You are on page 1of 13

RENCANA ANGGARAN BIAYA SARPRAS

KABUPATEN SERANG
KECAMATAN CARENANG
DESA MEKARSARI
PROVINSI BANTEN

JENIS PEKERJAAN : Rabat Beton Ready Mix


VOLUME : P: 210m L: 3.50m T:0.15m
: P: 150m L: 2.50m T:0.15m
LOKASI : Kp. Cigolok RT 008 RW. 004

TAHUN ANGGARAN : 2024


BIAYA : Rp 281,300,000

" Program Kementrian Pedesaan " 2024


REKAPITULASI RENCANA ANGGARAN BIAYA

Kegiatan : -
Pekerjaan : Rabat Beton Ready Mix
Lokasi : Kp. Cigolok RT 008 RW. 004
Provinsi : Banten
Kabupaten : Serang
Kecamatan : Carenang
Desa : Mekarsari
Sumber Dana : DD TA.2024
Volume : P: 210m L: 3.50m T:0.15m
: P: 150m L: 2.50m T:0.15m

NO URAIAN JUMLAH HARGA

A BELANJA MODAL ADM KEGIATAN 7,344,000.00

B BELANJA MODAL BAHAN 212,225,000.00

C BELANJA MODAL ALAT 25,485,000.00

D BELANJA MODAL UPAH 36,246,000.00

a. Jumlah Harga Pekerjaan (A+B+C+D) 281,300,000.00


b. Pajak Pertambahan Nilai (PPN 11%+PPH 1.5%) 26,528,125.00
c. Total Biaya Pekerjaan 254,771,875.00
f. Dibulatkan 254,771,800.00

TERBILANG =

Disetujui/Mengesahkan : Di Ketahui Dibuat dan di Verifikasi oleh :


Kepala Desa ………… Pelaksana Kegiatan Konsultan Perencanaan

……………………….. ……………………….. Irfan Rizky Mu'tasim, ST


NRPDes.
RENCANA ANGGARAN BIAYA

Kegiatan : -
Pekerjaan : Rabat Beton Ready Mix Desa : Mekarsari
Lokasi : Kp. Cigolok RT 008 RW. 004 Sumber Dana : DD TA.2024
Provinsi : Banten Volume : P: 210m L: 3.50m T:0.15m
Kabupaten : Serang P: 150m L: 2.50m T:0.15m
Kecamatan : Carenang

HARGA JUMLAH
BOBOT
URAIAN VOLUME Satuan SATUAN TOTAL
( Rp. ) ( Rp. ) (%)
1. BELANJA MODAL ADM KEGIATAN
Jasa Konsultansi Perencanaan Max 1.5% 1.00 Paket 4,215,000.00 4,215,000.00 1.50%
Honorarium TPK Ketua 1.00 Keg 850,000.00 850,000.00 0.30%
Honorarium TPK Sekretaris 1.00 Keg 710,000.00 710,000.00 0.25%
Honorarium TPK Anggota 1.00 Keg 540,000.00 540,000.00 0.19%
Papan Nama Kegiatan 1.00 Buah 350,000.00 350,000.00 0.12%
Prasasti 1.00 Buah 679,000.00 679,000.00 0.24%
Sub Total 1) 7,344,000.00 2.61%
2. BELANJA MODAL BAHAN
Paku 4 s/d 7 cm 33.00 Kg 23,000.00 759,000.00 0.27%
Kayu Kaso 4/6 cm 27.00 Btg 23,000.00 621,000.00 0.22%
Kayu Papan Bekisting 71.00 Btg 28,000.00 1,988,000.00 0.71%
Agregat A 140.00 M3 272,000.00 38,080,000.00 13.54%
Beton Ready Mix K-250 170.00 M3 992,000.00 168,640,000.00 59.95%
Polytene 125 mikron (Plastik cor) 67.00 Roll 24,000.00 1,608,000.00 0.57%
Alat Bantu 1.00 Ls 529,000.00 529,000.00 0.19%
Sub Total 2) 212,225,000.00 75.44%
3. BELANJA MODAL ALAT
Sewa Gerobak Roda 2 56.00 Hari 50,000.00 2,800,000.00 1.00%
Sewa Mobil Dump Truck 17.00 Hari 1,080,000.00 18,360,000.00 6.53%
Mobilisasi Uji Coring 1.00 Ls 1,000,000.00 1,000,000.00 0.36%
Uji Coring Beton 7.00 titik 400,000.00 2,800,000.00 1.00%
Uji Mutu Beton 7.00 titik 75,000.00 525,000.00 0.19%
Sub Total 3) 25,485,000.00 9.06%
4. BELANJA MODAL UPAH
Pekerja 326.00 HOK 96,000.00 31,296,000.00 11.13%
Tukang 45.00 HOK 110,000.00 4,950,000.00 1.76%
Sub Total 4) 36,246,000.00 12.89%
TOTAL 1+2+3+4 281,300,000.00 100.00%

