SSUPPORTING ELECTRICITY SUPPLY RELIABILITY IMPROVEMENT PROJECT – PACKAGE 4
ELLA GANTRY RC RETAINING WALL CONSTRUCTION METHODOLOGY
1. Overview
This report contains the methodology that must be followed for safe
construction of reinforced concrete retaining walls at Ella Gantry Location.
2
SSUPPORTING ELECTRICITY SUPPLY RELIABILITY IMPROVEMENT PROJECT – PACKAGE 4
ELLA GANTRY RC RETAINING WALL CONSTRUCTION METHODOLOGY
Fig. 2 – Soil fill at toe of 3.0m retaining wall (marked in red lines)
3
SSUPPORTING ELECTRICITY SUPPLY RELIABILITY IMPROVEMENT PROJECT – PACKAGE 4
ELLA GANTRY RC RETAINING WALL CONSTRUCTION METHODOLOGY
Fig. 3 – Plan view of a typical 4.0m excavation stretch for 2.0m retaining wall
iii. Once the targeted concrete strength for retaining wall is achieved,
soil excavation on the retained side shall be backfilled in 0.3m layers
with excavated soils at site and compacted to achieve 95% of
maximum dry density.
iv. Excavation on gantry land area shall commence afterwards in 1.0m
layers up to required ground level as per approved drawings.
v. All the drainage details shown in approved drawings regarding Ella
Gantry shall be followed for safety of the construction (refer QHP-
SES-10-GTY-03 & QHP-SES-10-GTY-10)