You are on page 1of 2

Well Name PRG-14 Field Pargo Platform / Pad PARGO wells Daily Cost (USD) 7900 Total Cost

atform / Pad PARGO wells Daily Cost (USD) 7900 Total Cost (USD) 94800 Report Date 01/02/2024
BRAZIL Workover # 18 Location Offshore Unit name Perenco red jacking SAP Code BRPAW114 Activity Type Opex WO Report No 12
Daily Workover Report unit
Drilling KB Elev. 15 WO Rig KB Elev. 39.9 Current Completion ESP New Completion ESP
WO Objective POOH ESP + Water Shut Off + RIH ESP
Tubing Hanger Elev. 21.03 Depth Units m Depth Reference MSL

BHA details Tripping / Drilling / Milling / Circulating Data


Run # Objective BHA Description & Workstring Data SOW (klbs) 50 Motor RPM / Unit Flow (round/lpm)
1 POOH ESP + Water Shut Off + RIH ESP Old ESP Baker: 1 discharge 513, 2 pumps 538, 1 intake 538, 2 protector 513, Flow Rate (lpm) PUW (klbs) 60 Motor RPM (rpm)
01 motor 562, sensor 400. FRW (klbs) Surface RPM (rpm)
2 CASING SCRAPING RUN#1 (SCRAPER 7") Drill bit 6", Scraper 7", 01 bit sub 4.3/4, Xo 4.13/16, 150 tbgs 4.5 eue w 120 Torque On Bottom (kft.lbs) Total RPM (rpm)
tbgs 3.5 eue SPP (bar)
Torque Off Bottom (kft.lbs) Min Annular Velocity (ft/min)
Run # Weight below Jar (klbs) Workstring OD. (in)
Well Architecture
1 4.4 4.5
Type OD PPF Grade ID Connection Top (m) Bottom (m)
2 1 7
Tubing 4.5 EUE#12.75 L-80 3.958 EUE -24.32 1646.82
Daily Summary Prod Casing 9.5/8" 43-47 P110 8.681 BT 2755 0
Replaced EA0A valve. Prod Casing 7" 26 lb/ft P110 6 BT 3278 2538
N/D & L/D std pipe w chicksan swivel.
N/D & L/D RT & hydraulic hoses. General Remarks
Operation with ML-3 tugboat.
POOH casing scraper 7" w tbgs 4.5 EUE from 2534 mR/T to 1646 mR/T. Last wo 19/01/2021
Perfs 3092-3096/ 3098-3103/3105.5- 3108.5/3113.6-3120.6/3127-3130 m/rt
Activities at 6:00 larger Dog Leg: 1172mMD 3,22°+1182mMD 3,22°
Max inclination: 2933mMD 18.8°
POOH casing scraper 7" w tbgs 4.5 EUE from 1646 mR/T.
Planned activities for next 24 hrs Old fish:
-Gun-Drop-Sub (0.33 m) + 2 Pipes 2 7/8" EU (17.70 m) + 1 Perforated Pipe 2 7/8" EU (9.67 m) +1 Pipe 2 7/8" EU (9.07 m) + Wet-Connector + Top-Sub (4.19 m) + TCP Cannon
POOH casing scraper 7" w tbgs 4.5 EUE from 1646 mR/T. (7.0 m).Total: 47.96 m.
Operation w SL Expro, run lib 6.125"
POOH :
Operations and time analysis -Clamp broken : 58 pieces
Interval (m) -Broken clamp parts in the well : 94 pieces [33 pieces of 16cm (hatch)/61 pieces of 9cm (ear)].
From To Description Elapsed (hrs) Code -Baker team performing TDR.
Depth Start Depth End Speed (m/hr)
-Damage identified in the ESP cable between tubing 66th-82th-84th-105th;
00:00 00:30 Lunch break. 00:30 LOG_LOG -Short circuit identified in tubing 257 th;
RIH string, tag top of the liner, WOS to pass w circu direct 200 -4 decompression points identified in the power cable between tubing's 258 and 259 th;
bbls of brine 8.6ppg, WOS to pass, drag down 3x w 2klb, 3x w -Short circuit identified in the power cable, near the splice of the MLE cable;
00:30 02:30 2534 2538 2 02:00 N_WellOps -05 stainless steel bandits and tubing
3klb, 3x w 4klb & 3x w 5klb, no success.
-Flow rate 2bbl/min. SITP 30 psi.
RIH string, tag top of the liner, WOS to pass, drag down 3x w Old ESP Baker: 1 discharge 513, 2 pumps 538, 1 intake 538, 2 protector 513, 01 motor 562, sensor 400.
2klb, 3x w 3klb, 3x w 4klb & 3x w 5klb, no success. Note:
In Parallel: -Pumps: Upper and lower pump with free shaft, with out accumulation of materials and with light drag mark;
02:30 06:00 2534 2538 1.14 03:30 N_WellOps -Intake: Free shaft and unobstructed intake area;
-Fabricated 200 bbls of the brine 8.6ppg;
-Performing valve pressure test 2.1/16 x 3kpsi. -Seal superior: Contaminated with water the chambers, free shaft and shaft extension - ok;
-Performing service orders. -Seal inferior: Upper chamber contaminated w water and lower chamber w oil clear;
-Motor: oil clear, free shaft, shaft extension and pothead connection - ok and light drag mark;
