User Manual RF I Report
User Manual RF I Report
• After submission of RFI Detail , the message will be shown at the top “ success- RFI
Report forwarded successfully to AE”.
➢RFI Report Form - Contractor
*Note for template : In the scheduled date and time column kindly keep the data in text
format and not in any other format. While copying data from other sources keep the
format in text only.
➢RFI Report Import - Contractor
• Upload the RFI Report by : select upload file → select file from file chooser dialog
•Click on submit
➢RFI Report Import - Contractor
•Once the file is uploaded the entries will be shown in the table below.
•A message will be shown at the top : “ Success – RFI report imported successfully” .
AE LOGIN – RFI REPORT
➢RFI Report - AE
AE can view the details submitted by Contractor and can take action on it. AE will follow
below steps:
•From Menu click on “Project Document and Approval” it will show sub menu, click on
“RFI Report”.
•Table will show the latest submitted details by contractor with action button “Assign
Inspector”
➢RFI Report - AE
•If the inspector is assigned the name of inspector will be shown in the table.
•A Message will be shown “ Success – Inspector Assigned Successfully”.
•Then AE can Upload the inspection report by clicking on “upload inspection report”.
➢RFI Report - AE
•If no inspector is assigned to the contractor within 24 hours, the contractor itself can do
the inspection and upload the inspection report
•On contractor login, it will get the option to upload inspection result.
➢RFI Report – Inspection Result upload - Contractor