,………… , 2023
Disetujui : Di Ketahui Dibuat dan di verifikasi oleh :
Kepala Desa …….. Pelaksana Kegiatan Konsultan Perencanaan

............................................ ............................................ Irfan Rizky Mu'tasim, ST


ANALISA HARGA SATUAN PEKERJAAN

Kegiatan : - Desa : Mekarsari

Pekerjaan : Rabat Beton Ready Mix Sumber Dana : DD TA.2024


Lokasi : Kp. Cigolok RT 008 RW. 004
Provinsi : Banten
Kabupaten : Serang
Kecamatan : Carenang

Total (Koef x
Item Pekerjaan Ref. Analisa Koefisien Satuan Volume Harga Satuan (Rp.) Biaya (Rp.)
Volume Gbr)

Pembersihan Lokasi 28/PRT/M/2016 M2 1,110.00


A TENAGA T.01.a

Pekerja 0.060 HOK 66.60 Rp 96,000 Rp 6,393,600

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) Rp 6,393,600


Angkut Material/Langsiran 28/PRT/M/2016 M3 277.50
A TENAGA T.15.d.1

Pekerja 0.300 HOK 83.25 Rp 96,000 Rp 7,992,000


B ALTA
Sewa Gerobak Roda 2 0.2000 Hari 55.50 Rp 50,000 Rp 2,775,000
Sewa Mobil Dump Truck 0.0600 Hari 16.65 Rp 1,080,000 Rp 17,982,000

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) Rp 28,749,000


Total (Koef x
Item Pekerjaan Ref. Analisa Koefisien Satuan Volume Harga Satuan (Rp.) Biaya (Rp.)
Volume Gbr)

Beton Ready Mix K-250 AHSP/2022 M3 166.50


A TENAGA 2.2.3.a.(a)
Pekerja 0.4000 HOK 66.60 Rp 96,000 Rp 6,393,600
Tukang 0.1000 HOK 16.65 Rp 110,000 Rp 1,831,500
B BAHAN
Beton Ready Mix K-250 1.0200 M3 169.83 Rp 992,000 Rp 168,471,360
Polytene 125 mikron (Plastik cor) 0.4000 Roll 66.60 Rp 24,000 Rp 1,598,400

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) Rp 178,294,860


Lapis Pondasi Agregat A 28/PRT/M/2016 M3 111.00
A TENAGA 5.1.(1)
Pekerja 0.4760 HOK 52.84 Rp 96,000 Rp 5,072,256
B BAHAN
Agregat A 1.2586 M3 139.70 Rp 272,000 Rp 37,999,651

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) Rp 43,071,907


Beskiting atau Acuan 2x Pakai 28/PRT/M/2016 M2 108.00
A TENAGA A.4.1.1.21
Pekerja 0.5200 HOK 56.16 Rp 96,000 Rp 5,391,360
Tukang 0.2600 HOK 28.08 Rp 110,000 Rp 3,088,800
B BAHAN
Kayu Papan Bekisting 0.6500 Btg 70.20 Rp 28,000 Rp 1,965,600
Kayu Kaso 4/6 cm 0.2500 Btg 27.00 Rp 23,000 Rp 621,000
Paku 4 s/d 7 cm 0.3000 Kg 32.40 Rp 23,000 Rp 745,200

JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) Rp 11,811,960


JUMLAH TOTAL Rp 262,415,347
HARGA DASAR SATUAN UPAH

HARGA HARGA
JUMLAH
No. URAIAN KODE SATUAN SATUAN SATUAN SATUAN JUMLAH KET.
PEMBULATAN
( Rp.) ( Rp.)

1. Pekerja HOK 96,000.00 SSH DESA


2. Tukang HOK 110,000.00 SSH DESA

DAFTAR HARGA DASAR SATUAN BAHAN

HARGA PPN PPH


JUMLAH
No. URAIAN KODE SATUAN SATUAN 11% 1.50% JUMLAH KET.
PEMBULATAN
( Rp.)

1 Paku 4 s/d 7 cm Kg 21,000.00 2,310.00 315.00 23,625.00 23,000.00 SSH DESA


2 Kayu Kaso 4/6 cm Btg 21,000.00 2,310.00 315.00 23,625.00 23,000.00 SSH DESA
3 Kayu Papan Bekisting Btg 25,200.00 2,772.00 378.00 28,350.00 28,000.00 SSH DESA
4 Agregat A M3 242,550.22 26,680.52 3,638.25 272,869.00 272,000.00 SSH DESA
5 Beton Ready Mix K-250 M3 882,000.00 97,020.00 13,230.00 992,250.00 992,000.00 SSH DESA
6 Polytene 125 mikron (Plastik cor) Roll 22,049.78 2,425.48 330.75 24,806.00 24,000.00 SSH DESA

DAFTAR BIAYA SEWA PERALATAN PER JAM KERJA

BIAYA PPN PPH JUMLAH


SEWA 11% 1.50% JUMLAH
No. URAIAN KODE SATUAN KET.
ALAT/JAM PEMBULATAN
(di luar PPN)
1 Sewa Gerobak Roda 2 Hari 50,000.00 50,000.00 SSH Desa
2 Sewa Mobil Dump Truck Hari 1,080,000.00 1,080,000.00 SSH Desa
LEMBAR PERHITUNGAN VOLUME
Rabat Beton Ready Mix
Kp. Cigolok RT 008 RW. 004

Pembersihan Lokasi 1110.000.


PANJANG L J LUAS
No. URAIAN
(M1) (M1) (Bh) M2
1. Segmen 1 210.00 3.50 1.00 735.000
2. Segmen 2 150.00 2.50 1.00 375.000

360.00 JUMLAH = 1,110.000

Angkut Material/Langsiran 277.500.


Vol VOLUME
No. URAIAN
(M3) M3
1. Beton 166.50 166.500
2. Agregat 111.00 111.000
- JUMLAH = 277.500

Beton Ready Mix K-250 166.500.


PANJANG L T J VOLUME
No. URAIAN
(M1) (M1) (M1) (Bh) M3
1. Segmen 1 210.00 3.50 0.15 1.00 110.250
2. Segmen 2 150.00 2.50 0.15 1.00 56.250

360.00 JUMLAH = 166.500

Lapis Pondasi Agregat A 111.000.


PANJANG L T J VOLUME
No. URAIAN
(M1) (M1) (M1) (Bh) M3
1. Segmen 1 210.00 3.50 0.10 1.00 73.500
2. Segmen 2 150.00 2.50 0.10 1.00 37.500

360.00 JUMLAH = 111.000

Beskiting atau Acuan 2x Pakai 108.000.


