NAW JOB NO - R 18278
Ref: PO No 0-847 Dated 01.06.2023 for 5 Nos Gear
Boxes on NAW Kolkatta
Sub: Inspection clearance dated 27.01.2024
1. Further to Internal inspection Reports and Raw Material test reports
submitted already by NAW, the following inspection were carried
out jointly on 27.01.2024 in presence of Mr MN Chandrasekaran,
Technical Advisor, VAID. These were reviewed jointly are as under —
a. All 5 Gear boxes were inspected for critical dimensions and
marked in the drawing and found to be OK
b. 04 following units out of OSnos were Run tested for
performance. The run test Inspection Record Sheets are
enclosed.
-CSC 200 having gear box sI no HZ 62
-CSC 180 having gear box sI no HZ 61
-CSC 160 having gear box sI no HZ 63
-CSC 140 having gear box sl no HZ 65
-CSC 160 having gear box sI no HZ 64
c. Photos of all 5 gearboxes were taken and are as enclosed.
d. From the joint inspection & testing, it is observed that same
are in line with internal reports already submitted.
2. With the above, the final inspection of all 05 no gear boxes are
completed.
3. With this, NAW can submit to VAID, Cochin office, for despatch
clearance.
4. Other formalities like painting, packing, fumigation etc., shall be as
per PO terms and advice from VAID, Cochin office.5. This inspection completion does not absolve NAW of their
Responsibility of Ensuring Satisfactory Performance at site and other
PO terms and conditions.
LST ITY Orn,
(Amann) (MN Chandrasekaran)
(NAW) VAID
Encl: a/a