‘THE NATIONAL COMPANY LAW TRIBUNAL
SPECIAL BENCH (COURT NO. 2)
NEW DELHI
Company Petition No. (IB)-521(ND)/2017
UNDER SECTION 9 OF THE INSOLVENCY AND BANKRUPTCY
CODE, 2016
In the matter of:
Sh. Narender Sharma, Applicant
Vs
Vistar Construction Pvt. Ltd. Respondent
Judgment delivered on: (.12,2018
Coram:
MS. INA MALHOTRA HON’BLE MEMBER (JUDICIAL)
S. K. MOHAPATRA HON’BLE MEMBER (TECHNICAL)
For Operational Creditor: Mr, Mukul Dev Sharma &
Mr. H.R. Khan Advocetes
For the Respondent: Ms. Mahjabeen Tawweer &
Mr. Shakti Verma Advocates.ORDER
S.K. Mohaparta, Member
1. Mr. Narender Sharma, claiming as the operational
creditor has filed this application under Section 9 of the
Insolvency and Bankruptcy Code, 2016 (for brevity ‘the
Code} read with Rule 6 of the Insolvency and Bankruptcy
(Application to Adjudicating Authority) Rule, 2016 (for
brevity ‘the Rules) for initiation of Corporate Insolvency
Resolution Process in respect of Respondent Company M/s
Vistar Construction Private Limited, claimed to be the
Corporate Debtor.
2, The Respondent M/s Vistar Construction Private
Limited against whom initiation of Corporate Insolvency
Resolution Process has been prayed for, is a company
incorporated on 09.10.1992 under the provisions of the
Companies Act, 1956 having its registered office at office C-
23, G.K. Enclave-1, New Delhi-110048. Since the registered
office of the respondent corporate debtor is in Delhi, this
‘Tribunal having territorial jurisdiction over the place, is the
Adjudicating Authority in relation to the prayer for initiation
of Corporate Insolvency Resolution Process in respect of
(i8)-s2ninoy2027respondent corporate debtor under sub-section (1) of
Section 60 of the Code.
3. The case of the applicant as stated in the application is
that the applicant had applied for the post of Civil Engineer
in the month of September, 2002 in the respondent
company. On selection appointment letter dated 03.10.2002
was issued to the applicant by the respondent company with
a gross salary of Rs. 1,20,000/- per annum. Later on, the
salary got increased to many folds and the last drawn salary
package of the applicant Operational Creditor was
approximately 27 Lacs.
4. Itis stated in the application that Operational Creditor
was forced to give his resignation on 27.05.2015 and it was
told that the company is not able to give him salary.
Accordingly, applicant gave his resignation letter and got
relieved from his post on 30.05.2015.
5. The Applicant has claimed that a letter of the
respondent company detailing full and final settlement of
applicant’s salary account has been issued by the
respondent Corporate Debtor, according to which the
applicant is entitled to receive Rs. 12,22,518/- as onae
01.06.2015. It is accordingly stated in the application that
as per the full and final settlement letter, Rs. 12,22,518/- is
to be paid by the respondent company to the applicant in
respect of his employment in respondent's company till
30.05.2015.
It is contended that despite various Emails and
telephonic calls, the respondent Corporate Debtor has failed
to pay the aforesaid amount of Rs. 12,22,518/- (Rupees
‘Twelve Lakhs Twenty Two Thousand Five Hundred and
Eighteen Only). It is alleged that the respondent Corporate
Debtor with mala fide intention has retained the lawful dues
of the applicant.
‘Thereafter, a legal notice dated 04.04.2017 was
issued by the applicant Operational Creditor through its
counsel to the respondent for payment of the outstanding
operational debt. In addition, a demand notice under
Section 8 of Insolvency and Bankruptcy Code, 2016 was
sent on 21.07.2017 to the respondent Corporate Debtor and
its Directors for payment of the unpaid operational debt of
Rs, 12,22,518/- along with interest at the rate of 18% per
annum.8. Applicant has submitted that the respondent company
has replied to the legal notice and demand notice issued
under Section 8 on 25.07.2017 and 27.07.2017 respectively
with false and frivolous grounds in order to avoid the
payment of legal dues of the applicant.
