Professional Documents
Culture Documents
`54
A standard loss of 10% of input is expected to occur. Actual input was as under: 53000 tonne of
material A at ` 7 per tonnes.
28000 tonne of material B at ` 5.30 per tonnes. 19000 tonne of material C at ` 2.20 per tonnes.
Actual output for a period was 92700 tonnes of product Z.
Compute:
a. Material cost variance,
b. Material price variance,
c. Material usagevariance,
d. Material Mix Variance,
e. Material Yield Variance.
Answer:
Material cost variance `5,000 A
Material price variance `12,200 A
Material usage variance `7,200 F
Material sub usage or yield variance `16,200 F
Material mix variance `9,000 A
A 40% 4
B 60% 3
The standard loss in processing is 15%. During April 2021, the company produced 1,700 kgs. of
finished output.
The position of stock and purchases for the month of April 2021 are as under:
A 35 5 800 3,400
B 40 50 1,200 3,000
Question 4.
The standard material input required for 1000 kgs of a finished product are given below:
P 450 20
Q 400 40
R 250 60
1100
Actual production in a period was 20000 kgs. of the finished product for which the actual
quantities of material used and the prices paid thereof, are as under:
P 10000 19
Q 8500 42
R 4500 65
% Rs. % Rs.
Raw Material I 50 40 60 42
Raw Material II 30 20 20 16
Answer:
Material cost variance `19,600 A
Material price variance `5,600 A
Material usage variance `14,000 A
Material sub usage or yield variance `Nil
Material mix variance `14,000 A
A 50 20 60 21 5000
B 30 10 20 8 2000
C 20 5 20 6 1200
Answer:
Material cost variance `17,500 A
Material price variance `3,000 A
Material usage variance `14,500 A
Material sub usage or yield variance `7,000 A
Material mix variance `7,500 A
A 8 kg 6.00
B 4 kg 4.00
During April, 1,000 kg of CEMCO were produced. The actual consumption of materials is as
under:
A 750 7.00
B 500 5.00
CALCULATE (a) Material Cost Variance; (b) Material Price Variance; (c) Material usage
Variance.
Answer:
Material cost variance `1,350 A
Material price variance `1,250 A
Material usage variance `100 A
Question 8. Study Material, 2017 Nov Similar
The standard mix to produce one unit of a product is as follows:
During the month of April, 10 units were actually produced and consumption was as follows:
Answer:
Material cost variance `2,225 A
Material price variance `1,875 A
Material usage variance `350 A
Material sub usage or yield variance `1,250 A
Material mix variance `900 F
A 60 20 1200
B 40 30 1200
- Normal loss 20
Output 80 2400
Actual data:
A 70 ? ?
B ? 30 ?
Answer:
Actual Price of material A `21.5
Actual Quantity of material B 39 units
Material Price Variance `105 A
Material Usage Variance `170 A
Material Mix Variance `46 F
Material Sub Usage Variance `216 A
Question 10. Study Materials
One kilogram of product K requires two chemicals A and B. The following were the details of
product K for the month of June 2021:
a. Standard mix for chemical A is 50% and chemical B is 50%.
b. Standard price kilogram of chemical A is ` 12 and chemical B is ` 15.
c. Actual input of chemical B is 70 kilograms.
d. Actual price per kilogram of chemical A is ` 15
e. Standard normal loss is 10% of total input
f. Total Material cost variance is ` 650 adverse.
g. Total Material yield variance is ` 135 adverse.
You are required to CALCULATE:
a. Total Material mix variance
b. Total Material usage variance
c. Total Material price variance
d. Actual loss of actual input
e. Actual input of chemical A
f. Actual price per kg. of chemical B
Answer:
Total Material mix variance `45 A
Total Material usage variance `180 A
Total Material price variance `470 A
Actual loss of actual input 20 Kgs
Actual input of chemical A 40 Kgs
Actual price per kg. of chemical B `20
Estimation-
Material-A 800 ? --
--
Actuals-
1480 kg of output produced.
Material-A 900 ? --
Material-B ? 32.50 --
59,825
Other Information-
Material Cost Variance = ` 3,625 (F) Material Price Variance = ` 175 (F)
You are required to CALCULATE:
a. Standard Price of Material-A;
b. Actual Quantity of Material-B;
c. Actual Price of Material-A;
d. Revised standard quantity of Material-A and Material-B; and
e. Material Mix Variance.
Answer:
Standard Price of Material-A; `45
Actual Quantity of Material-B; 650 Kgs
Actual Price of Material-A; `43
Revised standard quantity of
Material-A 886 Kgs
Material-B 664 Kgs
Material Mix Variance `210 A
Answer:
Actual quantity 5,100 Kgs
Actual price of material used `140
Material usage variance `15,000 A
Material cost variance `36,000 F
Answer:
Labour cost variance `256 A
Labour rate variance `160 F
Labour efficiency variance `436 A
Labour mix variance `108 A
Labour idle time variance `160 A
Labour sub efficiency variance `328 A
Question 15.
