Professional Documents
Culture Documents
Lan VFM VFM 2020 21 1692899168
Lan VFM VFM 2020 21 1692899168
MAY 2023
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
TABLE OF CONTENTS
INTRODUCTION ...........................................................................................12
Background ........................................................................................................12
Audit Objectives ................................................................................................. 12
Audit Scope ........................................................................................................13
Selection of Projects ........................................................................................... 13
i
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
3.3 Project Title: Stone pitching along Busambaga Road Phase 2 .............................. 59
3.3.1 Project details ................................................................................................ 59
3.3.2 Scope of works ...............................................................................................59
3.3.3 Status of works at the time of audit ................................................................. 59
3.3.4 Assessment of Economy .................................................................................. 60
3.3.5 Assessment of Efficiency ................................................................................. 61
3.3.6 Assessment of Effectiveness ............................................................................ 67
3.4 Project Title: Chain Link fencing of Namate Playground .......................................70
3.4.1 Project details ................................................................................................ 70
3.4.2 Scope of works ...............................................................................................70
3.4.3 Status of chain link works at the time of audit ...................................................71
3.4.4 Assessment of Economy .................................................................................. 71
3.4.5 Assessment of Efficiency ................................................................................. 72
3.4.6 Assessment of Effectiveness ............................................................................ 77
3.5 Project Title: Renovations of Toilets at Kiwafu P/S ..............................................80
3.5.1 Project details ................................................................................................ 80
3.5.2 Scope of works ...............................................................................................80
3.5.3 Status of works at the time of audit ................................................................. 80
3.5.4 Assessment of Economy .................................................................................. 81
3.5.5 Assessment of Efficiency ................................................................................. 82
3.5.6 Assessment of Effectiveness ............................................................................ 86
ii
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
ACRONYMS
Acronym Meaning
BoQs Bills of Quantities
CBR California Bearing Ratio
Ch. Chainage
CML Central Materials Laboratory
CRR Crushed Rock
DBST Double Bituminous Surface Treatment
DCP Dynamic Cone Penetrometer
DDEG Discretional Development Equalization Grant
DLP Defects Liability Period
DSD Double Surface Dressing
ESIA Environmental and Social Impact Assessment
FY Financial year
GCC General Conditions of Contract
GoU Government of Uganda
HRS Hours
IDA International Development Bank
IPCs Interim Payment Certificates
KM Kilometer
LGs Local Governments
MDD Maximum Dry Density
ME Municipal Engineer
MLHUD Ministry of Lands, Housing and Urban Development
mm Millimeter
OAG Office of the Auditor General
OHS Operational Safety and Health
PAC Public Accounts Committee
PDU Procurement and Disposal Unit
PST Project Support Team
SC Supervising Consultant
SCC Special Conditions of Contract
SFG School Facilitation Grant
TDG Transitional Development Grant
ToRs Terms of Reference
UGX Uganda Shillings
URF Uganda Road fund
URF Uganda Road Fund
USD US Dollars
Uganda Support to Municipal Infrastructure Development - Additional
USMID – AF
Funding
VAT Value Added Tax
VFM Value for Money
VIP Ventilated Improved Pit Latrine
WB World Bank
iii
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
EXECUTIVE SUMMARY
Government of Uganda represented by Ministry of Lands, Housing and Urban Development
(MLHUD) secured an additional financing facility of USD 360 million from the International
Development Association (IDA/World Bank) to finance Uganda Support to Municipal
Infrastructure Development-Additional Financing (USMID-AF) Program in the
Municipalities/Cities. The Municipalities/Cities are Arua, Gulu, Lira, Soroti, Moroto, Tororo,
Mbale, Jinja, Kabale, Fort Portal, Hoima, Entebbe, Masaka, Kitgum, Mubende, Kasese, Kamuli,
Lugazi, Mbarara, Apac, Busia and Ntungamo.
One of the conditions of effectiveness of the program was for the government to have in
place complete annual performance assessment. The Ministry of Lands, Housing and Urban
Development (MLHUD) requested the Auditor General to carry out a value for money
audit/assessment for USMID and non USMID infrastructure projects implemented in the
participating Municipalities/Cities in the financial year 2020/21.
The main objective of the audit was to undertake a Value for Money assessment of the
delivery of urban infrastructure undertaken by the Municipal Councils participating in the
Uganda Support to Municipal Infrastructure Development additional funding Program
(USMID-AF). The scope of the assessment covered all USMID funded infrastructure and a
selected number of non USMID financed infrastructure projects executed by the Municipality
in the Financial Year 2020/2021. The general approach was to audit one (1) USMID project
and five (5) non-USMID projects (2 URF projects and 3 SFG projects or vice versa) in the
financial year.
A participatory approach with the Ministry of Lands Housing and Urban Development
(MLHUD- USMID PST), Municipalities/Cities and World Bank was adopted. Project documents
including engineer’s estimates, designs, procurement files, works/material supply contracts,
progress reports, payment certificates, vouchers, quality control documents,
correspondences and minutes of management meetings were reviewed. Field inspections
were undertaken jointly with representatives of the respective Municipality/Cities for the
selected projects.
Performance was measured against a value for money assessment tool which was developed
and discussed with the stakeholders. In the assessment, the scoring tool considered
economy, efficiency and effectiveness with scores of 30%,35% and 35% respectively. The
scores for USMID and Non-USMID infrastructure projects were then combined by having
their scores weighted on a pro rata approach based on their cost. However, for
Municipalities/Cities with projects whose economy assessment was not applicable, separate
economy weights were computed to obtain the overall economy score.
For purposes of this assessment, six (6) infrastructure projects were supposed to be selected
and weights attached in relation to the project costs as shown in the table below. However,
the municipal council only implemented five (5) projects under the required funding
arrangements.
Audited Projects in FY 2020/2021
S/ Project Contract Weight Economy Fundin Method of
No amount (UGX) s (%) weights g execution
(%) Arrange
ment
1 Construction works for 13,440,379,271 91.81% 94.55% USMID Contracted
Rehabilitation to
Bitumen Standards of 6
Roads (2.954km)
1
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
The executive summary presents the results of the assessment and a summary of the
findings for each project in the Financial Year, conclusions, and recommendations for the city.
Chapter 1 presents the audit background, objectives, scope and project selection, Chapter 2
presents the approach and methodology used in the assessment and Chapter 3 presents the
detailed findings per project in the city.
During the comparison of the Engineer’s estimates and Contractor’s/ suppliers’ rates across
the Municipalities/Cities, five key items were assessed;
USMID funded projects; precast concrete class 30 barrier kerbs, bush clearing and
grubbing, CRR for road base, asphalt concrete for surfacing, white lines broken or
unbroken for road marking,
URF funded projects - (force account); 600mm diameter culverts, chippings, gravel,
cement and fuel.
2
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
For the DDEG projects and the URF contaxted projects, economy assessment was not
applicable.
The combined weighted economy score of 28.47 out of 30 implies that there were small
disparities in the engineer’s estimates, contractor’s/supplier’s rates and unit cost per square
meter of infrastructure for the assessed USMID and URF. The disparities can be attributed to
the absence of standardized guidelines for costing of civil works in the Municipalities. The
highest disparities for the Municipality are shown in the table below;
The following parameters were assessed; physical progress lag, presence of detailed
payment supporting documentation, payment above certified amounts, percentage of
overpayments, timeliness in payments, percentage of quality progress reports, presence of
site meeting minutes, percentage of approved supervising personnel on site, percentage of
approved equipment on site, presence of detailed certificate of completion and snag list,
presence of As-built drawings and maintenance manuals, presence of DLP
progress/monitoring reports and presence of Detailed Liability Certificate.
The efficiency assessment revealed that the assessment of physical progress lag based on
initial work program for the USMID project and one (01) of the URF funded project could not
be undertaken due to insufficient information. However, the two (02) DDEG funded projects
and the other URF funded project were completed within the programmed completion dates
thereby registering no physical progress lags.
Further, the USMID project was still within the initial contract duration and so assessment of
physical progress lag based on revised work program was not applicable and one of the URF
projects still did not have sufficient information to enable assessment of physical progress
lag based on revised work program.
It was noted that detailed payment supporting documents were availed for USMID funded
project and the two (02) URF funded projects. However, they were not availed for the two
(02) DDEG funded projects.
Audit also noted that save for one (01) URF project where some payment documentation
were missing and so audit could not conclusively assess payment above certified amount, all
the other projects had their payments consistent with the certified amounts.
3
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
An overpayment of UGX.3,982,990 was noted on one (01) of the URF funded projects while
for all the other projects, no overpayment was noted on the sampled items.
Audit also noted that save for one (01) DDEG funded project where all the payments were
made in time, the other DDEG funded project had some missing payment documentation
and so audit could not conclusively assess timeliness of their payments while for the USMID
and the two (02) URF funded projects, there were some delays noted in the payments.
The Municipality provided adequate and good quality project progress reports on the USMID
funded project and one of the DDEG funded project while for the two (02) URF funded
projects, some reports were availed but they were of poor quality and no report was availed
for the other DDEG funded project.
Further, it was observed that save for one (01) DDEG funded project where no site meeting
minutes were provided, all the other projects had site meeting minutes on file.
Adequate personnel were mobilized for all the projects. There was also evidence that
equipment was adequately mobilized on the USMID funded project and on one (01) of the
URF funded projects; however, for the other URF funded project and the two (02) DDEG
funded projects, there was no evidence that the required equipment was mobilized during
construction.
The weighted efficiency score of 22.89 out of 35 was mainly due to lack of information for
the audit team in assessment of some of the parameters like physical progress lag, payment
above certified amounts and timeliness in payments and also due to delays in payments and
absence of quality progress reports on most of the projects.
The effectiveness assessment revealed that for the USMID funded project 90% of the
expected material test results were availed while for the two (02) URF funded projects,
14.29% and 60% were availed and for the two (02) DDEG funded projects, no material test
results were availed.
On conformance of works to design drawings and physical specifications, all the checks
made on the USMID funded project and one of the DDEG funded projects conformed to the
physical specifications while for the two URF funded projects and the other DDEG funded
project, the drawings and specifications were not availed so the check was not carried out.
Furthermore, audit tests conducted on the USMID project, one of the URf project and one of
the DDEG project all passed while for the other URF and DDEG funded project s, audit tests
were not conducted.
Physical inspection of the works revealed no visible defects on the USMID and DDEG funded
projects while for the URF funded projects, minor defects were observed.
At the time of audit, the USMID funded project was on-going and so its functionality wasn’t
assessed. The URF and DDEG funded projects were functional and in use.
4
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
All the projects had the screening report and/or ESMP in place. The USMID and one of the
URF funded projects did not have evidence of fulfilment of environmental protection
measures while all the other projects had. For the fulfilment of social protection measures
save for one URF project, all the other projects had evidence of their fulfilment while for the
fulfilment of OSH measures, one URF funded project and one DDED funded project did not
have evidence of their fulfilment while the other project had.
The score of 27.80 out of 35 is mainly attributed to absence of material test results, non-
conformance of site works to physical specifications and the inadequacies in the
implementation of environmental, health, social and safety measures.
Effectiveness
The score on effectiveness was 28.52 out of 35
9 out of 10 expected material test results were on the file
(90% availability).
All the items checked conformed to the designs and
physical specifications.
All the audit tests conducted passed.
At the time of the audit, the major activity that was in
5
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
Efficiency
The score on efficiency is 12.00 out of 30
• Final report was dated 14th August 2021 but it did not
mention when the project was completed so the audit team
could not determine whether the works were completed
within the initial project duration.
• Payment supporting documents like Goods received notes
for gravel and aggregates, fuel receipts and field
attendance were attached to the payments.
• Payment for supplies of gravel was not consistent with
certified amounts and for some items like hire of equipment
and fuel, the payment vouchers were not availed so audit
could not determine whether the payments were consistent
with certified amounts.
• An overpayment of UGX.3,982,989.53 was noted which was
equivalent to 0.5% of the final project amount.
• Some payments were delayed by days ranging from 4 to
133 days while for some, the payment vouchers were not
availed and so audit could not assess their timeliness in
payment.
• Only two of the expected four monthly progress reports
were availed and they were of insufficient quality.
• Two (02) site meeting minutes dated 20th May 2020 and
24th November 2020 were on file.
• A works supervisor and a works manager were appointed
vide letters dated 13th July 2020.
• Review of documents showed that several equipment had
been hired and that they were adequate to accomplish the
project.
Effectiveness
The score on effectiveness was 18.00 out of 35
• Only one (01) of the expected seven (07) material test
results were on file (14.29% availability).
• Design drawings and physical specifications were not
6
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
Efficiency
The score on efficiency was 28.00 out of 35
• Works were completed wthin the original project duration
hence there was no physical progress lag.
• Detailed payment supporting documents were prepared
• The payments made to the contractor were consistent with
the amounts certified.
• No overpayment was noted.
• Payment for IPC No.2 was made timely but payment for IPC
No.1 was delayed by 32 days.
• Three (03) of the expected four (04) monthly progress
reports were availed and they were of insufficient quality
due to lack of key information such as: level of contractor’s
equipment mobilization, quality control, health, safety and
social-environmental issues.
• Site meeting minutes dated 18th May 2021 were availed.
• A contract manager was appointed vide letter dated 22nd
December 2020.
• No evidence of equipment of mobilization of equipment
during contsruction
• Substantial completion certificate stating completion date as
30th May 2021 was issued but no snag list was attached to
it.
• There were no conditions of contract specifying the
requirements of as-built drawings.
• There were no defects liability monitoring/inspection reports
on file.
Effectiveness
The score on effectiveness was 19.44 out of 35
• 3 of the expected 5 tests were present (60% availability).
• Design drawings and physical specifications were not
availed so the audit team could not determine conformance
of executed works to specifications.
• Audit tests were not carried out.
• Audit team observed failure at Ch. 0+855 LHS and
damaged works at 0+865.
• At the time of audit (15th June, 2022), the works had been
7
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
Efficiency
The score on efficiency was 32.67 out of 35
There was no physical progress lag as the project was
completed within the intended period.
Detailed payment supporting documents were not availed.
Payment of IPC No.1 was consistent with certified amounts.
No overpayment was noted.
Payment of IPC No.1 was made timely.
The two expected monthly progress reports were both
availed and the quality was good.
Two (2) site meetings minutes dated 14th April 2021 and 1st
December 2021 were on file.
A contract manager was duly appointed vide letter dated 1st
February 2021.
The contractor mobilized equipment/tools such as; tipper
lorry, spades and concrete mixer which were adequate to
deliver the project.
A substantial completion certificate stating the project
completion date as 30th April 2021 and accompanied with a
snag list was issued.
“As-built” drawings were not available on file.
There were DLP monitoring reports during the Defects
Liability Period.
A defects liability certificate showing the defects liability end
date as 1st November 2021was issued.
Effectiveness
The score on effectiveness was 32.00 out of 35
No material test results were on file.
The two (02) items checked both conformed to design
drawings and physical specifications.
All the audit tests conducted fulfilled the specification
requirements.
There were no visible defects observed on the infrastructure
at the time of audit.
