ANALISA HARGA SATUAN PEKERJAAN

BANDAR LAMPUNG

Supl A.4.5.1.7a. Pemasangan 1 m2 langit-langit PVC board + rangka galvalum


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.O1 OH 0.3500 80,000.00 28,000.00
Tukang Kayu L.O2 OH 0.3500 100,000.00 35,000.00
Kepala Tukang L.O3 OH 0.0350 125,000.00 4,375.00
Mandor L.O4 OH 0.0180 125,000.00 2,250.00
JUMLAH TENAGA KERJA 69,625.00
B BAHAN
Besi Hollow 2/4 M' 4.0500 7,500.00 30,375.00
Planfond PVC M' 5.0000 15,500.00 77,500.00
Join PVC M' 3.1000 2,500.00 7,750.00
Paku Skrup Kg 0.1100 30,000.00 3,300.00

JUMLAH HARGA BAHAN 118,925.00


C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 188,550.00
E Overhead & Profit 15% x D 28,282.50
F Harga Satuan Pekerjaan (D+E) 216,832.50