Professional Documents
Culture Documents
Chapter 13 Management Perspectivies 492-513
Chapter 13 Management Perspectivies 492-513
Pre-Assessment
Operating history indicated that the pipeline had been idle for a
period of four years before it was placed in service. While idle, the
line had been treated with corrosion inhibitors. This situation did not
preclude the use of DG-ICDA because the greatest extent of the
internal corrosion would have occurred during the 20 plus years of
operation prior to taking the line out of service and the three years of
operation after being returned to service. Records indicated that
methanol was occasionally injected when the line was in operation
due to changing flow conditions. The flow of natural gas was in the
same direction throughout the life of the pipeline.
As part of the pre-assessment, samples of internal residue were
collected and analyzed. Solid samples contained black powder (iron
sulfide) corrosion products. Some small amounts of amine and
carboxylate chemical inhibitors were detected, as well as trace
amounts of glycol and methanol
As a result of the pre-assessment, the pipeline segment was divided
into two DG-ICDA regions with the demarcation at roughly the mid
point.
• Start/Stop time
• Number of satellites
• Latitude, longitude and elevation
Critical angles were calculated for each region and the
corresponding pipeline operating conditions were recorded. For
each of the DG-ICDA regions, the results were:
• Region 1 – 10.5° at 28 million cubic feet/day and a pressure of
800 psi.
• Region 2 – 8° at 18 million cubic feet/day and a pressure of 400
psi.
Error limits in measurement of pipe depth and elevation are much
smaller than their impact on the critical angles and, therefore, do not
have a significant impact on the calculation (an 8° critical angle
corresponds to a rise of approximately 14 feet over a distance of 100
feet). Based upon the indirect inspection, five sites that exceeded the
critical angle were selected for direct examination. Three sites were
in DG-ICDA Region 1 (sites DG-ICDA 1, 2, 3) and two sites in
Region 2 (DG-ICDA 4, 5). Control sites were later selected in
conjunction with an in-line inspection and a subsequent ECDA.
Post Assessment
DG-ICDA was shown to be applicable as validated by running a
high resolution, MFL in-line inspection (see below).
The maximum corrosion rate is less than 2 mpy in the presence of
water as calculated by the dry gas model. The controlling factor in
determining the reassessment interval was the external corrosion
rate of 7 mpy, requiring a 9 year interval.
State Miles
Virginia 105
Maryland 69
District of Columbia 20
West Virginia 18
Leesburg
Rockville/Westmore
Dranesville Rockville
Plant
Herndon
Chantilly
Centreville
Gardiner
Ravensworth
Plant
PRESSURE LEGEND:
Bright Red -- Low Pressure (inches w.c.)
Blue -- 20 psig
Brown/Dark Red -- 30 psig White
Purple -- 50 psig
Green -- 55 psig
Plains
Magenta -- WG Transmission pressure
Pre-Assessment
The pipeline segment consists of approximately 8.8 miles within
one HCA. It is 24 inched in diameter, with an MAOP of 240 psi,
installed 50 years ago. Over its life there have been three (3)
replacement offsets. Two of these are 220 feet and 37 feet along
highly traveled streets. The third is 370 feet long, installed in 1970,
with a deep vertical drop to get down to street level from an elevated
freeway.
The ECDA pipeline segment is almost entirely underneath 18-inch
thick, reinforced concrete roads that have been overlaid with
asphalt. The area is congested and highly traveled (see Figure
13.12). There is a good history of cathodic protection of the pipeline
segment. The pipeline segment was divided into four (4) sections
based on positioning of isolation flanges. It was treated as one
ECDA region because of the similar environmental conditions
surrounding the piping. The pipe is approximately 6 feet below soil
surface.
North
DC – Maryland line
Approximate path
of 7 miles
24 in dia
API 5LX-42 ERW
Installed 1955
MAOP 240 psi
2. Data collection
- SCC, MIC testing
- Soil and water sampling
- pH, pipe-to-soil potential and resistivity measurements
3. Assessing coating
- Coating type, condition, adhesion
- Coating removal, testing water pH under coating
6. Prioritization
- Immediate action required
- Scheduled action required
- Suitable for monitoring
Post Assessment
The project demonstrated that ECDA was an effective tool for
assessing pipeline integrity. The definition of the pipeline segment
and the indirect inspection techniques employed were valid.
There were many lessons learned in this project that will be helpful
in future ECDA projects under pavement in congested areas:
• D.C. transit systems cause stray currents that need to be
addressed during an ECDA project.
• Overhead AC transmission lines can cause induced voltages on
the pipeline that may affect survey techniques and/or require
additional filtering for collection of accurate measurements.
• Projects are complicated further when there are two jurisdictions
involved (in this case Washington D.C. and Maryland).
• Crossings of other pipelines (e.g., water, gas distribution) need to
be identified as well as metal jacketed power and communica-
tions cables.
• Street permits and procedures for closing streets need to be thor-
oughly understood and addressed prior to commencement of
field operations.
• The logistics of traffic control and drilling of test holes through
the pavement are a part of the process that needs to be carefully
planned.
• There may be restrictions as to the hours where traffic lanes and
streets can be closed and when pipeline excavations can be
made.
• Provisions need to be made to address abandoned and parked
cars.
• Line location and alignment is critical to the success of the proj-
ect including collection of GPS data to facilitate data integration.
• Excavation and shoring procedures should be documented and
should comply with OSHA requirements.
• The jurisdiction may have procedural requirements for backfill-
ing excavations and handling excavated material. In cases where
the same dirt could not be used to backfill, the excavated mate-