You are on page 1of 4

tAG V

WA
SOME DESIGN AND CONSTRUCTION
S 'k S,,'k
CONSIDERATIONS
by G. S. LITTLEJOHN, BSc, PhD. CEng, MICE. FGS; B. JACK, CEng, MIStructE; and Z. SLIWINSKI, CEng, MICE"

This Paper introduces a method of estimating the lem when implementing the trapezoidal method.
anchor loads required to support a multi-tied con- The Paper then describes the main design and
tinuous wall. It involves a procedure which calculates stability considerations associated with trench exca-
the position and magnitude of a resultant tie at any vation under bentonite, and gives recommendations
stage of excavation by treating the wall as a single covering the main requirements for tremie concrete
tied structure. for load-bearing diaphragm walls.
Comparison of designs carried out by the Cemen- Methods of estimating anchor location, overall
tation method and experimental work indicates that stability and load carrying capacity with relevant
the results obtained provide a good estimate of the safety factors, are illustrated. Anchor construction
horizontal forces. Also shown are the results ob- stages are described, together with the post-tension-
tained by the generally used methods. ing procedures and corrosion protection normally
The new method has the advantage of being a recommended for sand anchors. Finally, the influence
repetitive single-tied wall design, and it is amenable of prestressed tie-backs on the lateral movements
to varying oil strata, which has always been a prob- and settlement of the retained soil mass is discussed.

DUE PRIMARILY TO the increasing The diaphragm process of construct- by restrictions on access and noise, and
tendency to design buildings with a ing load-bearing walls in the ground where a wall with high structural effi-
number of basement floors, the form- prior to main excavation, based on the ciency and few joints is required. In
ation level of the excavation being often use of bentonite slurry to hold open the addition, settlements of the soil sur-
at considerable depth below the foun- excavaticn until concrete has been rounding the excavation are minimised
dations of the neighbouring properties, placed, is such a method. The technique due to the ability of the bentonite to
methods of temporary and permanent is of special value in built-up areas reduce loss of ground during wall con-
earth suppcrt have been developed in since diaphragm walls may be con- struction and the strength and stiffness
recent years to keep pace with the in- structed in very close proximity to ex- of the wall itself. In some instances, the
creased efficiency of modern construc- isting buildings, where other methods diaphragm wall may serve as the ex-
tion. of piling and trenching may be ruled out terior wall for the permanent structure.
In many cases it is possible to
achieve appreciably increased effi-
Fig. 1. General view of anchored diaphragm wall, by courtesy of Trollope and ciency, as well as reducing settlements
Coils Ltd.—Guildhall Precincts Redevelopment during the main excavation, by using
prestressed soil anchors for supporting
the wall. Anchors provide intermediate
points of support at ono or more levels,
thereby reducing bonding moments,
w;'th consequent reductions in d'.men-
sions, reinforcement and depth of the
toe of the wall. Interior struts can be
eliminated, which in turn brings quite
large economic and constructional ad-
vantages. This is especially so in
cramped excavations, in wide cuts or
on sites where the contract programme
calls for the use of efficient excavation
and construction machinery (see Fig.
1).
Although both diaphragm wall and
soil anchor techniques have been
proved since the late 1950s, there is

«At the time of writing, all the authors were


with Cementation Co., Ltd. Dr. Littlejohn was a
consultant w.'th Cementation Ground Engineer-
ing, Ltd., but is now Lecturer in Geotechnics,
Dept. of Engineering, University of Aberdeen.
Mr. Jack, formerly a senior design engineer
with Cementation Technical Services Division,
has now started his own practice in Reigate as
consulting structural and foundation enoineers,
under the title Brian J. Jack. Mr. Sliwinski

I I
g
~I«
~4~ i ss
is working in a consultative capacity with
Cementation Piling and Foundations, I.td.

~
» isi i
14
I I
published information on walls are likely to be considered by the prac- prestressed and inclined soil anchors
by prestressed tie-backs. tising engineer, and to emphasise that entails a fundamental difference because
supported
whilst design procedures for excava- construction methods play a more sig-
The purpose of this article is to discuss nificant part in determining the forces
the main design and con- tions supported by soldiers and plank-
jn some detail which result in the
ing are readily available, the design of and displacements
struction aspects associated with an
continuous walls supported by tiers of wall and anchors.
anchored diaphragm wall in sand, which