At the time of audit, the works had been completed. and
the project works were observed to be in good shape and
serving their intended purpose.
The City Environmental Officer prepared an ESMP which
was approved by the Accounting Officer on 30th Sept,
2020.
There was evidence of fulfillment of environmental, social
and OSH measures.
5. Renovation of toilet at Economy
8
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
Kiwafu P.S - DDEG • This was a unique project and could not be compared with
the other selected projects since it had different items from
the selected ones. Economy assessment was therefore not
done and the scores obtained from efficiency and
effectiveness were converted to represent the score out of
100.
Efficiency
The score on efficiency was 23.33 out of 35
• There was no physical progress lag as the project was
completed within the intended period.
• Detailed payment supporting documents in form of detailed
measurement sheets were not available.
• Payments for both IPC No:1 and retention certificate were
consistent with certified amounts.
• No overpayment was noted.
• The conditions of contract were not availed so the audit
team could not tell the specified period of time within which
payments were to be effected. Audit could therefore not
assess the timeliness in payments.
• No progress report was on file.
• No site meeting minutes were on file.
• A contract manager was appointed vide letter dated 23rd
April 2021.
• Information that could be utilized to establish the
contractor’s level of equipment mobilization during
construction was not availed.
• There was no completion certificate on file.
• “As-built” drawings were not available.
• There were defects liability progress/monitoring reports.
• The Defects Liability Certificate stating the end of defects
liability period as 2nd Dec 2021 was prepared.
Effectiveness
The score on effectiveness was 27.05 out of 35
• No material test results were on file.
• The audit team did not carry out any checks on site works.
• The audit team did not carry out any tests since it was a
renovation without any structural elements and there was
also no material on site at the time of audit.
• The works had been completed at the time of audit and no
visible defects were observed on the works done under this
contract.
• At the time of audit (22nd June 2022), the works had been
completed and the facility was in use.
• There was evidence of fulfillment of environmental and
social protection measures.
• There was no information on file pertaining the fulfilment of
OSH measures.
9
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
RECOMMENDATIONS
To ensure proper documentation of project timelines and progress details, the Accounting
Officers should ensure that work programmes are prepared by contractors and approved
immediately after contract signing, commencement orders given out to contractors and at
practical completion of works, substantial completion certificates should be issued for all
contracted projects and detailed completion reports for the executed works prepared.
The Accounting Officer should always ensure that payment supporting documents are
provided for each item considered for payment.
The Accounting Officer should ensure that payment of contractor’s IPCs and Consultant’s
fee notes are made timely as per the terms in the signed contracts.
The Accounting Officer should ensure that all materials used for construction are tested
or certified by the responsible authorities to ensure conformance to quality requirements.
The Accounting Officer should ensure that all the required approvals are obtained to
ensure compliance to the environmental and social protection measures.
3. The Accounting Officer should put in place measures to ensure that works are always
executed and completed as per the planned timeline and where contractors fail to deliver
on time, liquidated damages should be charged.
4. The Accounting Officer should ensure that works are always measured during the
certification process, detailed measurement sheets prepared and attached to the
payment certificates for all contracted building or road projects. In addition, tally sheets
and goods received notes should always be prepared for materials supplied for force on
account projects.
10
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
6. The Accounting Officer should put in place measures to ensure that payments to
contractors and material suppliers are always made within the stipulated timelines.
7. For all projects, the Accounting Officer should ensure that the frequency and quality of
progress reports is improved. The reports should be prepared on a monthly basis and
should cover all project aspects including but not limited to physical and time progress,
quality control, financial details, personnel, equipment used, weather conditions and
summarised minutes of meetings.
8. The Accounting Officer should ensure that regular site meetings are conducted to assess
works progress and timely devise solutions to challenges and minutes of these meetings
should be prepared, signed and kept on file.
9. The Accounting Officer should put in place measures to ensure that in the course of
execution of works, contractors always adequately mobilize all the equipment as per the
contractual requirements.
10. The Accounting Officer should ensure that once projects reach substantial completion,
the works are inspected to check for any defects and a snag list developed that is issued
together with the certificate of substantial completion.
11. The Accounting Officer should ensure that as-built drawings or strip maps are prepared
and maintenance and operating manuals provided since they are vital during
maintenance of the respective projects.
12. The Accounting Officer should ensure that projects are inspected during the defects
liability period in order to update the snag lists on the rectified defects or any new
defects that may develop and then prepare a defects monitoring report.
13. The Accounting Officer should ensure that all materials used for construction are tested
or certified by the responsible authorities to ensure conformance to quality requirements.
This can be done by drawing up a quality assurance plan and ensuring that project
managers adhere to it.
14. The Accounting Officer should ensure that the identified defects are further investigated
and rectified as soon as possible. Performance of the different infrastructure should be
monitored even after expiry of the defects liability period to ensure early identification of
failure and remedial measures taken in time.
15. The Accounting Officer should put in place measures to ensure that all environmental,
social protection and occupational health and safety measures are fulfilled during the
execution of the works.
John F. S. Muwanga
AUDITOR GENERAL
11
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
CHAPTER ONE
INTRODUCTION
Article 163(3) of the 1995 Constitution of The Republic of Uganda requires the Auditor
General (AG) to conduct Financial and Value for Money (VFM) Audits in respect of any
project involving public funds.
This mandate is further amplified by Section 21 of the National Audit Act (NAA) 2008
which gives the Auditor General powers to conduct financial and value for money audits
for purposes of establishing economy, efficiency and effectiveness of any Ministry,
Department or Agency (MDA), Public Organization and any Local Government Council.
Section 40 of the National Audit Act, 2008, empowers the Auditor General to engage the
services of, or work in consultation with Professional or Technical Experts or Consultants
whether in the public service or not, to enhance the performance of the OAG.
Background
Government of Uganda (GoU) represented by Ministry of Lands, Housing and Urban
Development (MLHUD) is securing an additional financing facility of USD 360 million
from the International Development Association (IDA/World Bank) to finance Uganda
Support to Municipal Infrastructure Development-Additional Financing (USMID-AF)
Program.
During the second year of the program for financial year 2020/21 , the program
participating Municipalities were increased to twenty two municipal councils in Uganda
and the Municipalities/Cities are, Arua City, Gulu City, Kitgum Municipality , Lira City ,
Apac Municipality, Soroti City, Moroto Municipality, Mbale City, Tororo Municipality, Busia
Municipality, Kamuli Municipality, Jinja City, Lugazi Municipality, Entebbe City, Hoima
City, Mubende Municipality, Fortportal City, Kasese Municipality, Mbarara City, Ntungamo
Municipality, Kabale Municipality and Masaka City.
One of the conditions for effectiveness of the program is for government to have in
place a complete annual performance assessment report covering all the agreed linked
disbursement indicators. Accordingly, as part of this requirement, the Ministry of Lands,
Housing and Urban Development (MLHUD) has requested for a value for money
audit/assessment for USMID and non-USMID infrastructure projects which were
implemented in the financial year 2020/21 in the 22 Municipalities and Cities that
participated in the USMID-AF implementation during the FY2020/21. The VFM
assessment for the financial year 2020/2021 will generate comparable results across
participating Municipalities and Cities.
Audit Objectives
The main objective of the audit is to undertake a Value for Money assessment of the
delivery of urban infrastructure undertaken by the twenty-two (22) Municipal/city
Councils participating in the Uganda Support to Municipal Infrastructure Development
Additional Funding Program (USMID-AF).
12
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
Audit Scope
The audit focused on the USMID project and a sample of other non-USMID financed
projects undertaken in the FY 2020/2021.