Consequently on 29.08.2017 applicant tad filed an
application under section 9 of the Insclvency and
Bankruptcy code, 2016 read with rule 6 of the Insolvency
and Bankruptey (Application to Adjudicating Authority)
Rules, 2016. However due to some technical defect, the
application was withdrawn and liberty to file fresh petition
was allowed.
10. Subsequently on 05.10.2017 a fresh demand notice
under Section 8 of the Code was sent by the operational
creditor to the corporate debtor and its directors for the
payment of unpaid operational debt of Rs. 12,22,518/-
(Twelve lakhs twenty two thousand five hundreds and
eighteen only) along with interest @ 18% per annum.
11. In response to the demand notice dated 05.10.2017
corporate debtor replied on 16.10.2017 in which it is alleged
that false and frivolous grounds were taken to avoid thepayment of legal dues of operational Creditor. It is stated
that the company has suffered loss of Rupees 15,00,000/-
lacs due to default committed by applicant operational
creditor. It is further stated that as per the employment
contract one-month notice was to be given before the
resignation, which has not been done by the operational
creditor causing huge loss to the company.
12, In this regard applicant has contended that the
resignation was given because operational creditor was
compelled to leave the job by the company. It is further
argued that no such objection was ever taken by the
corporate debtor at the time of resignation or at any point of
time within last 2 years. Applicant has denied that no
belongings of the company has been kept by him, nor even
any written communication was ever made by the company.
It is alleged that the said objection is nothing but a lame
excuse given by the corporate debtor to avoid the payment
of legally recoverable dues.
13. In connection with the civil suit, applicant has
submitted that the corporate debtor maliciously filed the
civil suit before the civil judge to create a pending disputea
14,
15,
16,
between the parties. However, it is argued that civil suit was
filed after the filing of the previous insolvency application,
‘The operational creditor has relied on the final
settlement statement, in which it has been clearly stated that
the amount of Rs. 12,22,518/- was full and final amount held
with the company and also form 16 part A dated 14.05.2015
and part B dated 26.05.2015 and form 12BA which shows
the tax deduction and total of income of operational creditor.
It has been contended that as no payment was made
within 10 days of the demand notice sent under Section 8 of
the Code and as there is no pending dispute in respect of the
“unpaid operational debt the application filed under Section 9
should be admitted by initiating Corporate Insolvency
Resolution Process against the Corporate Debto-.
Respondent Corporate Debtor has filed its reply on
06.12.2017 mainly with the contention that the applicant's
performance at the duty was not satisfactory and respondent
had issued timely warnings to applicant to improve his
performance efficiency. It is alleged that instead of improving
his skill and experience in the work, Applicant vide its letter
dated 27.05.2015 had chosen to submit his resignation fromae
17.
18,
his employment with respondent company with effect from
27.08.2015 and requested respondent to relieve him from his
employment immediately. It is stated that the submission of
the said resignation letter of the Applicant was not in
compliance with the terms of the employment contract with
respondent, as he had to give one month written prior notice
before leaving his employment with respondent.
It is submitted that the sudden and immediate
resignation of applicant and as he had stopped coming to the
office immediately after that had caused great uncertainty
and effected the execution of the work in the project. The said
project was to be completed within a deadline as committed
to the Client / Costumers / Allottees of the project. It is
alleged that it has caused further financial loss te Respondent
as the applicant failed to formally hand over the details of
work executed by him.
It is further stated that respondent did not handover all
the requisite documents, including working drawings,
schedules, building plans, etc. relating to the execution of the
project in the site and consequently, the new engineer who
hhad replaced the applicant was not able to execute the worka
19,
20.
with the pace which was supposed to be done for a period of
three months. Accordingly, Respondent had to incur a
financial loss of INR 15,00,000/- (appx.) due to the willful
negligence and default committed on the part of the Applicant
for the delay in execution of the project.