The following was the composition of a gang of workers in a factory during a particular month,
in one of the production departments. The standard composition of workers and wager rate per
hour were as below:
Skilled : Two workers at a standard rate of `. 20 per hour each.
Semi-skilled : Four workers at a standard rate of `12 per hour each
Unskilled : Four workers at a standard rate of ` 8 per hour each.
The standard output of the gang was four units per hour, of the product.
During the month in question, however, the actual composition of the gang and hourly rates paid
were as under:
Nature of worker No. of Worker Wage rate paid per worker per hour engaged
Skilled 2 `20
Semi-skilled 3 `14
Unskilled 5 `10
The gang was engaged for 200 hours during the month, which included 12 hours when no
production was possible, due to machine break-down, 810 units of the product were recorded as
output of the gang during the month.
You are required:
(a) to compute the standard unit labour cost of the product;
(b) to compute the total variance in labour cost during the month; and
(c) analyse the variances in (b) above into sub-variances and reconcile.
Answer:
Labour cost variance `256 A
Labour rate variance `160 F
Labour efficiency variance `436 A
Labour mix variance `108 A
Labour idle time variance `160 A
Labour sub efficiency variance `328 A
Question 16.
The standard labour employment and the actual labour engaged in a week for a job are as under:
During the 40 hours working week, the gang may produce 1,800 labour hours of work.
CALCULATE:
(a) Labour Cost Variance (b) Labour Rate Variance
(c) Labour Efficiency Variance (d) Labour Mix Variance
(e) Labour Yield Variance
Answer:
Answer:
Labour cost variance `2,424 A
Labour rate variance `2,000 A
Labour efficiency variance `424 A
Labour mix variance `80 F
Labour idle time variance Nil
Labour sub efficiency variance `504 A
(`)
Direct Material:
32.00
Direct Labour:
The company manufactured and sold 6,000 units of the product during the year. Direct material
costs were as follows:
12,500 units of A at ` 4.40 per unit
18,000 units of B at ` 2.80 per unit
88,500 units of C at ` 1.20 per unit
The company worked 17,500 direct labour hours during the year. For 2,500 of these hours, the
company paid at ` 12 per hour while for the remaining, the wages were paid at standard rate.
CALCULATE
a. Materials price variance & Usage variance
b. Labour rate & Efficiency variances.
Answer:
Materials price variance `19,100 A
Material Usage variance `500 A
Labour rate variance `10,000 A
Labour Efficiency variances. `4,000 F
Question 18. Study Material
The following information is available from the cost records of Novell & Co. for the month of
March 2021:
You are required to CALCULATE relevant material and labour variance for the month.
Answer:
Material cost variance `11,600 A
Material price variance `7,600 A
Material usage variance `4,000 A
Labour cost variance `6,750 A
Labour rate variance `4,950 A
Labour efficiency variance `1,800 A
Question 19. Study Material
XYZ Company has established the following standards for factory overheads.
Variable overhead per unit: ` 10/-
Fixed overheads per month ` 1,00,000
Capacity of the plant 20,000 units per month. The actual data for the month are as follows:
Actual overheads incurred `3,00,000
Actual output (units) 15,000 units
CALCULATE overhead variances :
a. Production volume variance
b. Overhead expense variance
Answer:
Production volume variance `25,000 A
Overhead expense variance `50,000 A
Answer:
Expense variance `2,000 F
Volume variance `16,680 A
Total fixed overheads variance 14,680 A
Question 21. Study Material
Following information is available from the records of a factory:
Budget Actual
Answer:
Fixed overhead cost variance, `1,500 A
Expenditure variance, `2,000 A
Volume variance. `500 F
Question 22.
XYZ Ltd. has furnished you the following information for the month of August:
Budget Actual
Working days 25 26
Answer:
F.O. cost Variance `1,250 (A)
F.O. Expenditure ` 5,000 (A)
F.O. Volume Variance ` 3,750 (F)
F.O. Efficiency Variance `750 (A)
F.O. Capacity Variance ` 2,700 (F)
F.O. Calendar Variance `1,800 (F)
V.O. Cost variance ` 3,000 (A)
V.O. Expenditure Variance ` 2,000 (A)
V.O. Efficiency Variance `1,000 (A)
Budgeted fixed overhead rate is ` 1.00 per hour. In July, the actual hours worked were 31,500.
CALCULATE the following variances:
a. Volume variance.
b. Expenditure variance.
c. Total overhead variance.
Answer:
Volume variance. `3,000 F
Expenditure variance. `1,000 A
Total overhead variance. `2,000 F
Budget Actual
The standard time to produce one unit of the product is 20 hours. CALCULATE relevant
Variable overhead variances.
