PARTIDAS EJECUTADAS CON MENOR

PRESUPUESTO DE OBRA
ITEM DESCRIPCION METRADO APROBADOS POR LA ENTIDAD

UND METRADO P.U TOTAL METRADO MONTO S/ %


01 TRABAJOS PRELIMINARES
01.02 CAMPAMENTO glb 1.00 101,800.00 S/ 101,800.00 1.00 S/ 101,698.20 99.90%
01.03 MOVILIZACIÒN Y DESMOVILIZACIÒN DE EQUIPO glb 1.00 122,358.72 S/ 122,358.72 1.00 S/ 122,236.37 99.90%
01.07 MEJORAMIENTO ACCESOS A D.M.E. Y CAMPAMENTO km 0.40 34,318.31 S/ 13,727.32 0.40 S/ 13,658.69 99.50%
01.09 APERTURA DE DME Y CAMPAMENTO glb 1.00 125,271.22 S/ 125,271.22 1.00 S/ 125,020.67 99.80%
01.10 FLETE DE MATERIALES A OBRA glb 1.00 400,069.14 S/ 400,069.14 1.00 S/ 397,186.69 99.28%
03.04 CONFORMACION DE TERRAPLENES m³ 34,964.73 32.15 S/ 1,124,116.07 32,464.68 S/ 1,043,739.46 92.85%
04 SUB BASES Y BASES
04.02 BASE GRANULAR DE 0.15 M m² 102,467.63 21.57 S/ 2,210,226.78 100,987.63 S/ 2,178,303.20 98.56%
05 PAVIMENTO ASFALTICO
05.01 IMPRIMACION ASFALTICA m² 98,189.24 10.03 S/ 984,838.08 96,773.24 S/ 970,635.60 98.56%
05.02 TRATAMIENTO SUPERFICIAL BICAPA (TSB) m² 97,119.64 19.57 S/ 1,900,631.35 - S/ - 0.00%
05.03 RIEGO DE LIGA m² 97,119.64 5.69 S/ 552,610.75 95,719.64 S/ 544,644.75 98.56%
06 DRENAJE
06.01 ALCANTARILLAS MCA
06.01.02 TRAZO/NIVELES Y REPLANTEO m² 1,160.64 6.00 S/ 6,963.84 1,018.57 S/ 6,111.41 87.76%
06.01.03 DESVIO PROVISIONAL DE CURSOS DE AGUA m 1,142.40 26.38 S/ 30,136.51 1,003.58 S/ 26,474.43 87.85%
06.01.05 EXCAVACION PARA ESTRUCTURAS C/MAQUINARIA m³ 2,218.00 9.41 S/ 20,871.38 2,019.72 S/ 19,005.59 91.06%
06.01.06 ENCOFRADO Y DESENCOFRADO CUERPO m² 1,950.00 52.64 S/ 102,648.00 1,807.43 S/ 95,143.12 92.69%
06.01.07 ENCOFRADO Y DESENCOFRADO CABEZALES m² 755.28 51.52 S/ 38,912.03 675.76 S/ 34,815.16 89.47%
06.01.09 CONCRETO F'C = 1000 KG/CM2 PARA SOLADOS m² 523.36 38.78 S/ 20,295.90 439.58 S/ 17,046.92 83.99%
06.01.10 CONCRETO F'C = 210 KG/CM2 m³ 570.22 574.51 S/ 327,597.09 513.42 S/ 294,965.09 90.04%
06.01.11 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m³ 1,363.80 38.09 S/ 51,947.14 1,260.72 S/ 48,020.80 92.44%
06.02 ALCANTARILLAS TMC
06.02.01 DESBROCE Y LIMPIEZA MANUAL m² 2,762.10 2.90 S/ 8,010.09 2,479.60 S/ 7,190.84 89.77%
06.02.02 TRAZO NIVELES Y REPLANTEO m² 2,762.10 6.00 S/ 16,572.60 2,479.60 S/ 14,877.60 89.77%
06.02.03 DESVIO PROVISIONAL DE CURSOS DE AGUA m 392.08 26.38 S/ 10,343.07 364.15 S/ 9,606.28 92.88%
06.02.04 DEMOLICION DE ALCANTARILLAS DE TMC L=9.00 m und 25.00 824.79 S/ 20,619.75 23.00 S/ 18,970.17 92.00%
06.02.06 EXCAVACION PARA ESTRUCTURAS C/MAQUINARIA m³ 1,566.48 9.41 S/ 14,740.58 1,536.31 S/ 14,456.71 98.07%
06.02.07 TUBERIA CORRUGADA DE ACERO GALVANIZADO CIRCULAR DE 36''
m 189.59 784.57 S/ 148,746.63 136.08 S/ 106,764.29 71.78%
DE DIAMETRO
06.02.10 ENCOFRADO Y DESENCOFRADO CABEZALES m² 1,179.60 51.52 S/ 60,772.99 1,039.25 S/ 53,542.16 88.10%
06.02.11 ACERO DE REFUERZO F'Y = 4200 KG/CM2 kg 9,322.83 7.76 S/ 72,345.16 9,107.46 S/ 70,673.89 97.69%
PARTIDAS EJECUTADAS CON MENOR
PRESUPUESTO DE OBRA
ITEM DESCRIPCION METRADO APROBADOS POR LA ENTIDAD