Selection of Projects
Projects were selected from the infrastructure projects undertaken by the Municipality in
the financial year under review. Generally, for the Municipality, 1 USMID funded project
was selected in addition to Five (5) non-USMID projects where applicable. Selection of
the non-USMID projects was based on the following agreed criteria:
Under this criterion, five (05) projects were selected for audit and these comprised one
(1) USMID, two (2) URF, one (1) SFG and one (1) DDEG funded project.
The following table shows projects selected and their corresponding weights for Entebbe
Municipal Council in the Financial Year 2020/21.
13
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
14
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
CHAPTER TWO
AUDIT METHODOLOGY
The audit was carried out in accordance with the International Organization of
Supreme Audit Institutions (INTOSAI) Performance Auditing Standards and Value for
money (VFM) Auditing guidelines prescribed in the Office of the Auditor General (OAG)
VFM audit manual.
The standards require that the audit is planned in a manner which ensures that an
audit of high quality is carried out in an economic, efficient and effective way, and in
a timely manner.
The audit was based on a Value for Money (VFM) assessment tool that evaluated
economy, efficiency and effectiveness to ensure attainment of the specific audit
objectives. This tool was developed in consultation with USMID Program Support
Team and the World Bank.
Assessment of Economy
This related to an assessment of the unit cost of infrastructure and made
comparisons with similar quantity and quality of infrastructure implemented in other
Municipalities/Cities that fell within the same cluster.
To ensure realistic and comparable assessment of the unit cost per square meter for
road works, preliminary and general items, and earthworks were excluded; while for
buildings, only Preliminary and general items were excluded.
The documents reviewed for this assessment included but were not limited to;
Engineers’ estimates, works contracts, material supplies’ contracts, and force account
planning documentation.
Assessment of Efficiency
In the assessment of efficiency, the following was undertaken:
i. An assessment of the progress of works against time; this was assessed by
determining the physical progress lag as the difference between the planned physical
progress and actual physical progress as at the time of audit;
ii. An evaluation of the existence and effectiveness of internal controls for certification
and payment of executed works; this was assessed by checking for the availability of
detailed payment supporting documentation, comparison of certified amounts with
the amounts paid out, quantity verification through comparison of certified quantities
with measured quantities, assessing timeliness of payments by determining any
delays in the payment for executed works/services and materials supplied;
iii. A review of the contract supervision and monitoring arrangements; In undertaking
this review, an assessment was made on the number and quality of progress reports
prepared, availability of minutes of site meetings, comparison of approved
15
Value for Money Audit/Assessment of the Municipalities Participating in the Uganda Support to Municipal
Infrastructure Development Additional Funding (USMID AF) Program
supervising personnel with personnel involved in the supervision of the works and
comparison of approved equipment with equipment found on site.
iv. For completed projects, a review of the contract supervision and monitoring
arrangements during project closure was done; in undertaking this review, an
assessment was made of presence of detailed Completion Certificate/ Taking-Over
Certificate, the presence of as-built drawings and maintenance manuals, the number
and quality of DLP progress/ monitoring reports prepared and presence of the
Defects Liability Certificate.
The documents reviewed for this assessment included; civil works contracts,
consultancy/service contracts, Interim Payment Certificates, fee notes and payment
vouchers, measurement/calculation sheets, time sheets, work programs, progress
reports, minutes of site meetings, material delivery notes, material supplies’
contracts, EHSS progress reports, force account planning documentation,
Environment screen reports among others.
Field inspections and measurement of some of the executed works were undertaken
in the presence of a representative of the PDE, the contractor and Supervision
Consultants, and quantities of sampled works were measured and compared to
respective quantities certified for payment so as to assess the accuracy in valuation
of the works.
Assessment of Effectiveness
The assessment focused on the quality and usage of the infrastructural works
undertaken by the Municipalities. The following were undertaken:
i. An assessment of the quality of works under implementation; this was assessed by
checking for the percentage of material test results on file, comparing site works to
the design requirements, comparing audit material test results of sampled items to
specifications, and visually checking for the presence of any defects on the works;
ii. An assessment on the utilization of the infrastructure; this involved undertaking site
visits to assess the usage and functionality of the completed or partially completed
infrastructure;
iii. An assessment of the level of compliance with the Environmental and Social
Safeguards as well as the implementation of Health and Safety requirements on
active sites.
The documents reviewed for this assessment included; material test results, civil
works contracts, monthly progress reports, original design reports/drawings, design
review reports and drawings, Special specifications, Environment, Health and Social
Management reports, environment screening reports among others.
Additionally, field inspections were carried out at auxiliary sites such as quarry sites,
dump sites, borrow pits, contractor’s camp sites, site clinics etc. The visits intended
to assess the level of compliance of contractor’s to EHSS requirements.
16
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
17
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
To Review contract Presence of detailed certificate of completion At least 3/4 parameters present
Supervision and and snag list - Satisfactory, otherwise,
monitoring arrangements unsatisfactory.
during project Closure Presence of As-built drawings and
(Satisfactory, maintenance manual
unsatisfactory) Presence of DLP progress/monitoring reports
3 To assess the usage and To assess the quality of Percentage of Material test results on file (3 100% present – 3mks, 90% -
quality of the works under Marks) ≤100% - 2mks; 80% - ≤90% - 1mk,
infrastructural works implementation (19 Less than 80% - 0mk
undertaken by the Marks)
% conformance of site works to design 100% conformance – 5mks, <100%
Municipalities
drawings and physical specifications (5 - ≥80% - 3mks, <80% - ≥60% -
(effectiveness) Max
Marks) 1mk, Less than 60% - 0mk
points - 35
% conformance of audit test results to 100% conformance – 8mks, 99% -
specifications (8 Marks) ≥80% - 3mks, 79% - ≥60% - 1mk,
Less than 60% - 0mk
Presence of defects from visual observations No defects observed – 3mks; Minor
18
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
19
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
The total score for this parameter for the Municipality/City was the sum of the scores
obtained for all the 5 items selected.
In Municipalities/Cities where the engineer’s estimates for some items were not
applicable, these were not considered and a conversion factor was applied in the
respective cases.
2 Unit project item costs as Item 1, (2marks) 5 items that were common to all USMID & Non USMID Municipal/City works contracts
per signed Contracts. were selected. The unit cost of each of these items was obtained from the signed
Item 2, (2 marks)
(10 Marks) contracts.
Item 3, (2marks)
The lowest unit cost for a particular item across the Municipalities/Cities in the
Item 4, (2 marks) selected/chosen cluster was given the maximum score of 2. The scores (Si) of the
Item 5, (2 marks) other Municipalities/Cities in the selected cluster for that particular item were
computed using the formula; �� = ����/�, in which Fm is the lowest unit cost for a
particular item across the Municipalities/Cities in the selected cluster and F is the unit
cost of a particular item for the Municipality/ City under consideration.
Each of the items selected was assessed separately across the Municipalities/Cities in
the cluster. The highest unit cost was used in cases where the unit cost for a
particular item varies within the same contract.
The total score for this parameter for the Municipality/City was the sum of the scores
obtained for all the 5 items selected.
20
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
21
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
Clustering of Municipalities/Cities
Clustering of Municipalities/Cities was carried out following the geographical regions
of Uganda and four (4) clusters were made as shown in the Table below.
22
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
Weighting
Weighting of the projects was done to cater for financial risks associated with the
projects whilst giving consideration to infrastructure with a bigger monetary value.
Thus the weighting was done pro-rata to the costs of the infrastructure selected for
assessment, using the formula below;
Wx=Px/Σ (P1, 2.., N) where Wx is the weight for project x, Px is the project cost and N is
the number of projects selected.
