Name of Project: Addis Ababa Transport sector headquarter project

Name of Client: Addis Ababa City Administration Mega Project Construction Office
Name Contractor: Zhongyang construction Group
Name of Consultant: Ethiopian Construction Design and Supervision Works Corporation-BUDSWS
Weekly Action Plan፡ Breakdown of 60 days’ physical & Financial Plan

ለ 60 ቀናት የታቀዱ ዋና ዋና ተግባራት (ከ 10/06/2015 ዓ.ም እስከ 09/08/2015 ዓ.ም.)

60-day special plan (የካቲት 09 --- ሚያዝያ 09/2015)


60 ሚያዝያ (Financial
Goals Day Afte የካቲት (Financial Plan) መጋቢት (Financial Plan)
Bas Plan)
and e
targe r 60 W W1 W3 (%)
tasks t days W3 W4 Sum W1 W2 W3 4 Sum (%) W2
plan (%) (%) (%) Sum (%)
(%) (%) (%) (%) (% (%) (%)
)
Go 61. 0.62 0.87 0.62 0. 0.63 0.88 0.63%
al 19 % % % 87 % %
የትራንስፖር 2.97%
Rev
ት ቢሮ 67.6 0.7 %
የተቋማት
ised 6.43
2
0.53
8
1.31 2.14
sch
ህንፃ ግንባታ
edu
le

የፕሮጀክት ስም ምርመራ
በቀጣይ 60 ቀናት የታቀዱ ዋና ዋና ስራዎች (List of activities)

የትራንስፖርት ቢሮ የብሎክ ስም
የተቋማት ህንፃ ግንባታ
11th floor
Formwork

Page 1 of 4
Reinforcement Bar
Concrete Work
Finishing Work
Sanitary
Electrical
Mechanical
12th floor
Formwork
Reinforcement Bar
Concrete Work
Finishing Work
Sanitary
Electrical
Mechanical
13th floor
Formwork
Reinforcement Bar
Concrete Work
Finishing Work
Sanitary
Electrical
Mechanical
14th floor
Formwork
Reinforcement Bar
Concrete Work
Finishing Work
Sanitary
Electrical
Mechanical
15th floor
Formwork
Reinforcement Bar
Concrete Work
Finishing Work
Sanitary
Electrical
Mechanical

Page 2 of 4
በ 60 ቀን ዕቅድ አፈፃፀም ሂደት ሊያጋጥሙ የሚችሉ ዋና ዋና ተግዳሮቶች እና ታሳቢ የተደረጉ የእርምት እርምጃዎች
ሊያጋጥሙ የሚችሉ ዋና ዋና ተግዳሮቶች
የፕሮጀክት ስም የታሰበ የእርምት እርምጃ
(ከ 10/06/2015 ዓ.ም እስከ 09/08/2015 ዓ.ም)

Page 3 of 4
ስራዎችን በትይዩ ኣለማስኬድ ስራ ተቋራጩ ስራዎችን በትይዩ መጀመር የሚችልበትን መንገድ ማስቀመጥ
የሲሚንቶ እጥረት ከሲሚንቶ ፋብሪካዎች ጋር በመነጋገር መፍቴ መስጠት
የትራንስፖርት ቢሮ የለዉጥ ስራዎች መኖር ለለዉጥ ስራዎች ዲዛይን ማሻሻያ በአፋጣይ ምላሽ መስጠት
የተቋማት ህንፃ ግንባታ ክላርፍኬሽን ላይ በአማከሪ በኩል በጊዜ ምላሽ አለመስጠት

Page 4 of 4