Professional Documents
Culture Documents
Lot 3 Rehabilitation of FMR Purok Silangan Brgy. Salakit
Lot 3 Rehabilitation of FMR Purok Silangan Brgy. Salakit
Salakit
Location : Brgy. Salakit, Kiamba, Sarangani Province
DETAILED ESTIMATES
Summary:
Direct Cost P 247,500.00
Profit P 24,750.00
Contingency, Overhead and Miscellaneous P 19,800.00
VAT P 17,325.00
Total Indirect Cost P 61,875.00
Total Cost P 309,375.00
Unit Cost P 309,375.00
Bid Cost P 309,375.00
DETAILED ESTIMATES
3 Dumptruck 10,800.00 10.00 P 324,000.00
2 Backhoe 12,500.00 10.00 250,000.00
1 Payloader 14,500.00 10.00 145,000.00
1 Road Roller 12,500.00 10.00 125,000.00
1 Water Truck 4,500.00 10.00 45,000.00
889,000.00
Materials:
Materials Unit Price Quantity
Embankment 150.00 12,226.25 cu.m. P 1,833,937.50
1,833,937.50
Summary:
Direct Cost P 2,751,737.50
Profit P 275,173.75
Contingency, Overhead and Miscellaneous P 220,139.00
VAT P 192,621.63
Total Indirect Cost P 687,934.38
Total Cost P 3,439,671.88
Unit Cost P 351.67 /cu.m.
Bid Cost P 3,439,684.27
DETAILED ESTIMATES
Unit Cost P 570.62 /cu.m.
Bid Cost P 961,380.58
DETAILED ESTIMATES
No. Manpower Rate/Day No.of Days
1 Const. Foreman 700.00 8.00 P 5,600.00
2 Skilled Worker 450.00 8.00 7,200.00
4 Unskilled Worker 320.00 8.00 10,240.00
23,040.00
Equipment:
Unit Equipment Rate/Day No.of Days
3 Dumptruck 10,800.00 8.00 P 259,200.00
1 Backhoe 12,500.00 8.00 100,000.00
359,200.00
Summary:
Direct Cost P 382,240.00
Profit P 38,224.00
Contingency, Overhead and Miscellaneous P 30,579.20
VAT P 26,756.80
Total Indirect Cost P 95,560.00
Total Cost P 477,800.00
Unit Cost P 329.28 /cu.m.
Bid Cost P 477,805.04
DETAILED ESTIMATES
Profit P 106,104.00
Contingency, Overhead and Miscellaneous P 84,883.20
VAT P 74,272.80
Total Indirect Cost P 265,260.00
Total Cost P 1,326,300.00
Unit Cost P 5,979.17 /cu.m.
Bid Cost P 1,326,299.49
DETAILED ESTIMATES
37,500.00
Materials:
Materials Unit Price Quantity
Cement 260.00 380.00 bags P 98,800.00
Sand 1,000.00 12.00 cu.m. 12,000.00
Boulders 800.00 60.00 cu.m. 48,000.00
158,800.00
Summary:
Direct Cost P 219,340.00
Profit P 21,934.00
Contingency, Overhead and Miscellaneous P 17,547.20
VAT P 15,353.80
Total Indirect Cost P 54,835.00
Total Cost P 274,175.00
Unit Cost P 4,693.97 /cu.m.
Bid Cost P 274,174.79
ITEM 1046(1) 100mm thk. CHB LOAD BEARING (INCLUDING REINFORCING STEEL)
Quantity: 936.00 sq.m.
Manpower:
1 Foreman 500.00 20.00 days P 10,000.00
2 Skilled Worker 350.00 20.00 days 14,000.00
4 Unskilled Worker 270.00 20.00 days 21,600.00
45,600.00
Materials:
Cement 260.00 253.00 bags P 65,780.00
Sand 1,000.00 21.00 cu.m. 21,000.00
100mm thk CHB 30.00 12,168.00 pcs 365,040.00
Reinforcing Steel 60.00 1,536.00 kgs 92,160.00
543,980.00
Direct Cost P 589,580.00
Profit P 58,958.00
Contingency, Overhead and Miscellaneous P 47,166.40
VAT P 41,270.60
Total Indirect Cost P 147,395.00
Total Cost P 736,975.00
Unit Cost P 787.37 /sq.m.
Bid Cost P 736,978.32
Submitted By:
Submitted By:
T SCHEDULE
FOURTH QUARTER
27.81%
P 4,958,211.93
100.00%
P 17,828,881.43
MRRM TRADING AND CONSTRUCTION
Project Name : Rehabilitation of 2.08Km Farm-to-Market Road from Purok Silangan to Brgy. Salakit
Location : Brgy. Salakit, Kiamba, Sarangani Province
Submitted By:
SUMMARY OF QUANTITIES
GENERAL REQUIREMENTS
B.9 MOBILIZATION/ 1.00 lump sum P 309,375.00 P 309,375.00
DEMOBILIZATION
B.5 PROJECT BILLBOARD 2.00 each P 6,250.00 P 12,500.00
ROAD UPGRADING
100(3) INDIVIDUAL REMOVAL OF TREES 23,228.00 cu.m. P 214.27 P 4,977,063.56
104(1) EMBANKMENT 9,781.00 cu.m. P 351.67 P 3,439,684.27
105 SUBGRADE PREPARATION 12,896.00 sq.m. P 33.32 P 429,694.72
200 AGGREGATE SUBBASE COURSE 1,684.80 cu.m. P 570.62 P 961,380.58
201 AGGREGATE BASE COURSE 1,184.00 cu.m. P 396.39 P 469,325.76
311(1) PORTLAND CEMENT CONCRETE PAVEMENT 2,400.00 sq.m. P 1,373.94 P 3,297,456.00
DRAINAGE STRUCTURE
103(1) STRUCTURE EXCAVATION 1,451.06 cu.m. P 329.28 P 477,805.04
404 REINFORCING STEEL BAR, GRADE 40 6,833.90 kgs P 86.93 P 594,070.93
405 STRUCTURAL CONCRETE, CLASS A 221.82 cu.m. P 5,979.17 P 1,326,299.49
103(6) CULVERT AND DRAIN EXCAVATION 45.61 cu.m. P 421.51 P 19,225.07
500(1) 36" DIAMETER RCCP 42.00 ln.m. P 7,876.79 P 330,825.18
506 STONE MASONRY HEADWALL 58.41 cu.m. P 4,693.97 P 274,174.79
1046(1) 100mm THK. CHB LOAD BEARING 936.00 sq.m. P 787.37 P 736,978.32
(INCLUDING REINFORCING STEEL)
1027(1) CEMENT PLASTER FINISH 1,248.00 sq.m. P 138.64 P 173,022.72
Submitted By: