
V= 28.80 M'
Tot. 2,5/6" = 28.80 M'

2. Kaki Kuda-kuda 6/14 cmm(2,5/6") Jlh Kuda-kuda


V= 2.75 x 2 x 3.00
V= 16.50 M'
Tot. 2,5/6" = 16.50 M'

3. Hanger 6/14 cm (2,5/6") Jlh Kuda-kuda


V= 1.35 x 1 x 3.00
V= 4.05 M'

Total Kayu 6/14 cm (2,5/6") Pjg Kayu


V= 49.35 / 4.80
V= 10.28 Btg

4. Balok Skoor 5/14 cm (2/6") Jlh Kuda-kuda


V= 0.9 X 2 x 3.00
V= 5.40 M'
5. Balok TARIK 5/14 cm (2/6") Jlh Kuda-kuda
V= 1 x 2 x 3.00
V= 6.00 M'
Tot. 2/6" = 11.40 M'

Total Kayu 5/14 cm (2/6") Pjg Kayu


V= 11.40 / 4.80
V= 2.38 Btg
Kuda-Kuda K2
1. Balok Tarik 2x 6/14 cm (2,5/6") Jlh Kuda-kuda
V= 4.3 x 2 x 2.00
V= 17.20 M'
Tot. 2,5/6" = 17.20 M'

2. Kaki Kuda-kuda 6/14 cmm(2,5/6") Jlh Kuda-kuda


V= 2.75 x 2 x 2.00
V= 11.00 M'
Tot. 2,5/6" = 11.00 M'

3. Hanger 6/14 cm (2,5/6") Jlh Kuda-kuda


V= 1.35 x 1 x 2.00
V= 2.70 M'

Total Kayu 6/14 cm (2,5/6") Pjg Kayu


V= 30.90 / 4.80
V= 6.44 Btg

4. Balok Skoor 5/14 cm (2/6") Jlh Kuda-kuda


V= 0.9 X 2 x 2.00
V= 3.60 M'
5. Balok TARIK 5/14 cm (2/6") Jlh Kuda-kuda
V= 1 x 2 x 2.00
V= 4.00 M'
Tot. 2/6" = 7.60 M'

Total Kayu 5/14 cm (2/6") Pjg Kayu


V= 7.60 / 4.80
V= 1.58 Btg
Kuda-Kuda Setengah
1. Balok Tarik 2x 6/14 cm (2,5/6") Jlh Kuda-kuda
V= 2.5 x 2 x 3.00
V= 15.00 M'
Tot. 2,5/6" = 15.00 M'

2. Kaki Kuda-kuda 6/14 cmm(2,5/6") Jlh Kuda-kuda


V= 2.75 x 2 x 3.00
V= 16.50 M'
Tot. 2,5/6" = 16.50 M'

Total Kayu 6/14 cm (2,5/6") Pjg Kayu


V= 31.50 / 4.80
V= 6.56 Btg

3. Balok Skoor 5/14 cm (2/6") Jlh Kuda-kuda


V= 0.9 X 1 x 3.00
V= 2.70 M'

Tot. 2/6" = 2.70 M'

Total Kayu 5/14 cm (2/6") Pjg Kayu


V= 2.70 / 4.80
V= 0.56 Btg

Page 4 of 6
Program : Dana Desa
Jenis Kegiatan : Pemb. Kantor
Ukuran/Dimensi : 12.5 x 9.0 M
Volume : 1 Unit

DATA PERHITUNGAN ( BACK UP DATA )


No
SKET GAMBAR TAKE OFF SHEET
1. Balok Nok 5/10 cm (2/4")
V= 12.65 x 1
V= 12.65 M'
Total Kayu 5/10 cm (2/3") Pjg Kayu
V= 12.65 / 4.80
V= 2.64 Btg

2. Gording 5/7 cm (2/3") Pjg


V= 85.70
V= 85.70 M'
Total Kayu 5/7 cm (2/3") Pjg Kayu
V= 85.70 / 4.80
V= 17.85 Btg

3. Lisplank 2/25 Pjg


V= 42.00
V= 42.00 M'
Total Kayu 2/25 cm Pjg Kayu
V= 42.00 / 4.80
V= 8.75 Lbr
Jlh Kuda-kuda
4. Baut 12" = 18 x 5 = 90 Bh
Plat Strip 2 x 5 = 10 Bh

