You are on page 1of 34

CONSTRUCTION CLAIMS MANAGEMENT

&
EOT DELAYS ANALYSIS

Contract Module
Part 1

Presented by :
Hany Ismail, MSc, PMP
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS

CONTRACT MODULE
CONTRACT IS ONE OF THE MOST IMPORTANT REFERENCES
AND DOCUMENTS FOR ANY CLAIM , YOU HAVE TO REFER
FOR EVERY ENTITLEMENT YOU ASKING FOR IN YOUR CLAIM
WITH THE CONTRACT REFERENCE AND ITS CLAUSE.
IN CONTRACT MODULE AND ITS LECTURES WE WILL FOCUS
ON SOME OF THE MOST IMPORTANT CONCEPTS AND
ESSENTIAL INFORMATION , YOU HAVE TO KNOW DURING
YOUR CLAIM PREPARATION FORM THE CONTRACT
ADMINISTRATION POINT OF VIEW.

WWW.PLANNINGENGINEER.NET
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS

PART 1
INTRODUCTION ABOUT CONTACTS &
CONTRACTS TYPES

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Agenda
• Introduction
• Construction Industry Parties
• What is Contract ?
• Contract Strategy
• Contract Need
• Contract Documents
• Contract Documents Priorities
• Construction Contract Forms
• Contracting Process
• Types of Contract
• Conditions of Contract
• Legal Laws WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Construction Industry Parties


The key parties involved in most construction projects
and considers what each of their roles are and how
they are linked to one another i.e. the contracts that are
entered into between them.
Employer
Contractor
Professional Team ( Engineer )
Sub-Contractors
Employer's Agent/Project Manager
Funder / Sponsor WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Construction Industry Parties


The relationship between all the parties differs
according to the contract type ,form and conditions.

Employer

Engineer

Contractor

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

What is a Contract
 A contract is defined as: “An agreement made
between two or more parties which is enforceable by
law to provide something in return for something
else from a second party".

 The two parties are expected to perform the various


obligations they have undertaken, as expressed in a

mutually agreed set of contract documents.

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Strategy
 Contract strategy means selecting organizational
and contractual policies required for the execution
of a specific project.

 The development of the contract strategy comprises


a complete assessment of the choices available for
the management of design and construction to
maximize the probability of achieving project
objectives.
WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Strategy
A proper contract strategy for a project involves Four
key decisions:

 Setting the project objectives and constraints.

 Selecting a proper project delivery method.

 Selecting a proper contract form / type.

 Contract administration practices.

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Do you think …

All Agreements are Contracts ??

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

 Competent (legal standing) Parties


For an agreement to be a contract, there must be two or
more competent parties. In order to be considered
competent, a part must have a certain legal standing.

 Proper Subject Matter


For the subject matter of a contract to be proper, the first
requirement is that it was be clearly defined as to the
rights and obligations of each party. Second, the
purpose of the contract must not violate the law.
WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

 Consideration
There must be a lawful and valuable consideration given
to both parties. A consideration often called "Something
for Something." A consideration must, also, be possible.

 Agreement
For valid contract, there must be a mutual agreement.
An agreement is considered to have been reached
when an offer made by one party is accepted by the
second party. Both parties must wish and intend their
bargain to be enforceable by law. WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

 Proper Form
The terms of a contract must be written so that both
parties are very sure of what their rights and
responsibilities are.

 Consent (agreement) of the Parties


The agreement must be free from Misrepresentation or

Duress (by force) , ..etc.

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Need
 Contracts provide a description of responsibilities and
liabilities.

 Contracts bind parties to their duties.

 Contracts can establish a time frame for duties.

 Contracts can secure payment.

 Contracts can provide resources.

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

What are the …

Contract Documents??

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Documents
The contract is defined by the contract documents,
which are developed from the tender documents.

Contract
Documents

Agreement General Special


Additional
Form Conditions Conditions

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Documents
1- Contract Agreement.
Which represent the final agreement document that is signed by both
parties and contains the full detailed information about them.

2- Letter of Tender.
Letter of Tender is the letter which is completed by the contractor and
contains the signed offer to the Employer.