It is also the case of respondent that there is an
existence of dispute between the parties with regard to the
payment, even prior to the issuance of the Secticn 8 notice of
the Code. The factum of the dispute was also brought to the
knowledge of the Operational Creditor/Applican: in the reply
to the notice under Section 8 of the Code. It is submitted that
after the Applicant resigned from the office, without giving
prior notice and handing over requisite documents, the
Respondent has suffered financial loss and many projects
were delayed.
Itis further submitted that the respondent had sent two
egal notices for the recovery of Rs.15,00,000/- for the loss
occurred to the Respondent, as applicant herein has left the
organization without giving prior notice and handing over
requisite documents.ae
21.
22.
23.
It is further submitted that the Respondent has filed a
civil suit for recovery before Civil Judge Junior Division,
Gautambudh Nagar, bearing Suit No.395 of 2017 titled as
Vistar Construction Private Limited Vs. Narender Sharma,
wherein learned Civil Judge issued notice on 16.10.2017. It
is contended that suit for recovery is a suit governed by
Article 113 of the Limitation Act, 1963 as per which the suit
has to be filed within three years of arising of the cause of
action. The cause of action arose on the date of the
resignation of the applicant, which is very much within the
limitation and therefore the claim of the respondent is not
barred by limitation, It is submitted that the said suit is still
sub-judice before the learned Civil Judge.
‘The respondent has also denied the genuineness of the
full and final settlement letter and the TDS certificate relied
upon by the Applicant as they don’t bear the signature and
seal of the company.
It is submitted that the Applicant in its application has
denied that no document, working drawing, schedules,
building plans, etc. relating to the execution of the projects at
the site were kept with him and no written communication
().s21)Noy2017oe
24,
25.
26.
was ever made by the respondent. It is submitted in this
regard that being a senior civil engineer all che working
drawings, schedules, building plans, etc. relating to the
execution of the project at the site were kept with the
applicant and the respondent kept on asking to hand over the
same verbally which was ignored by the applicant.
Heard the learned counsels for the parties and perused
the case papers.
‘The main contention of the applicant is that the notice
under Section 8 of the Code was issued to the respondent
company first time on 21.07.2017 to which respondent has
replied only on 27.07.2017. It is argued that respondent
‘company cannot dispute the unpaid amount for the first time
in his response to the demand notice. It is accordingly
contended that no dispute was pre-existing and therefore the
application under Section 9 should be allowed.
It is pertinent to mention here that applicant had earlier
filed an application under Section 9, which was numbered as
IB No. 321(ND) /2017. Prior to filing of the said application,
notice under Section 8 was issued on 21.07.2017. However,
as the notice was addressed to ‘8C DEVELOPERS’ which is
n
Wo)s2xinoy2017a different entity from that of the respondent company and
as prior Section 8 notice was not issued to the respondent
company, applicant prayed for withdrawal of the application,
Accordingly, IB No. 321(ND)/2017 was dismissed as
withdrawn on 18.09.2017 with liberty to file fresh petition.
27. Pursuant to the liberty granted the present IB No,
521(ND)2017 has been filed afresh on the same cause of
action.
28, The following relevant date wise developments as
detailed in the case records are reproduced below for proper
appreciation of the matter.
The applicant submitted his
27.05.2015 | resignation.
04.04.2017 | Legal notice was given by applicant for
salary dues.
Notice under Section 8 of the Code was
21.07.2017 | issued on behalf of the applicant
Reply of respondent to the legal notice,
25.05.2017
27.07.2017 | Reply of respondent to the notice issued
under Section 8 of the Code.
2
8) saxtwovy201729.08.2017 | Initial Section 9 application filed in the |
matter.
18.09.2017 | Dismissed as withdrawn with Hberty to
file fresh petition
20.09.2017 |Notice issued by respendent for
recovery.
25.09.2017 | Notice issued by respondent for
recovery.
Fresh notice under Section & was issued
05.10.2017
before filing the present petition.
Reply to Section 8 notice by respondent
16.10.2017
Notice issued in Civil Suit No.395 of
16.10.2017
2017 for recovery.
16.11.2017 | Present application filed.
