Work Breakdown Structure ( WBS )

LEVEL 1` LEVEL 2 LEVEL 3 PIC DURATION PREDECESSOR


1.1.1 Evaluation & Recommendation
Project Manager 2 -
(A)
1.1 1.1.2 Determine Project Team (B) Project Manager 2 A
Initiation
1.1.3 Develop Project Charter (C) Project Manager 3 B
1.1.4 Project Charter Approved (D) Project Manager 1 C
1.2.1 Project Team Kickoff Meeting
ALL 1 C
1.2 (E)
Planning 1.2.2 Develop Project Plan (F) ALL 2 E
1. Aplikasi
TrashTracker 1.2.3 Submit Project Plan (G) ALL 1 F
1.3.1 Create an SRS document that
defines the software requirements System analyst 10 F
specification. (H)
1.3 1.3.2 Define existing procedures in
System analyst 10 F
Execution the system. (I)
1.3.3 Create flow documents, flow
System analyst 5 I
systems. (J)
1.3.4 Create User Persona (K) System analyst 3 J
1.3.5 Analyze suitable design
UI/UX Designer 1 K
methods (L)
1.3.6 Creating the interface of the
UI/UX Designer 20 L
system (M)
1.3.7 Prototype the application (N) UI/UX Designer 5 M
1.3.8 Create a test plan for system
Software tester 5 N
implementation. (O)
1.3.9 Control alignment and System
1 O
completeness of all documents. (P) Documentation
1.3.10 Create a software user guide System
3 P
information systems. (Q) Documentation
1.4.1 Project Management Project Manager - -
1.4.2 Project Status Meetings Project Manager - -
1.4 Control 1.4.3 Risk Management Project Manager - -
1.4.4 Update Project Management
Project Manager - -
plan
1.5.1 Audit Procurement Project Manager - -
1.5.2 Document Lessons Learned ALL -
1.5
1.5.3 Update Files/Records ALL -
Closeout
1.5.4 Gain Formal Acceptance (R) Project Manager 3 Q
1.5.5 Archive Files/Document (S) Project Manager - A-R