Professional Documents
Culture Documents
Anchored Diaphragm Walls in Sand - Some Design and Construction Considerations
Anchored Diaphragm Walls in Sand - Some Design and Construction Considerations
WA
SOME DESIGN AND CONSTRUCTION
S 'k S,,'k
CONSIDERATIONS
by G. S. LITTLEJOHN, BSc, PhD. CEng, MICE. FGS; B. JACK, CEng, MIStructE; and Z. SLIWINSKI, CEng, MICE"
This Paper introduces a method of estimating the lem when implementing the trapezoidal method.
anchor loads required to support a multi-tied con- The Paper then describes the main design and
tinuous wall. It involves a procedure which calculates stability considerations associated with trench exca-
the position and magnitude of a resultant tie at any vation under bentonite, and gives recommendations
stage of excavation by treating the wall as a single covering the main requirements for tremie concrete
tied structure. for load-bearing diaphragm walls.
Comparison of designs carried out by the Cemen- Methods of estimating anchor location, overall
tation method and experimental work indicates that stability and load carrying capacity with relevant
the results obtained provide a good estimate of the safety factors, are illustrated. Anchor construction
horizontal forces. Also shown are the results ob- stages are described, together with the post-tension-
tained by the generally used methods. ing procedures and corrosion protection normally
The new method has the advantage of being a recommended for sand anchors. Finally, the influence
repetitive single-tied wall design, and it is amenable of prestressed tie-backs on the lateral movements
to varying oil strata, which has always been a prob- and settlement of the retained soil mass is discussed.
DUE PRIMARILY TO the increasing The diaphragm process of construct- by restrictions on access and noise, and
tendency to design buildings with a ing load-bearing walls in the ground where a wall with high structural effi-
number of basement floors, the form- prior to main excavation, based on the ciency and few joints is required. In
ation level of the excavation being often use of bentonite slurry to hold open the addition, settlements of the soil sur-
at considerable depth below the foun- excavaticn until concrete has been rounding the excavation are minimised
dations of the neighbouring properties, placed, is such a method. The technique due to the ability of the bentonite to
methods of temporary and permanent is of special value in built-up areas reduce loss of ground during wall con-
earth suppcrt have been developed in since diaphragm walls may be con- struction and the strength and stiffness
recent years to keep pace with the in- structed in very close proximity to ex- of the wall itself. In some instances, the
creased efficiency of modern construc- isting buildings, where other methods diaphragm wall may serve as the ex-
tion. of piling and trenching may be ruled out terior wall for the permanent structure.
In many cases it is possible to
achieve appreciably increased effi-
Fig. 1. General view of anchored diaphragm wall, by courtesy of Trollope and ciency, as well as reducing settlements
Coils Ltd.—Guildhall Precincts Redevelopment during the main excavation, by using
prestressed soil anchors for supporting
the wall. Anchors provide intermediate
points of support at ono or more levels,
thereby reducing bonding moments,
w;'th consequent reductions in d'.men-
sions, reinforcement and depth of the
toe of the wall. Interior struts can be
eliminated, which in turn brings quite
large economic and constructional ad-
vantages. This is especially so in
cramped excavations, in wide cuts or
on sites where the contract programme
calls for the use of efficient excavation
and construction machinery (see Fig.
1).
Although both diaphragm wall and
soil anchor techniques have been
proved since the late 1950s, there is
I I
g
~I«
~4~ i ss
is working in a consultative capacity with
Cementation Piling and Foundations, I.td.
~
» isi i
14
I I
published information on walls are likely to be considered by the prac- prestressed and inclined soil anchors
by prestressed tie-backs. tising engineer, and to emphasise that entails a fundamental difference because
supported
whilst design procedures for excava- construction methods play a more sig-
The purpose of this article is to discuss nificant part in determining the forces
the main design and con- tions supported by soldiers and plank-
jn some detail which result in the
ing are readily available, the design of and displacements
struction aspects associated with an
continuous walls supported by tiers of wall and anchors.
anchored diaphragm wall in sand, which
Ground Engineering 15
(a) (b) (c) In this design method, it is
assumed that there is a point of rota-
tion as in the single-tied wall, but this
Pa'ressures.
R, point does not occur at a tie level but at
some intermediate level between the
T,
first and second ties. Since this level
cannot readily be determined its posi-
Pp Pa'epth tion has to be estimated, as outlined
of
F.O.S. 1 previously.
This procedure may be continued
down through any number of ties.
Tie No. 2
CZZZ
Tie No. 2
Tie No. 3
IZZKKZ
Tie No. 4
CZZZZ
Experimental results
Fig. 4 TschebotarioR's method
Terzaghi's method
T = Actual tie force Brinch Hansen's method
7 = Density
H = Total height retained Cementation's method I I
'St
—30 ft
Key G.R. Golder
ii 18ft G.D. -Gould
I
are familiar and should involve no (v) Although the procedure is simple, have to be varied as construction takes
difficulties in implementing. it produces results which comply place. For this purpose it is necessary
(ii) It is amenable to varying soil strata closely with experimental data for a quick and rapid design method to
— always a problem when imple- available to date. be available and it is noteworthy that
menting the trapezoidal method. The necessity of close co-ordination Cementation have produced a computer
(rii) It allows struts or ties to be in- between the design, soils and con- program that can analyse continuous
serted at levels chosen by the en- struction engineers throughout all multi-tied walls supporting soils of vary-
gineer to take full advantage of the stages of the work is again emphasised ing characteristics and which enables
initial cantilevering abilities of dia- because whenever the problem of quick amendments to be made to the
phragm walls —
difficult, if at all foundations is being studied, especially design based on the soil conditions ex-
possible, when using the trape- in the field of retaining walls, the design posed as the wall is being constructed.
zoidal method. may have to be amended as the work (To be continued)
(rv) It allows the wall penetration to proceeds. The limited number of bore-
be calculated based on a rota- holes which can be put down on any In the second part of this Paper,
tiona! criteria as well as the direct site is generally insufficient to provide a Z. Sliwinski considers wall construction,
summation of horizontal forces complete picture of the ground strata while the third, by G. S. Littlejohn, deals
used in the trapezoidal method. and tie bar positions and forces may with anchor design.
Ground Engineering 17