UND METRADO P.U TOTAL METRADO MONTO S/ %


06.02.12 CAMA DE GRAVA ARENOSA m³ 63.14 196.80 S/ 12,425.95 60.95 S/ 11,995.31 96.53%
06.02.13 CONCRETO F'C = 1000 KG/CM2 PARA SOLADOS m² 294.96 38.78 S/ 11,438.55 262.97 S/ 10,197.94 89.15%
06.02.14 CONCRETO F'C = 175 KG/CM2 CABEZALES m³ 175.28 472.31 S/ 82,786.50 163.16 S/ 77,063.54 93.09%
06.02.15 RELLENO CON MATERIAL PROPIO PARA ESTRUCTURAS m³ 741.11 38.09 S/ 28,228.88 728.06 S/ 27,731.69 98.24%
06.02.16 MAMPOSTERIA CON PIEDRA EMBOQUILLADA F'C = 175 KG/CM2 +
m³ 310.05 289.48 S/ 89,753.27 293.26 S/ 84,892.90 94.58%
60%PM
06.02.17 LIMPIEZA Y CONFORMACION DE CAUCE m 765.60 50.11 S/ 38,364.22 633.46 S/ 31,742.56 82.74%
06.03 CUNETAS
06.03.01 TRAZO DE NIVELES Y REPLANTEO m² 22,930.24 6.00 S/ 137,581.44 13,609.41 S/ 81,656.46 59.35%
06.03.02 EXCAVACION MANUAL EN OBRAS DE ARTE m³ 2,150.70 47.46 S/ 102,072.22 1,302.29 S/ 61,806.68 60.55%
06.03.03 ENCOFRADO Y DESENCOFRADO m² 711.63 40.46 S/ 28,792.55 429.87 S/ 17,392.54 60.41%
06.03.04 CONCRETO F'C = 140 KG/CM2 m³ 2,150.70 465.55 S/ 1,001,258.39 1,308.05 S/ 608,962.68 60.82%
06.03.05 JUNTA ASFALTICA m 9,614.89 7.93 S/ 76,246.08 5,857.53 S/ 46,450.21 60.92%
06.04 BADENES
06.04.01 TRAZO NIVELES Y REPLANTEO m² 120.00 6.00 S/ 720.00 112.00 S/ 672.00 93.33%
06.04.03 EXCAVACION PARA ESTRUCTURAS C/MAQUINARIA m³ 52.89 9.41 S/ 497.69 48.63 S/ 457.61 91.95%
06.04.04 CONCRETO F'C = 100 KG/CM2 PARA SOLADOS m² 108.64 38.78 S/ 4,213.06 87.04 S/ 3,375.41 80.12%
06.04.05 ENCOFRADO Y DESENCOFRADO m² 60.30 44.43 S/ 2,679.13 56.30 S/ 2,501.41 93.37%
06.04.06 CONCRETO F'C = 210 KG/CM2 m³ 37.98 534.39 S/ 20,296.13 36.06 S/ 19,270.10 94.94%
06.04.09 JUNTA DE CONSTRUCCION (JC) 5/8'' m 34.00 14.39 S/ 489.26 33.00 S/ 474.87 97.06%
09 TRANSPORTE
09.15 TRANSPORTE DE MAT. GRANULAR PARA BASE HASTA 1KM m³ 15,370.15 6.53 S/ 100,367.08 15,149.65 S/ 98,927.21 98.57%
09.16 TRANSPORTE DE MAT. GRANULAR BASE D > 1KM m³ 844,563.47 1.03 S/ 869,900.37 831,443.70 S/ 856,387.01 98.45%
09.17 TRANSPORTE DE AGUA PARA BASE HASTA 1KM m³ 657.16 12.83 S/ 8,431.36 642.69 S/ 8,245.72 97.80%
09.18 TRANSPORTE DE AGUA PARA BASE D > 1KM m³ 510.17 1.54 S/ 785.66 489.69 S/ 754.13 95.99%
12.03 PROGRAMA DE MANEJO DE REISDUOS
12.03.01 ADQUISICION DE CONTENEDORES und 15.00 732.00 S/ 10,980.00 10.00 S/ 7,320.00 66.67%
12.03.02 BAÑO QUIMICO PORTATIL mes 10.00 4,560.00 S/ 45,600.00 2.80 S/ 12,768.00 28.00%
12.04 PROGRAMA DE CIERRE Y ABANDONO
12.04.02 READECUACION AMBIENTAL DE DME ha 1.50 13,124.85 S/ 19,687.28 0.50 S/ 6,526.43 33.33%