Answer:
Variable overhead cost variance `150 A
Variable overhead expenditure variance `400 A
Variable overhead efficiency variance `250 F
Question 25. Study Material
The following data has been collected from the cost records of a unit for computing the various
fixed overhead variances for a period:
Budgeted Actual
Required:
CALCULATE (i) Fixed Overhead Cost Variance (ii) Fixed Overhead Expenditure Variance (iii)
Fixed Overhead Volume Variance (iv) Fixed Overhead Efficiency Variance and (v) Fixed
Overhead Capacity Variance.
Answer:
Fixed Overhead Cost Variance Nil
Fixed Overhead Expenditure Variance `60,000 A
Fixed Overhead Volume Variance `60,000 F
Fixed Overhead Efficiency Variance `40,000 A
Fixed Overhead Capacity Variance. `1,00,000 F
Answer:
Efficiency variance `6,360 F
Capacity variance `17,280 A
Calendar variance `5,760 A
Expenditure variance `2,000 F
Volume variance `16,680 A
Total Fixed overhead variance `14,680 A
Description of Fixed cost per unit Variable cost per Total cost per unit
overhead in ` unit in ` in `
The factory has actually produced only 100 units in a particular month. Details of overheads
actually incurred have been provided by the accounts department and are as follows:
You are required to CALCULATE the Overhead volume variance and the overhead expense
variances.
Answer:
Overhead Volume Variance `3,00,000 A
Variable Overhead Expenditure Variance Nil
Fixed Overhead Expenditure Variance `4,00,000 A
Question 29. Study Material
The following information was obtained from the records of a manufacturing unit using standard
costing system.
Standard Actual
Working days 20 21
Actual overheads were ` 2,95,000 out of which ` 62,500 fixed . Actual hours 74,000 Overheads
are based on the following flexible budget
You are required to calculate the following overhead variances (on hour’s basis) with appropriate
workings:
a. Variable overhead efficiency and expenditure variance
b. Fixed overhead efficiency and capacity variance.
Answer:
Variable overhead efficiency variance `11,400 F
Variable overhead expenditure variance `10,500 A
Fixed overhead efficiency variance `3,800 F
Fixed overhead capacity variance `14,000 F
Answer:
Fixed Overhead Expenditure Variance `800 A
Actual Overheads Incurred `12,800
Actual Hours for Actual Production `1,600 hours
Fixed Overhead Capacity Variance `4,000 A
Standard hours for Actual Production 2,000 hours
Fixed Overhead Efficiency Variance `2,000 F
Answer:
Variable overhead expenditure variance `4,800 A
Variable overhead efficiency variance `8,400 F
Fixed overhead budget variance `21,000 F
Fixed overhead capacity variance `18,500 A
Fixed overhead efficiency variance `17,500 F
Capacity ratio 91.63%
Efficiency ratio 108.64%
Activity ratio 99.55%
Question 33. Nov 21
In a manufacturing company the standard units of production for the year were fixed at 1,20,000
units and overhead expenditures were estimated to be as follows: 10
Fixed 12,00,000
Semi-variable (60% expenses are of fixed nature and 40% are of 1,80,000
variable nature)
Variable 6,00,000
Actual production during the month of April, 2021 was 8,000 units. Each month has 20 working
days. During the month there was one public holiday. The actual overheads were as follows :
Particulars Amount (`)
Fixed 1,10,000
Semi-variable (60% expenses are of fixed nature and 40% are of variable) 19,200
Variable 48,000
You are required to calculate the following variances for the month of April 2021:
(`)
1,130
Budgeted output for the third quarter of a year was 10,000 Kg. Actual output is 9,000 Kg. Actual
cost for this quarter are as follows :
(`)
Answer:
Material cost variance `30,600 A
Material price variance `11,400 F
Material usage variance `42,000 A
Variable overhead variance `12,200 A
Variable overhead efficiency variance `2,000 A
Variable overhead expenditure variance `10,200 A
Labour cost variance `24,400 A
Labour rate variance `20,400 A
Labour efficiency variance `4,000 A
The production schedule for the month of June, 2013 required completion of 40,000 units.
However, 40,960 units were completed during the month without opening and closing work-in-
process inventories.
Purchases during the month of June, 2013, 2,25,000 kg. of material at the rate of ` 4.50 per kg.
Production and Sales records for the month showed the following actual results.
Material used 2,05,600 kg.
Direct labour 1,21,200 hours; cost incurred ` 3,87,840
Total factory overhead cost incurred ` 1,00,000
Sales 40,000 units
Selling price to be so fixed as to allow a mark-up of 20 per cent on selling price.
Required:
a. Calculate material variances based on consumption of material.
b. Calculate labour variances and the total variance for factory overhead.