wall used. In the case of steel piling


where the wall is driven into the
ground, the pressures before excava-
WALL tion at either side may be considered
"at rest", whereas with diaphragm wall
DESIGN construction where an excavation is
opened up and the ground stabilised by
the use of bentonite some yielding of
by B. J. JACK the soil occurs, tending to reduce the
"at rest" pressures to those approach-
ing the active state. Therefore, even
within the field of continuous retaining
When studying the support of exca- Terzaghi. This method was established walls different parameters will have to
vations. the following topics have to from experiments carried out on an ex- be employed depending upon the type
be considered: (i) the type of soil to be cavation in Berlin through cohesicnless of construction, spacing of props, etc.
retained, (ii) the type of wall to be material supported by soldier piles and The stress distribution, which gov-
used, and (iii) the method of design. planking. It should be remembered, erns the design, depends upon the
The first stage is the collection and however, that the pressure distribution walling material used, the method of
interpretation of soils data. In this con- was based on an envelope enclosing construction and the centres at which
nection the design engineer has to de- assumed parabolic distributions at each the struts or ties are installed, since it
cide the type of soils investigation re- stage of excavation, the size and shape is the effective span at any one stage of
quired to facilitate the design of the being calculated equal to the magnitude construction that will determine the de-
permanent structure and provide the and distribution of the actual measured flection, and consequently the re-
construction engineer with sufficient in- strut forces. This trapezoidal pressure distribution of soil pressures. One of the
formation to build the work. These two distribution is valid only under certain most important factors in this respect
separate requirements can quite often conditions since the actual earth pres- is the strength of the soil in front of the
lead to different soils tests and affect sures are a function of the degree and wall mobilising the passive pressure,
the distribution of boreholes throughout type of freedom for lateral expansion of as this determines the additional di-
the site. The role of the soils engineer in the retained soil. mension below excavation level making
this kind of problem cannot be over- It is evident that the soil pressures up the effective span.
emphasised; he and the wall designer existing behind contiguous piles, steel In the case of multi-tied walls, as
should co-ordinate from the initial con- sheet piling and diaphragm walling will stage by stage excavation proceeds the
cepts of the work right through to final be different to those of a soldier pile passive pressure producing the effective
design stage and even into the con- construction as the earth support pro- span at any one stage can be assessed
struction period. vided by the material to be excavated approximately, but as excavation pro-
Once the soils investigation has been at any stage acts on the full wall face ceeds past a particular stage the ground
carried out and test results are avail- and not on small areas, which is the which was restraining the wall is re-
able, both for the permanent and tem- case when using soldier piles. The bear- moved and further deflection can take
porary works construction, the design ing pressure will be less, reducing the place. The amount of passive resistance
engineer must choose what type of wall wall's lateral movement, thus effecting built up at any intermediate stage,
is to be employed for the support of the the redistribution of earth pressure. when removed, must be added to the
excavation. These days, a wide variety active pressures on the wall, since in
cf methods is available, varying from Design parameters the previous stage it was subtracted to
planking and strutting through to the Rowe's work on single tied walls has produce the resultant pressure diagram
use of diaphragm walls which can be clearly shown that one of the most im- and hence the tie bar forces above. If
incorporated in the permanent struc- portant factors in this type of design is this is done, then the final soils distri-
ture. Having chosen the method or a the wall's flexibility, which tends to re- bution achieved will be of a triangular
number of methods of retaining the soil, duce the maximum bending moments form with exaggerated "bumps" at each
the design engineer is now faced with and increase the tie bar forces through tie level, the amount of additional pres-
the problem of how to determine the arching of the ground. It is quite logical sure at a tie being dependent upon the
structural stresses, tie bar forces, etc. that the smaller the deflection, the passive resistance built up at the in-
The design of walls to support deep smaller will be the arching effect and it stallation stage of that tie.
excavations is an art rather than a is reasonable to expect that where the With regard to the soil parameters
science, but nevertheless it is essential wall continues below the excavation which should be used in determining
that a logical approach is taken in the level, a high degree of fixity will produce the passive pressure which is available
design. Shallow excavations can utilise a less effective span, a smaller wall de- at any particular stage of excavation, it
cantilever or single-tied walls, for flection and less redistribution of soil is considered that the design should be
which much valuable information has pressures due to arching. It therefore evaluated for two conditions, firstly
been supplied by Rowe in his experi- seems inappropriate to use the "trape- using the immediate or undrained soil
mental work. By a careful study of the zoidal" method when designing walls of parameters, and secondly with the
soil parameters, wall flexibility, etc., in this type, because in these instances drained soil parameters, as it has been
~hase designs the engineer can make a one would expect a more triangular shown that the latter condition can
fair estimation of the behaviour of the pressure distribution. arise in a very short time period. This
structure in practice. If an extreme case is considered approach is, therefore, applicable not
At present little direction is available where a continuous diaphragm or sheet only to the design of works of a per-
cn continuous multi-tied wall design, piled wall is constructed in the ground manent nature such as underpasses, but
where cable anchors or struts are incor- and struts are inserted at close centres also for temporary works where, as in
porated in the support system. For deep as the excavation proceeds, little or no basement construction, the wall is only
walls using planking and strutting, the redistribution of soil pressures will exposed during the construction period.
methods recommended are generally take place and the resulting pressure Since the drained parameters approach
based on the "trapezoidal" pressure diagram will be of a triangular form. The the ultimate strength cf the soil, the
distribution which was originated by actual values will depend on the type of factor of safety when using these para-