PANJANG T J LUAS
No. URAIAN
(M1) (M1) (Bh) M2
1. Segmen 1 210.00 0.15 2.00 63.000
1. Segmen 2 150.00 0.15 2.00 45.000

360.00 JUMLAH = 108.000

Perhitungan Volume - 7
KURVA RENCANA PELAKSANAAN PEKERJAAN FISIK

Kegiatan : -
Pekerjaan : Rabat Beton Ready Mix
Lokasi : Kp. Cigolok RT 008 RW. 004
Kabupaten : Serang
Sumber Dana : DD TA.2024

BOBOT MINGGU KE-1 MINGGU KE-2 MINGGU KE-3 MINGGU KE-4


NO JENIS PEKERJAAN Jumlah KET
(%) H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11 H12 H13 H14 H15 H16 H14 H18 H19 H20 H21 H22 H23 H24 H28 H26 H27 H28

1 Pembersihan Lokasi 6,393,600.00 2.38 0.24 0.24 0.24 0.24 0.24 0.24 0.24 0.24 0.24 0.24 100

2 Angkut Material/Langsiran 28,749,000.00 10.71 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 80
3 Beton Ready Mix K-250 178,294,860.00 66.45 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 2.56 60
4 Lapis Pondasi Agregat A 43,071,907.20 16.05 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 0.62 40
5 Beskiting atau Acuan 2x Pakai 11,811,960.00 4.40 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 20
0
JUMLAH 268,321,327.20 100.00
RENCANA 1.28 1.45 4.01 4.01 4.01 4.01 4.01 4.01 4.01 4.01 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.77 3.34 2.73 2.56
KUMULATIF PROGRES RENCANA - - 1.28 2.74 6.75 10.76 14.77 18.77 22.78 26.79 30.80 34.81 38.58 42.35 46.12 49.90 53.67 57.44 61.21 64.98 68.75 72.52 76.29 80.06 83.83 87.61 91.38 94.72 97.44 100.00
FOTO DOKUMENTASI

Rabat Beton Ready Mix Kp. Cigolok RT 008 RW. 004 Desa Mekarsari

PROGRES

0%

PROGRES

0%

PROGRES

0%
FOTO DOKUMENTASI

Rabat Beton Ready Mix Kp. Cigolok RT 008 RW. 004 Desa Mekarsari

PROGRES

0%

PROGRES

0%

PROGRES

0%
RENCANA JALAN BETON

SEGMEN 2 (P.150m)
Provinsi BANTEN

Kabupaten SERANG

Kecamatan CARENANG

Desa MEKARSARI

JENIS PRASARANA

JUDUL GAMBAR

DIBUAT OLEH :
Jalan Desa

Irfan Rizki Mu'tasim, ST


SEGMEN 1 (P.210m) Konsultan Perencanaan

DIPERIKSA OLEH :

DISETUJUI OLEH :

NO GAMBAR

SITE PLAN
CL

Agregat A T = 10cm
Beton K-250 T= 15cm (Ready Mix)
Plastik Cor
Provinsi BANTEN

Kabupaten SERANG

Kecamatan CARENANG

Tanah Asli Desa MEKARSARI

JENIS PRASARANA

350
POTONGAN MELINTANG JALAN

JUDUL GAMBAR

CL

DIBUAT OLEH :

Irfan Rizki Mu'tasim, ST


Beton K-250 T= 15cm (Ready Mix) Konsultan Perencanaan

DIPERIKSA OLEH :

DISETUJUI OLEH :

350
NO GAMBAR

DENAH PERKERASAN JALAN (SEGMEN 1)


CL

Agregat A T = 10cm
Beton K-250 T= 15cm (Ready Mix)
Plastik Cor
Provinsi BANTEN

Kabupaten SERANG

Kecamatan CARENANG

Tanah Asli Desa MEKARSARI

JENIS PRASARANA

250
POTONGAN MELINTANG JALAN

JUDUL GAMBAR

CL

DIBUAT OLEH :

Irfan Rizki Mu'tasim, ST


Beton K-250 T= 15cm (Ready Mix) Konsultan Perencanaan

DIPERIKSA OLEH :

DISETUJUI OLEH :

250
NO GAMBAR

DENAH PERKERASAN JALAN (SEGMEN 2)

You might also like