Crew change (RED-7-4B > RED-7-4C) & safety -Sensor: Ok;
06:00 07:00 meeting: Spinal maneuver: Risks involved, preventive 01:00 HSE_Safety -MLE and sensor line without damage;
measures and attention during the maneuver. -ESP: 04 stainless steel bandits.
07:00 10:30 Check w Rio operational sequence, meanwhile replaced EA0A 03:30 N_Cpy
valve. Injectivity test I
-Q= 4.0 BPM / P= 13PSI / Vol. 200BBL.
10:30 11:00 N/D & L/D std pipe w chicksan swivel. 00:30 RU/RD_FT_S&C
11:00 12:30 N/D & L/D RT & hydraulic hoses. 01:30 RU/RD_FT_S&C -Top liner 2538 m/rt w scraper, try pass no success (run N°2)
12:30 13:00 Lunch break 00:30 LOG_LOG
New ESP Baker:
13:00 17:30 POOH casing scraper 7" w tbg 3.5 EUE (120tbgs) w 4.5 EUE 2534.73 2266.71 59.56 04:30 TRIP_WS -
(30/149), PUW 88 klb, SOW 70 klb.
17:30 18:00 Deck management, moving loads to clear an escape route.. 00:30 HSE_Safety Safety Activities
Crew change (RED-7-4C > RED-7-4B) & safety Activity Type Daily Total Comment
18:00 19:00 meeting: Spinal maneuver: Risks involved, preventive 01:00 HSE_Safety Tool Box talks / PJSM / JSA / Induction / Training, etc. 2 22 Spinal maneuver: Risks involved, preventive
measures and attention during the maneuver. measures and attention during the maneuver.
19:00 19:30 Operation with ML-3 tugboat: backload metal box bcs 004 00:30 LOG_LOG Accident / Incident / Near Miss / HiPo 0 0
(SPH-02) w 4 platform bags. POST Cards 2 2 11 Open
19:30 00:00 POOH casing scraper 7" w tbg 3.5 EUE & 4.5 EUE, PUW 76 klb, 2266.71 1980.41 63.62 04:30 TRIP_WS Permit to Work 4 38 1WIP + 37PTW
SOW 62 klb.
HSE Information
Next day operations (00:00 to 06:00)
Interval (m) LTI Free days 748
From To Description Elapsed (hrs) Code
Depth Start Depth End Speed (m/hr) 13/01/2022. During POOH, when removing the 15th pipe (5th pipe by the night team) on the zipline, the pipe sleeve
00:00 00:30 Lunch break. 00:30 LOG_LOG Last Incident Details (date, description) bumped into the rig stabilization beam. The rigger positioned himself and placed his hand inside the tube sleeve to pull
the pipe toward the dock, placing his hand within the payload's range. When pulling the pipe, it came down on his finger,
00:30 05:30 POOH casing scraper 7" w tbg 3.5 EUE & 4.5 EUE, PUW 60 klb, 1980.41 1646.82 66.72 05:00 TRIP_WS pressing between the beam and the pipe coupling.
SOW 50 klb.
Last Inspection/ Audit (date, description) Sup Wo audit - 13/01/2024
05:30 06:00 Deck management, 60 pipes 4,5"EUE removed from the pipe 00:30 LOG_LOG
deck. Fuel Data
HPU Type Diesel Unit Selection liters
Daily Consumption 211 Daily Initial Stock 1200
Average Consumption 277.72727272727 Daily Reception 211
Total WO Consumption 3055 Daily Final Stock 1200
BOP Informations
Type Date Comments
BOP Function test 22/01/2024 5 sec blind closing time and annulus BOP 11 sec.
BOP Pressure test 23/01/2024 300psi & 3kpsi for 10' (positive test)
BOP Configuration Blind/shear Ram + BOP 11" 5K + Annular Hydril GK SN1002140 -11" x 5kpsi, packing changed the 13st December 2023 (PRG 24 -
DDR 33).
Latest Safety Drills
Type Date Comment
Kick Drill 31/01/2024 Performed a well closure simulation w team RED-7-4B.
Workover Fluid / Filtration
Type Sea water Filtration
Density (sg) 1.03 Filter Type Cartridge
Free Standing Liquid Level 0 Filter Rating Absolute
Open / Closed Circ System Open Filter Size 0
Solid Control None
Daily Losses 240 Cumulative Losses 2845
Additives
Concentration
Additive Brand Name Consumed Stock Unit
Quantity Unit
POB
Head count
Position Company
Permanent Temporary
WO Supervisor Perenco 2
Mechanic Perenco 1
WO Unit Crew Perenco (Driller) 2
WO Unit Crew Perenco (Derrick Man) 2
WO Unit Crew Braserv (Roughneck +aux plat) 10
WO Unit Crew Engeman (electrician) 1
PERENCO Reps Engeman (Crane Operator) 1
WO Unit Crew Engeman (HSE) 1
PERENCO Reps SPT WO 1
Total 20 1
Day Supervisor Luiz Alberto Night Supervisor Flávio Santos