23
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
CHAPTER THREE
Project details
The project details are presented in the following table.
Scope of Works
Works on this USMID project comprises rehabilitation to bitumen standard of 6 roads
totaling to 2.954 Km; i.e., Kampala Road (2.058km), Market Street (0.130km), Hill
Lane (0.141km), Lugard Avenue (0.123km), Apollo Square (0.115km), Auxiliary Road
(0.387), and Beautification of Kampala Road, Lighting of Mayor’s Gardens and
Erection of Signage Boards at Strategic points within the Municipality.
24
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
The revision in scope following the design review by the supervision consultant
involved the following:
The road length reduced by 0.264Km to a total of 2.690Km following deduction of
0.141Km Hill Lane and 0.123Km Lugard Avenue following the design review
changes;
Subbase: 150mm thick Natural Gravel G30 was proposed for all roads.
Kampala Road
(2.058km)
Entire road was at
Culverts installation
1) level; preparation of
sub grade materials
and trial sections were
in progress
25
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
Market Street
(0.130km)
2) Culvert installation had
just commenced on
market street
Assessment of Economy
The score for economy was 28.84 out of 30 as detailed below:
26
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
The score was 4.63 out of 5. The Engineer’s rates for two (02) items i.e. CRR for road
bed and white lines, broken or unbroken were higher than the lowest in the cluster.
27
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
The score was 9.76 out of 10. The contractor’s rates for CRR for road base were
higher than the lowest in the cluster.
28
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
The score was 14.45 out of 15.00 in comparison to the lowest cost per square meter
of the USMID funded project road works. The project’s unit cost per square meter
was 1.04 times the lowest in the cluster.
Management Response
We acknowledge the finding of the auditors. This is likely to have been caused by the
difference in geographical location that has an effect on the cost and source of
different materials such as asphalt.
Auditor’s Remark
The management response is noted but this could not have been caused by asphalt
concrete as it had thelowest rate in the cluster.
29
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Assessment of Efficiency
The score on efficiency was 23.33 out of 35 as detailed below.
Management Response
We acknowledge the findings of the auditors. This was caused by delays in design reviews. A no cost extension of time was granted up to 4th Dec 2022.
Relevant approvals for the subbase material was done and the contractor has improved the speed of execution. Current progress is at about 80%.
Auditor’s Remark
The management response is noted.
(ii) Assessment of physical progress lag basing
on revised work programme
At the time of audit (28th June 2022), the works N/A N/A N/A
were still within the original project duration and
so this parameter was not applicable.
(b) Assessment of the existence and Risk of effecting payment The Accounting Officer should
effectiveness of internal controls for that is not commensurate always ensure that payment
30
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the finding of the auditors but wish to clarify that contractor’s establishment on site is evidenced by level of mobilization for equipment
and materials and also the setting up of the camp site. This is discussed and inspected at every site meeting. Attached is a copy for your verification.
Auditor’s Remark
The required report was not availed for verification.
(ii) Payment above certified amounts
Payments made to the contractor and consultant were
N/A OK OK
consistent with the certified amounts as shown in the
table below:
Contractor’s Payments
S/No Type of payment Certified amount (UGX) Paid amount (UGX) Payment above certified amount Remarks
1 Advance Payment 2,688,075,854.00 2,688,075,854.00 None OK
2 IPC No:1 977,719,229.00 977,719,229.00 None OK
3 IPC No:2 1,126,014,192.00 1,126,014,192.00 None OK
31
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Consultant’s payments
S/No Type of payment Certified amount (UGX) Paid amount (UGX) Payment above certified Remarks
amount
1 Fee Note No:1 179,945,500.00 179,945,500.00 None OK
2 Fee Note No:2 284,831,298.00 284,831,298.00 None OK
3 Fee Note No:3 341,498,733.00 341,498,733.00 None OK
4 Fee Note No:4 387,550,153.00 387,550,153.00 None OK
5 Fee Note No:5 305,679,433.00 305,679,433.00 None OK
6 Fee Note No:6 119,428,978.00 119,428,978.00 None OK
(iii) Percentage of overpayments (as a result of
variance between audit values and certified
works) to the certified value of the works
The audit team undertook physical measurements of
N/A OK OK
the quantities of some of the constructed works and
these were compared with certified quantities and no
overpayment was obtained as shown in the table
below:
32
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Assessment of % of overpayment (as a result of variance between audit values and certified works) to the certified value of the
works (10 Marks)
Item checked Unit Planned Rate Payment Audit Diff. between Amount Remarks
quantity (UGX) quantity quantity Audit & paid over paid
600mm diameter m 2,631 400,000 1,910.55 2,339.00 quantities -428.45 0 More works done since last
concrete culverts certified quantities
900mm diameter m 1,431 580,000 751.83 933.00 -181.17 0 More works done since last
concrete culverts certified quantities
Total Overpayment: 0
Total Payment (Final Contract Amount): 15,859,647,540
% Overpayment: 0
33
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
34
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
35
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
S/No Description Equipment as per the Equipment (As per May Equipment (Observed on
Contract Progress Report) Site)
1. Bulldozer 1 1 0
2. Wheel loader 1 1 0
3. Excavator 1 1 1
4. Motor grader 1 1 1
5. Dump trucks 4 2 3
6. Concrete mixer 1 1 1
7. Concrete vibrators 1 1 1
8. Plate compactor 2 2 0
9. Vibro Roller 2 1 1
10. Pedestrian roller 2 2 1
11. Mobile laboratory 1 Not reported 1
12. Bloom truck 1 1 0
13. Water bowser 2 1 1
14. Generator 1 1 0
15. Pickup 3 4 1
(d) Other Findings related to project management
1. Insurances and Policies
The municipal council did not provide the documentation related to some of the insurance policies as shown in the table below. As such, the Auditor
could not ascertain the status/validity of such policies.
Description of
S/ Serial No. of policy/
insurance policy/NEMA Date of issue Issuer Expiry date Remarks
No license/Bank guarantee
license
1 Contractor’s All Risks Not provided Unknown Unknown Unknown Unknown
2 Motor Commercial 201/080/1/001809/2020/10 31st March 2022 CIC General Insurance (U) Ltd 17th December Valid
36
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors but note these documents were available though we could have missed handing them to the auditors. A
copy of the contractors all risk, plant and machinery and workers compensation availed for your further reference.
Auditor’s Remark
The contractor’s all risks and plant and machinery policies were not availed for verification.
2. Securities and Guarantees
The auditor noticed that the professional indemnity was not availed.
S/No Description Amount Date of issue Expiry date Issuing Bank Remarks
1. Advance payment guarantee 2,688,075,854 7th October 2021 31st October 2022 Stanbic Bank (U) Ltd GCC 60 & SCC
60.1
2. Performance security 1,075,230,342 23rd April 2021 31st July 2022 Stanbic Bank (U) Ltd GCC 61 & SCC
61.1
3. ES Performance Security 268,807,585 22nd April 2021 31st August 2023 Stanbic Bank (U) Ltd GCC 61 & SCC
61.1
4. Professional indemnity - - - - Not available
Management Response
We acknowledge the findings of the auditors but note these documents were available though we could have missed handing them to the auditors. Copy
of professional indemnity is attached for verification.
Auditor’s Remark
No evidence was of professional indemnity was availed.
37
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Assessment of Effectiveness
The score on effectiveness was 29.81 out of 35 as detailed below.
38
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
39
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
40
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors but note, these documents were available though we could have missed handing them to the auditors.
Approvals for the above availed Borrow pits by MCC Dump site.
Auditor’s Remark
There was no verifiable information in respect of borrow pits approval by Entebbe Municipal Council (EMC) and the provided evidence was instead
approval for stockpile yard and not dump site.