Ground Engineering 15
(a) (b) (c) In this design method, it is
assumed that there is a point of rota-
tion as in the single-tied wall, but this
Pa'ressures.
R, point does not occur at a tie level but at
some intermediate level between the
T,
first and second ties. Since this level
cannot readily be determined its posi-
Pp Pa'epth tion has to be estimated, as outlined
of
F.O.S. 1 previously.
This procedure may be continued
down through any number of ties.

Comparison with existing design


Fig. 2 .Sr-t methods
Comparison of designs carried out by
the Cementation method and experi-
meters can be reduced below that nor- T,. Fig. 2 (c) shows mental work indicates that the results
this represented
mally employed, and values of 1.1 to diagramatically. obtained provide a good estimate of the
1.2 are recommended for consideration. horizontal forces and Fig. 4 shows this
The remaining problem now is to cal- method compared with model experi-
culate the position and magnitude of ments carried out by Rowe and Briggs
Design method R,. As T, is unknown, then both the
design method for for two, three and four tied walls. Also
The following position and magnitude of R, are un-
multi-tied walls has been developed by shown are the results obtained for
known. By assuming one, the other analyses carried out by the generally
Cementation to incorporate the effects may be calculated and the initial as- used methods.
of the temporary support produced by sumption checked. Since the lever arm Fig. 5 shows the method compared
the passive pressure at intermediate ex- of R, to the position of factor of safety with a full scale experiment and designs
cavation stages. of unity is usually small in comparison for this project submitted by various
It involves a procedure which calcu- to its magnitude it is necessary that engineers.
lates the position and magnitude of a this dimension is calculated to a high Field evidence from other tests on
resultant tie at any stage of excavation degree of accuracy and the following full scale walls is encouraging but
by treating the wall as a single tied iteration procedure is recommended to
modifications
structure. ensure a convergence upon the correct
to the method will be
built in if necessary in the form of flexi-
The method requires that the follow- answer. bility coefficients when the complete
ing assumptions are made: Fig. 3 shows the case where the ex- results of full scale and model tests,
(i) The mobilising and resisting soil cavation level has been reduced to a currently being carried out by Cementa-
forces are those determined using position for the insertion of the fourth tion, are available.
Rankine's earth pressure theory. tie. It is considered that until a method
(ii ) At failure there is an unique point Considering the equilibrium of the of design is produced which takes into
of rotation in the plane of the wall. system account the full interaction of the wall
j
(iii The wall is only of sufficient length ZH = 0 is satisfied when: and the soil flexibilities, then empirical
to mobilise a factor of safety of T( =R„— R methods of this nature must be used.
unity against rotation at any stage M = 0 is satisfied when The approach described takes account
of excavation. (R.xj —(Ts.y) = 0 .........
(2) of varying soil strata, wall flexibility and
The first assumption is made to sim- where y = D — x —1 method of excavation, and should en-
plify the calculations, and is the usual Substituting in (2) able the design engineer to make a bet-
one made when calculating earth pres- i(xj = (R.x)—T (D —x —1) ter assessment of the wall's behaviour
sures in the design office. = (R.x.)—TsD+Ts.x+Ts.1
The second assumption —
that the Substituting in Newton-Raphson's
than by assuming a trapezoidal pressure
distribution for a continuous wall, for
point of rotation occurs in the plane of iteration formula, which it was not originally envisaged.

the wall enables the following simple
n+1
R.x —TsD+ Ts.x+ Ts.1 The main advantages of the new
procedure to be used in calculating the n R+T method may be listed as:
additional tie bar forces produced when
the passive pressure is "transferred" to
where x, is the new estimate
and xn is the previous estimate of X
of X (i) It is a repetitive single-tied wall
design with which most engineers
the active side during the next stage of (This process is continued until the re-
excavation. quired accuracy is reached.)
Consider the equilibrium conditions This method can now be followed Original ground level
of the system shown in Fig. 2 (a) and through a typical design by considering f I
4~44'44 4444 44'4444 44~
(b). From Fig. 2 (a) the action of the wall as excavation pro- J
XH = 0 is satisfied when:
R
ceeds. The first stage of excavation is
T, = P,' PB'..............
(1) usually a cantilever having an exposed ——~
Tr
ZM = 0 is satisfied when: height of the order of 2— 5 m. The bend-