G PEKERJAAN PAS. PLAFOND Luas Plafond


RKB
A= P x L
A= 12.70 x 8.00
A= 101.60 M2

Luas Total = 101.60

Tripleks 4 mm
Luas Tripleks= 2.40 x 1.20 = 2.88 M2
Volume Triplek= 35.28 ≈ 35.00 Lbr

RUANGAN
- Kayu 5/5" Melintang
= 11.58 x 8 = 92.67 / 4.8
19.31 Btg
Memanjang
= 7.67 x 12.7 = 97.37 / 4.8
= 20.28 Btg

- Gantungan= 100.65 / 4.8 = 20.97 Btg


Total Kayu = 60.56 ≈ 61.00 Btg

Profil Siku = 94.80 / 4.80 = 19.75 Btg


19.75 ≈ 20.00 Btg

H PEKERJAAN LANTAI
1. Cor Beton Tumbuk t = 5 cm
RKB
L.I = P x L x t
L.I = 12.70 x 8 x 0.05
L.I = 5.08 M3

V.Tot = 5.08 M3

Page 5 of 6
Program : Dana Desa
Jenis Kegiatan : Pemb. Kantor
Ukuran/Dimensi : 12.5 x 9.0 M
Volume : 1 Unit

DATA PERHITUNGAN ( BACK UP DATA )


No
SKET GAMBAR TAKE OFF SHEET
I PAS. KERAMIK
1. Pasang Keramik
Kantor 2 Ruang + Gudang
Keramik 40x40 (Speks. Ikat)
L. I= P x L
L. I= 11.50 x 8
L. I= 49.00 M2

TERAS
Keramik 40x40 anti Slip (Speks. Ikat)
L. I= P x L
L. I= 8.00 x 1.2
L. I= 10.60 M2

Luas Tot.= 10.60 11.00 M2

Bon bon keramik = 17 M

1 Unit Unit
J PEKERJAAN KUNCI 1. Pasang kunci tanam 2 slag = 1 x 3 = 3 Bh
2. Pasang engsel pintu = 3 x 2 = 6 Ps
3. Pasang engsel jendela = 2 x 5 = 10 Ps
4. Tarikan Jendela = 1 x 5 = 5 Ps
5. Hak Angin = 2 x 5 = 10 Ps
6. Grandel Pintu = 1 x 3 = 3 Ps
6. Grandel Jendela = 1 x 5 = 5 Ps

K PEKERJAAN PENGECATAN 1. Cat Dinding Tembok + Kolom


Luas Dinding Tembok = Luas Plesteran + Luas Kolom = 332.74 M2
2. Cat Plafond+Profil
Cat Plafond = Luas Plafon = 121.60 M2
3. Cat Kusen
Cat Kusen Pintu + Jendela = 25.77 M2

M PEKERJAAN LISTRIK 1. Instalasi Listrik


No Uraian Volume Satuan Keterangan
1 Saklar Ganda 4 Bh
2 Saklar Tunggal
3 Stop Kontak 4 Bh
4 Box Zekering 1 Bh
5 Kabel Nym 1.2mm 216 m
6 Pipa PVC 3/4" 15 Btg
7 Lampu 10 Bh
8 Simpang 3 Bulat 5 Bh
9 Elbow 7 Bh
10 Clip Pipa 30 Bh
11 Fitting 10 Bh

Luas Lbr (4.8 m) Btg (4.8 m) Multipleks Lbr


Sloof 20/25 = 39.0 = 45.08 27.05
Kolom 20/20 = 50.816 = 35.29 17.64

Kolom Tombak layar 15/15 = 5.76 = 6.67 4.00

Ring Balk 18/15 = 28.044 = 32.46 19.48


Balok Pinggang 15/15 = 8.1 = 9.38 5.63
Balok Top Gevel 15/15 = 13.14 = 15.21 9.12

50% 100.56
Papan Mal = 108.79 ≈ 51.00 Lbr
Multipleks 9 mm = 17.64 ≈ 9.00 Lbr
Kayu Perancah 1/2", Klas III = 100.56 ≈ 51.00 Btg

Page 6 of 6