Scope of Works
This method statement is intended to outline the activities and the methods
used in cleaning and flushing of chilled water system and its chemical
treatment.
All activities will be carried out in accordance with the contract details and
in full compliance to the project specifications.
All work within the rights-of-way of the standards and specifications will
be done in compliance with requirements issued by authorities.
This flushing procedure for chilled water system covers all steps that
include:
1. Cleaning and flushing with fresh water
2. Flushing with cleaning chemical
3. Addition of Corrosion & Scale Inhibitor
4. Addition of Bio-side for biological control
Required Tools/Equipment
Tool box / Tool kit
Meters/gauges
Page 1|3
HVAC MOS
Power Tools
Temporary pump
Chemicals
Page 2|3
HVAC MOS
Run the pump and circulate the water (with chemicals added) for a
minimum period of 24 hours as per specialist supplier’s
recommendations.
Samples to be taken and tested in 3rd party laboratory. The water
quality must be achieved as per the requirements agreed in the
contract or as applicable
Specialist contractor shall collect samples and conduct tests until
satisfactory results are obtained as required which is a condition
when no increase in iron level is observed and a level of iron less
than 1ppm is achieved and the water is clear, colorless and odorless.
After the cleaning process is completed as described above the
cleaning solution shall be flushed out.
Step 3: Addition of Corrosion & Scale Inhibitors
The entire chilled water system is re-filled with fresh and clean
water and treated with corrosion and scale inhibiting treatment
chemical at the rate of 3Kg per cubic meter of the system volume or
as applicable depending upon the chemical concentration.
After 24 hours of circulation samples are taken to ensure the
concentration levels i.e. 800-100 ppm as NaNo2
Step 4: Biological Control – Chemical Treatment
Biological control chemical, shall be dosed at the agreed rate per
cubic meter using the manual dosing pot.
This is a shock dosing which shall be done after every three months.
Inspection
The inspection request shall be raised for consultant to witness the
flushing and cleaning process at different stages and results shall be
noted on checklists.
Chemical test reports shall be provided with all other
documentations.