3- Letter of Acceptance.
Letter of Acceptance” is the letter sent from the Employer to the
contractor including any annexed attached agreed between both parties.
If the Letter of Acceptance is not available it will be referred to the
Contract Agreement and related dates.

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Documents
4- Conditions of Contract.
1. Special Conditions.
2. General Conditions
Which represents the rights and obligations for both parties

5- Specifications.
Which should contain a detailed description on design and material used
in execution.

6- Drawings.
Which Indicates to the drawings specified in the Specification Document
and any drawing modifications written by the Consultant.

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Documents
7- Programme
Means the document(s) entitled schedules, completed by the
Contractor and submitted with the Letter of Tender, as included in
the Contract. Such document may include the Bill of Quantities,
data, lists, and schedules of rates and/or prices.

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Documents Power??

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contract Documents - Priorities


In the Case of any differences arising between the contract
documents, What is the order of documents power?

For Example :

1.The Contract Agreement 5.Drawings

2. Letter of Acceptance 6. Specifications

3. The Particular Conditions 7.B.O.Q

4. The General Conditions

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Construction Contract Forms


They are forms guide the drafting of documents on civil
engineering and construction projects for the purpose of
obtaining tenders, awarding and administering Contracts.

As such they legally define the responsibilities and duties


of Employers (who commission work) and Contractors
(who carry out work) in the Works Information such as
( Fidic Contract Forms , NEC Form , …etc.).

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Contracting Process
Identify Project
Prepare Scope
Select Contract
Prepare Tender Documents
Invite Tenders
Tender Meetings
Tender Evaluation
Place Contract
WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Types of Contracts

Cost Plus
Cost based
Target Cost
Contract
Unit Price
Price based
Lump Sum

WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis – Part 1

Unit Price contract


 Contract Value: Tender price is usually increased by

variations and claims.

 Payment : Payment is paid monthly for all work


completed during the month or any duration agreed .

 Design Changes : Offers a facility for the client to


introduce changes in the work defined in the tender
documents.

 Additional Payments : Additional payments for any


changes in the work content of the contract.
Construction Claims Management & EOT Delay Analysis – Part 1

Unit Price contract


 Using : This contract is best suitable for repetitive
works.

 Variations : Not limited

 Additional Payments : For variations or quantity


increase of the items in the BOQ

WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis – Part 1

Lump-sum contract
 Contract Value: Single tendered price is given for the
completion of specified work by a certain date.

 Payment : May be staged at intervals on the completion.

 Design Changes : Contract has a very limited flexibility


for design changes.

 Contract Final Price : Final price is known at tender.

 Contractor Risk : High Level of Risk.


 Employer Risks : Low Level of Risks, transfer risks to
the contractors. WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis – Part 1

Lump-sum contract
 Using : This contract may be used for a turn key
construction

 Important Risk : An important risk t the client is that of


not receiving competitive bids from desirable
contractors who may avoid a high-risk lump-sum
contract.

 Variations : limited variations are expected

 Additional Payments : For variations Only.


WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Construction Claims Reference


to the Contract

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Construction Claims
• A construction claim is a request for payment or
time extension to which the contractor considers
him/herself entitled under the contract conditions
and terms . There are three types under which
claims are required:

Extension of time only.

 Additional cost.

 Both extensions of time and additional cost.


WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Legal systems

Legal Systems

Civil Law Common Law


) ‫( القانون المكتوب‬ )‫( السوابق القضائية‬

WWW.PLANNINGENGINEER.NET
Construction Claims Management ( Contract Module – Part 1 )

Egypt Applicable Law

Egypt Applicable Law

Civil Law Administrative Law


) »‫( القانون الخاص «القانون المدنى‬ ) »‫( القانون العام «القانون اإلدارى‬

Arbitration Law
Law 89 and its Law 119 year 2008 (Law 27 year 1997)
Amendments () ‫قانون البناء الموحد‬ ( ‫قانون‬
) ‫التحكيم‬

WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis – Part 1

WWW.PLANNINGENGINEER.NET
Thank You …
We hope you enjoy our lecture today

Hope to receive your feedback and recommendations

Contact Info
WWW.PLANNINGENGINEER.NET
INFO@PLANNINGENGINEER.NET
Mobile : +20 1277767728 /PlanningEngineerDotNet

/groups/4809645

You might also like