(ii) Evidence of fulfilment of social protection
Poor project Risk of social The Accounting Officer
measures
management deprivation should always ensure
There was no information availed to the Audit team on the engagement
that social protection
of the community regarding how the project was likely to affect them
measures are
socially and how the project management intends to mitigate the
undertaken during
negative aspects. Whereas, the Project Manager informed the Audit
project execution.
Team that the community was being engaged through public address
sensitization, there was no evidence to back up those assertions.
41
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
42
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
43
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
44
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
45
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
(a) Assessment of the price difference between similar quality and quantity of
works
(i) Comparison of unit project item costs as per Engineers estimates
A comparison of the engineer’s estimates of five (05) selected items for the URF
funded force on account projects was made against the lowest among the
Municipalities and the results of the assessment are presented in the table below:
The score was 3.71 out of 5. The Engineer’s estimate for 600mm diameter concrete
culverts and fuel were higher than the lowest in the cluster while the rate for cement
was not availed to the audit team.
Management Response
We acknowledge the findings of the auditors. The Engineer’s rates are derived from
the market survey done every financial year.
Auditor’s Remarks
The market survey report was not availed for verification.
46
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additio
The score was 8.67 out of 10. The supplier’s rate for 600mm diameter concrete
culverts, fuel and cement were higher than the lowest in the cluster.
Management Response
We acknowledge the findings of the auditors however It should be noted that this
were suppliers’ rates of which the Municipality had no control over; however these
were the lowest from the Best Evaluated Bidder and were with in the market range
of the area.
Auditor’s Remarks
The management response is noted.
The score was 9.67 out of 15.00. The project’s unit cost per square meter was 1.55
times the lowest in the cluster.
47
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the Auditors and on future projects quality reports will be prepared and filed on project management file.
Auditor’s Remarks
To be followed up.
(ii)Assessment of physical progress lag basing on Lack of adequate The Project Manager should
revised work programme and reliable project always ensure that relevant
There were no time extension approvals on file and as such information denies project documentation is prepared
Poor documentation
audit could not determine whether the works were stakeholders an and secured for proper project
completed on time. Therefore, physical progress lag bassed opportunity to make management and utilization by
on revisd work program could not be assessed. informed decisions various stakeholders
Management Response
We acknowledge the finding of the auditors and on future projects quality reports will be prepared and filled on project management file.
48
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
49
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
50
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Assessment of % of overpayment (as a result of variance between audit values and certified works) to the certified value of
the works (10 Marks)
Item checked Unit Planned Rate Payment Audit Diff. Amount Remarks
quantity (UGX) quantity quantity between over paid
audit &
paid
quantities
Gravel M3 2,430.00 33,900 2,430 2,414.26 15.74 533,586
Bitumen Kg 22,200.00 4,594.60 22,200 22,014.08 185.92 854,228.03
Chippings (14/20) Kg 260,000.00 150.00 240,000 235,826.45 4,173.55 626,032.50
Chippings (10/12) Kg 220,000.00 150.00 220,000 206,872.38 13,127.62 1,969,143.00
Total Overpayment: 3,982,989.53
Total Payment (Final Project Amount): 774,668,000.00
% Overpayment: 0.5
Management Response
We acknowledge the observations of the auditors. By the nature of surfacing works, normally extra materials are procured to take into account of
any eventualities such as wastes due to bitumen that remain both in the drums and the distributor besides chippings that remain at stockpile yard.
The discrepancy could have come from admeasurements for actual executed works. On future projects extra precaution shall be taken to further
minimize on the errors.
Auditor’s Remarks
To be followed up.
(ii) Timeliness in Payments Delayed payments negatively
Clause 49 (3) of PPDA regulations of 2014 requires affect the cash flows which may
payments to contractor/supplier to be made within negatively impact on project The Accounting Officer should
30 days of receipt of request for payment. Review of delivery. ensure that payment are made
the project payment documents indicated that some
timely as per the terms in the
payments were delayed by days ranging from 4 to
Could lead to interest claims signed contracts.
133 days while for some, the payment vouchers were
not availed and so audit could not assess their due to delayed payments
timeliness in payment as shown in the table below:
51
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the finding of the auditors. This was caused by non-availability of funds. Auditors recommendation noted and future projects
timely payments shall be made to contractors.
Auditor’s Remark
The management response is noted and will be followed up in future audits.
(c) Review of Contract Supervision and
Monitoring Arrangements The Accounting officer
(i) Percentage of quality progress reports should put measures to
Lack of information/ data
prepared ensure that quality
which limits stakeholders
Poor project management progress reports
Regulation 6(5) (b) of the PPDA (force account) from making informed
addressing all key project
regulations requires the works manager to prepare decisions.
aspects are always
monthly progress reports for the works. The project was prepared for all projects.
delivered over a period of about four (4) months implying
52
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors. We have standardized the reporting tool to ensure better reports.
Auditor’s Remark
To be followed up.
(ii) Presence of minutes of site meetings
It is a good project management pr.actice to hold regular
site meetings at least on a monthly basis to discuss issues
pertaining to execution and progress of the project.
N/A OK OK
Review of the project management file showed that two
(02) site meeting minutes dated 20th May 2020 and 24th
November 2020 were on file.
(iii) Percentage of approved supervising
personnel on site
Clause 5 and 6 of PPDA regulations of 2014 (force
account mechanisms) of 2014, mandates the Accounting N/A OK OK
Officer to appoint a Works Supervisor and a Works
Manager respectively to supervise the works. These were
appointed vide letters dated 13th July 2020.
(iv)Percentage of approved equipment on site
At the time of the audit, the works had been completed.
Review of documents showed that several equipmwnt had N/A OK OK
been hired and that the were adeqauate to accomplish
the project. The pictorial progress report availed also had
53
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
54
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors. For future projects material testing and manufacturers certification shall be captured at all levels.
Auditor’s Remark
To befollowed up.
(ii) Percentage conformance of site works to design The Accounting Officer should
drawings and physical specifications Risk of executing
always ensure that design
Design drawings and physical specifications were not substandard works owing
drawings and specifications are
availed so the audit team could not determine conformance Poor project management to lack of guiding design
available so that they are
of executed works to design drawings and physical drawings and physical
followed in execution of the
specifications. specifications
works.
55
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors. The drawings were taken by the Hon. Minister for Economic Development at one of his monitoring
exercise. We have managed to get a copy of the design drawings and this has been attached for your verification.
Auditor’s Remark
The management response is noted but no verifiable evidence concerning design drawings have been provided.
(iii) Percentage conformance of audit test results to
specifications
The audit team carried out tests on gravel utilized on the
N/A OK OK
project. All material properties fulfilled the specification
requirements thus translating into 100% conformance to
specifications.
Material Sample Test done Auditor Specification Comment Remarks
(S/N) resultsresults (N/mm2)
(N/mm2)
Gravel GOA/LC/ CBR (%) 41.00 30% Minimum Passed
M&B/G02 Liquid limit 36.70 45 Maximum Passed
Plasticity Index 14.60 16 Maximum Passed
Shrinkage 165.90 120 - 400 Passed
product
Linear Shrinkage 7.90 9 Maximum Passed
Grading modulus 2.35 1.2 Minimum Passed
(iv) Physical inspection to ascertain presence of
defects from visual observations
The audit team inspected works on 15th June, 2022 in the The Accounting Officer should
Risk of premature failure
presence of the Engineering staff from Entebbe Municipal ensure that the observed
of the road
Council Engineer’s Office. It was observed that the defects are rectified.
infrastructure had some minor defects as shown in the
table below:
56
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Edge break failure at Ch. 0+710 Stripping of surface dressing at Ch. 0+675
Management Response
We acknowledge the findings of the auditors. Wearing of edges and stripping of surface dressing is sometimes caused by silt from unpaved connecting
accesses that silt the road and facilitate growth of vegetation. In the process of removal sections are damaged. We have improved by spraying instead
of weeding/uprooting.