MP ——M, ing moments in the wall under this con- R4


(about position of T,) dition can be determined by the usual
From Fig. 2 (b) methods, but it should be noted that
ZH = 0 is satisfied when: the maximum bending moment occurs
Ti+T =P"—P" below the first tie level and not at the Excavation level
XM = 0 is satisfied when: tie level, as is often assumed when de- for the insertions
M p " = M 4 " (about the
centroid signing walls of this nature.
of tie T4
of T, and T, j After the installation of the first tie,
If we now consider a resultant tie R, the second stage of excavation pro-
in Fig. 2 (b) acting at the centroid of ceeds down to the level required for the
T, and T,'hen: insertion of the second tie. Under this Fig. 3
R,=T,+T,=P —P„" condition a single-tied retaining wall
Substituting for T, from equation (1) exists for which, as mentioned previ- R = Previous resultant tie force
then P; — P,'+T, = P "— Pp" ously, knowledge of the interaction of R
II
= New resultant tie forco
the soil and the wall flexibility is avail- I = Previous resultant tie force level
which gives the amount of pressure able. However, when the second tie is
transferred to T, when excavation pro- installed very little information is avail-
I
ll
= New resultant tie force level
ceeds to the point for the insertion of able on the redistribution of the soil T,1 T,s T,s & Tt = Individual tie forces
16
Tie forces Tie forces Tie forces
TI 6H'00 per ft TIIIHi .100perft Tl 5 H: x 100 per ft

987654321 9876543211 987654321 I

Tie No. 1 sxsi~m Surface level Tie No.1 ~ssa ~ Surface


'/////
level Tie No. I Surface level
'////////'//
aaaa i/ // ///// ~xx
x
v

Tie No. 2
CZZZ
Tie No. 2

Tie No. 2 Tie No. 3 exxavva


essed
C

Tie No. 3
IZZKKZ
Tie No. 4
CZZZZ

Excavation level ~ Excavation level


/r/////////////
~ Excavation level
/ /////////////
~
Wall with two ties (a) Wall with three ties (b) Wall with four ties (c)

Experimental results
Fig. 4 TschebotarioR's method
Terzaghi's method
T = Actual tie force Brinch Hansen's method
7 = Density
H = Total height retained Cementation's method I I

0.00 ft Fig. 5. Comparison of strut loads on retaining wall


s i (Journal of the Soil Mechanics and Foundations Division,
Gravel, sand, 4 ft
silt & claY
[ American Society of Engineers, May, 1970)
10 ft
110 2l 35
WL —10 ft Notes 1) Strut length 12 ft =
C 0 d'-=10' During construction it was found that penetration below -60 ft
could not be achieved. The actual load on S5, therefore, is
21 ft higher as the wall tends to cantilever over S5
Silt
110 8 30
—20 ft
C 400 x( - 10'n
CW 200 I I II 9 — ——I
II II 4 s

'St
—30 ft
Key G.R. Golder
ii 18ft G.D. -Gould
I

135 8 38 „ =9 ll~ II= i~t 4 T Tschebotarioff


d'5 W.A. Wilson "A"
II II II

C 0 'Ss —40 ft W.B. Wilson "B"


C 0 C C.L Cementation Co.. Ltd
10 ft A Actual
=~=a t 1 ——
J ~7~v= i ii II=II —l~
—50 ft
6R
il i il li~
6ft —60 ft
0 100 200 300 500 600 700

Strut load in kips

are familiar and should involve no (v) Although the procedure is simple, have to be varied as construction takes
difficulties in implementing. it produces results which comply place. For this purpose it is necessary
(ii) It is amenable to varying soil strata closely with experimental data for a quick and rapid design method to
— always a problem when imple- available to date. be available and it is noteworthy that
menting the trapezoidal method. The necessity of close co-ordination Cementation have produced a computer
(rii) It allows struts or ties to be in- between the design, soils and con- program that can analyse continuous
serted at levels chosen by the en- struction engineers throughout all multi-tied walls supporting soils of vary-
gineer to take full advantage of the stages of the work is again emphasised ing characteristics and which enables
initial cantilevering abilities of dia- because whenever the problem of quick amendments to be made to the
phragm walls —
difficult, if at all foundations is being studied, especially design based on the soil conditions ex-
possible, when using the trape- in the field of retaining walls, the design posed as the wall is being constructed.
zoidal method. may have to be amended as the work (To be continued)
(rv) It allows the wall penetration to proceeds. The limited number of bore-
be calculated based on a rota- holes which can be put down on any In the second part of this Paper,
tiona! criteria as well as the direct site is generally insufficient to provide a Z. Sliwinski considers wall construction,
summation of horizontal forces complete picture of the ground strata while the third, by G. S. Littlejohn, deals
used in the trapezoidal method. and tie bar positions and forces may with anchor design.

Ground Engineering 17

You might also like