Auditor’s Remark
The management response is noted but there are no connecting roads at these chainages implyinh that there could have been a different cause of the
observed defects.
(b) Assessment of the utilization of the
The Accounting Officer should
infrastructure Reduced funstionality of
ensure that the observed
(i) Observed functionality and usage the road
defects are rectified.
At the time of audit, the works had been completed and
57
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors. We have improved our maintenance to ensure the functionality is improved.
Auditor’s Remark
The management response is noted.
(c) Assessment of the fulfilment of environmental
and social impact requirements, health and safety
(i) Presence of an ESIA/ESMF or environmental
screening report
At the time of audit, works had been completed. Review of N/A OK OK
the project management file indicated that the
Environmental Officer prepared an ESMP which was
approved by the Accounting Officer on 30th September
2019.
(ii) Evidence of fulfilment of environmental The Accounting Officer should
protection measures always ensure that
Risk of environmental
There was no record showing that environmental Poor project management environmental protection
deprivation
protection measures were implemented. measures are undertaken during
project execution.
(iii) Evidence of fulfilment of social protection The Accounting Officer should
measures always ensure that social
There was no record showing that social protection Poor project management Risk of social deprivation protection measures are
measures were implemented. undertaken during project
execution.
(iv) Evidence of fulfilment of OSH measures The Accounting Officer should
There was no record showing that OSH measures were Risk of injury to the always ensure that OSH
Poor project management
implemented. workers measures are undertaken during
project execution.
58
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal
Infrastructure Development - Additional Funding (USMID-AF) program
Status of the drainage channel along Busambaga road at the time of audit
59
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal
Infrastructure Development - Additional Funding (USMID-AF) program
60
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
61
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
S/No. Type of payment Certified amount (UGX) Paid amount (UGX) Payment above(UGX) Remarks
1 IPC No:1 148,795,373 148,795,373 None OK
2 IPC No:2 126,564,284 126,564,284 None OK
Assessment of % of overpayment (as a result of variance between audit values and certified works) to the certified value of the
works (10 Marks)
Item checked Unit Planned Rate Payment Audit Diff. between Amount Remarks
quantity (UGX) quantity quantity audit & paid over paid
quantities
Lined stone M2 3,570 48,000 3,360 3,359 1 0
pitching
Total Overpayment: 0
Total Payment (Final Contract Amount): 289,127,639.85
% Overpayment: 0.0
62
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
S/No. Type of payment Certified Expected latest payment date Payment Delays in Remarks
date date payments
1 IPC No: 1 25th Feb 2021 27th March 2021 28th April 2021 32days Delayed by 32days
2 IPC No: 2 7th June 2021 7th July 2021 23rd June 2021 - OK
Management Response
We acknowledge the findings of the auditors. The delay for payment of IPC: 1 was because of lack of funds.
Auditor’s Remark
The management response is noted.
(c) Review of Contract Supervision and Poor project Lack of information/ data The Accounting officer should
Monitoring Arrangements management which limits stakeholders from put measures to ensure that
(i) Percentage of quality progress reports making informed decisions. quality progress reports
PPDA regulations of 2014, clause 53(3) (g) requires the addressing all key project
contract manager to prepare monthly progress reports. aspects are always prepared
The project was executed over a period of 160 days for all projects.
implying that at least four (4) monthly progress reports
were expected.
Reports for January 2021, March 2021 and May 2021 were
available but were of poor quality due to lack of key
information such as: level of contractor’s equipment
63
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Responses
We acknowledge the findings of the auditors. Our reports lacked some key project information, we have since standardized the report form.
Auditor’s Remark
To be followed up.
(ii) Presence of minutes of site meetings
It is a good project management practice to hold regular
site meetings at least on a monthly basis to discuss issues
pertaining to project execution and progress.
N/A OK OK
Review of the project documents indicated that only one
(1) site meeting for the month of May 2021 was held as
evidenced by presence of site meeting records dated 18th
May 2021.
(iii) Percentage of approved supervising
personnel on site
Clause 52 of PPDA regulations of 2014 requires the
Accounting Officer to appoint a Contract Manager to
N/A OK OK
manage the contract. Upon reviewing the project
management records, the Auditor observed that a Contract
Manager was appointed vide letter dated 22nd December
2020.
(iv) Percentage of approved equipment on site The Accounting officer should
At the time of audit, the project had been completed. Lack of information/ data which put measures to ensure that
Review of the project management records showed that limits stakeholders from quality progress reports
Poor project
there was no information that could be utilized to establish making informed decisions. addressing all key project
management
the contractor’s level of equipment mobilization during aspects like equipment
construction. mobilization are always
prepared for all projects.
64
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors. Auditors recommendation noted, completion certificates will always be issued indicating the status of
defects at substantial completion.
Auditor’s Remark
To be followed up.
(i) Presence of As-built drawings and Lack of as-built drawings may
The Accounting Officer should
maintenance manuals Poor project ensure that As-built drawings
hinder economic and effective
There was no conditions of contract specifying the formulation are always prepared and duly
future maintenance
requirements of as-built drawings. approved at every project
interventions.
completion.
Management Response
We acknowledge the findings of the auditors. Auditors recommendation noted, As-built drawings will always be prepared and duly approved on future
projects.
Auditor’s Remark
To be followed up.
(ii) Percentage of DLP progress/monitoring reports The Accounting Officer should
There may be a missed
There were no defects liability monitoring/inspection Poor project ensure that DLP inspections
opportunity of identifying
reports on file. management at project are conducted, snag lists
developing defects and
closure stage updated, and reports made on
rectifying them.
its future projects.
Management Response
65
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Auditor’s Remark
The provided evidence is a snag list at substantial completion but DLP progress/monitoring reports are prepared thorough out the defects liability period
to inform possible development of defects during the DLP.
(ii) Presence of defects liability certificate
A defects liability certificate dated 3rd December 2021
stating end of defects liability period as 30th November N/A OK OK
2021 was duly issued.
66
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
(a) Assessment of the quality of works under implementation The Accounting Officer should
It poses a risk of use of ensure that materials to be
(i) Percentage of material test results on file
Poor project materials that do not used in the permanent works
Review of the project management file showed that three (03) of the
management conform to the are tested to avoid using
expected five (05) tests were present representing 60.00% availability
specifications. materials that do not meet
as indicated in the table below:
specification.
S/No Tests Expected Tests results on file
1 Sand tests Absent
Tests on mortar Absent
Culvert tests (manufacturer's certificate) Present
Cement (manufacturer's certificate) Present
Reinforcements (manufacturer's certificate) Present
Management Response
We acknowledge the findings of the auditors but wish to note that the drawings were taken by Hon Minister for Economic monitoring , we have
however managed to retrieve a copy is attached for your verification.
67
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors. Rectification of defects Planned for this financial year.
68
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
69
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal
Infrastructure Development - Additional Funding (USMID-AF) program
70
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal
Infrastructure Development - Additional Funding (USMID-AF) program
Status of the chain link at Namate play ground at the time of Audit
71
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding
(USMID-AF) program
72
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding
(USMID-AF) program
Assessment of % of overpayment (as a result of variance between audit values and certified works) to the certified
value of the works (10 Marks)
Planne Paymen
Uni d Rate t Audit Diff. between audit Amount
Item checked Remarks
t quantit (UGX) quantit quantity & paid quantities over paid
y y
28,000.
Length of chain link M 570.00 570.00 571.30 1.30 0
00
Number of fence No. 330.00 55,000. 330.00 330.00 0.00 0.00
73
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding
(USMID-AF) program
74
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding
(USMID-AF) program
75
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding
(USMID-AF) program
Management Response
We acknowledge the findings of the auditors. Auditors’ recommendation noted, As-built drawings will always be prepared and duly
approved on future projects.
Auditor’s Remark
The management response noted and will be followed up in future audits.
(iii) Percentage of DLP progress/monitoring reports
Document review showed that there were DLP monitoring reports N/A OK OK
during the Defects Liability Period.
(iv) Presence of defects liability certificate
On reviewing the project management file, the audit team
N/A OK OK
established that a defects liability certificate was issued and it
showed the defects liability end date as 1st November 2021.
76
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding
(USMID-AF) program
Management Response
We acknowledge the findings of the auditors. Auditors recommendation noted on future projects tests will be carried out on all materials.
Auditor’s Remark
The management response is noted and will be followed up in future audits.
(i) Conformance of site works to design
drawings and physical specifications
Some works items were checked by the audit team to
ascertain conformance to design drawings and
N/A OK OK
physical specifications. It was observed that the two
(02) items checked both conformed to design
drawings and physical pecifications 100% as indicated
in the table below:
S/n Item Description Drawings/ Field checks/measurements Deviation Conformity
Specifications
1 Concrete pole (Height in 2.7 2.7 - OK
m)
2 Galvanized chain link G-10 G-10 - OK
gauge
77
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding
(USMID-AF) program
78
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding
(USMID-AF) program
79
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Developm
(USMID-AF) program
80
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Developm
(USMID-AF) program
81
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
It also showed that the original project duration was 1.5 months
implying that the initial intended completion date was 26th June 2021.
Therefore, the project was completed within the initial completion
duration and so there was no physical progress lag.
(ii) Assessment of physical progress lag basing on revised
work Programme N/A OK OK
The project was completed within the initial completion period.
(a) Assessment of the existence and effectiveness of
The Accounting Officer
internal controls for certification and payment of executed
should ensure that all
works
necessary
(i) Presence of detailed payment supporting documentation
Poor project Payments may be made for documentation to show
Clause 17(4) of the PPDA (contracts) regulations 2014 requires that
management. unexecuted works. proof of works done is
the actual work done is measured during the performance of a
attached to certificates
contract and is finally reconciled on effecting payments. The auditor
being effecting
noted that detailed payment supporting documents like measurement
payments.
sheets were not availed to the audit team.
(ii) Payment above certified amounts
Audit review of the available payment documents revealed that
N/A OK OK
payments for both IPC No:1 and retention certificate were consistent
with certified amounts as shown in the table below:
82
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
(v) Review of Contract Supervision and Monitoring Poor project Lack of information/ data The Accounting officer
Arrangements management which limits stakeholders should put measures to
83
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Responses
We acknowledge the findings of the auditors. Progress reports were prepared and a copy has been attached for your verification.
Auditor’s Remark
No progress report was availed for verification.
(ii) Presence of minutes of site meetings
It is good project management practice to hold regular site meetings The Accounting Officer
at least on a monthly basis to discuss issues pertaining to project should ensure that site
Poor project
execution and progress. Project bottlenecks cannot meeting are held
management and
be discussed in time. regularly and their
administration.
However, review of the project management file indicated that no respective minutes
site meeting records were available thus no site meetings held. should be prepared.
84
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors but do clarify that In the progress report for the month of June 2021, under equipments, it is indicated
that there was a compressor and cutter at site. annex 22(b).
Auditor’s Remark
The management response is noted but no verifiable evidence [annex 22(b)] of a progress report copy as stated above was provided.
(vi) Review of Contract Supervision and Monitoring The Accounting Officer
Arrangements during project closure should inspect works at
(i) Presence of detailed certificate of completion Poor project Rectification of snags may completion and identify
There was no completion certificate on file. management. not be done effectively. any defects then issue
the completion
certificate.
Management Response
We acknowledge the findings of the auditors but clarify that a completion certificate for the works was prepared and a copy has been attached for your
verification annex 23.
Auditor’s Remark
The management response is noted but no verifiable evidence of a substantial certificate of completion copy [annex 23] as stated above was provided.
(ii) Presence of As-built drawings and maintenance manuals The Accounting Officer
There were no As-built drawings on file. Lack of as-built drawings should ensure that As-
Poor project
may hinder economic and built drawings are
management
effective future always prepared and
maintenance interventions. duly approved at every
project completion.
(iii) Percentage of DLP progress / monitoring reports
Document review showed that there were DLP monitoring reports N/A OK OK
during the Defects Liability Period.
(iv) Presence of defects liability certificate
The Defects Liability Certificate stating the end of defects liability N/A OK OK
period as 2nd Dec 2021 was prepared and accordingly issued.
85
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors. Auditors recommendation noted ,materials tests will be carried out on future projects.
Auditor’s Remark
The management response noted and will be followed up in future audits.
(ii) Percentage conformance of site works to design
drawings and physical specifications N/A OK OK
The audit team did not carry out any checks on site works.
(iii) Percentage conformance of audit test results to
specifications
The audit team did not carry out any tests since it was a N/A N/A N/A
renovation without any structural elements and there was also
no material on site at the time of audit.
(iv) Physical inspection to ascertain presence of defects
The auditors inspected the works on 22nd July 2022 in the
presence of the Engineering Staff from Municipal Engineer’s
N/A OK OK
Office Entebbe. The works had been completed at the time of
audit and no visible defects were observed on the works done
under this contract.
(d) Assessment of the utilization of the infrastructure
N/A OK OK
(vii) Observed functionality and usage
86
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
Management Response
We acknowledge the findings of the auditors however during execution of works safety gears and safe site conditions were observed. Auditors
recommendation noted and on future projects more OSH measures will be put in place.
Auditor’s Remark
The management response noted and will be followed up in future audits.
87
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
88
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
approved work Physical progress lag Physical lag ≤ 5% - N/A 0 N/A N/A N/A
programs and – (difference between 5mks; >5% - ≤ 10% -
outputs the planned as 4mks; >10% - ≤ 20% -
(Efficiency) derived from the 3mks; >20% - ≤ 25% -
Max points - current approved 2mks; >25% - ≤ 30% -
35 revised work program 1mk; above 30% - 0mks
and actual physical
progress) (5 Marks)
To assess the Presence of detailed Detailed measurement 0 2 2 0 0
existence and payment supporting sheets present – 2mks;
effectiveness of documentation e.g. Absent – 0mks
internal controls measurement sheets
for certification (2 Marks)
and payment of Payment above No payment above 3 0 3 3 3
executed works certified amounts certified amount –
(18 Marks) (IPCs, fee notes, 3mks; Any payment
material supply above certified amount -
invoices etc.) (3 0mks
Marks)
% of overpayment 0% overpayment - 10 5 10 10 10
(as a result of 10mks; 1% - ≤5% -
variance between 5mks; 6 - ≤10% -
audit values and 2mks; above 10% -
certified works) to the 0mks
certified value of the
works (10 Marks)
Timeliness in payment Payment within 0 0 0 3 0
of IPCs, fee notes, contractual provision –
material supply 3mks; Otherwise – 0mks
invoices etc. (3
Marks)
89
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
90
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
91
Value for Money Audit/assessment of the Municipalities participating in the Uganda Support to Municipal Infrastructure Development - Additional Funding (USMID-AF) program
marks) mks
92