35. There is no dispute that respondent company has
replied within 10 days to both the notices respectively issued.
under Section 8 by raising interalia following disputes.
ae
3
(08)s2n(no/2017ae
(a) The applicant resigned suomoto and was not
forced to resign. Only oral warning was issued to the
applicant to improve his efficiency.
(b) Sudden resignation without one month written
prior notice was in violation of the terms of ‘employment
contract’
(c) After resignation as the applicant has stopped
coming to office immediately thereafter, had caused great
uncertainty and affected the execution of the work in the
project which was to be completed within a deacline causing
financial loss to respondent company.
(a) Applicant has failed to formally hand over
requisite documents including working drawings, schedules,
building plans ete. relating to the execution of the project in
the site and consequently, the new engineer who had
replaced applicant was not able to execute the work with that
pace which was supposed to be done for a period of three
months,
(c] Respondent had to incur a financial loss of INR
15,00,000/-(appx.) due to the willful negligence and default
(i3}s211Noy2017ae
committed on the part of Applicant for the delay in execution
of the project.
(0 Two legal notices were sent to the applicant on 20
and 25! September, 2017 for recovery of aforesaid amount.
36. It is seen that various disputes raised relates back to
the date of resignation. There is a dispute as to whether it is,
a suomoto resignation or a forced one. Issues have been
raised on the breach of ‘employment contract’; on the ground
that required advance notice was not given before stopping to
attend office. In addition, there has been a counter claim of
loss, Such plausible contentions require further investigation
and the dispute relates to the date of resignation followed by
its effect.
37. At this stage it is immaterial to consider who will
succeed. Besides this forum, in the present proceeding, is not
supposed to examine the merit of the disputed claims made
by the parties.
38. Respondent has also filed a civil suit for recovery before
Civil Judge Junior Division, Gautambudh Nagar, bearing
Suit No.395 of 2017 titled as Vistar Construction Private
Limited Vs. Narender Sharma, which is pending adjudication.
A claimant can lodge recovery suit even on the last day of the
(us}s2ainoy2017three years limitation period. Respondent had an offsetting
claim and suit has been filed within the
tation period as
per the provisions of law. Therefore until the outcome of the
pending recovery case, the claim / ‘counter claim of loss’
remains disputed.
39. Existence of dispute largely depends on the facts and
circumstances of each case. In the factual background of this
case ‘existence of real dispute’ cannot be totally overruled.
40. Existence of an undisputed operational debt is sine qua
non for initiating CIRP under Section 9 of the Code. The Code
is not intended to be substitute to a recovery forum, The
moment there is existence of a dispute, the corporate debtor
gets out of the clutches of the Code.
41. The expression “existence” has been understood as
follows: “The Shorter Oxford English Dictionary gives the
following meaning of the word “existence”:
a. Reality, as opp to appearance.
b. The fact or state of existing; actual possession of being.
Continued being as a living creature, life, esp. under
adverse conditions.
wy
16
(18)-521{Noy2017ae
42.
43,
Something that exists; an entity, a being, All that exists.
(Page 894 - Oxford English Dictionary)’,
Under Section 5(6) of the Code "dispute" includes a suit
or arbitration proceedings relating to —
a. the existence of the amount of debt;
b. the quality of goods or service; or
c. the breach of a representation or warranty.
Since the word used, in the definition of "dispute", is
“includes” the dispute can be on any ground and has a wide
meaning. Adjudicating Authority is only to see whether there
is a plausible contention of dispute which requires further
investigation. Any dispute can be raised. Adjudicating
authority is not to see the adequacy of dispute. Dispute must
be existing and must not be vague. In the present case
dispute on breach of terms of employment has been raised.
‘There is also a counter claim. Besides a suit has been filed
within the limitation period and is pending adjudication in a
court of law. In the facts it can be said that dispute is not
only existing but also is continuing. The fact of “existence of
dispute” has been informed within the stipulated period in
the replies sent under section 8 (2) of the Code,
2
uspsaxgnoy/2017om
44, The relevant sub-section 5 of Section 9 of the Code runs
as under:
“Section 9 (5) The Adjudicating Authority shall,
within fourteen days of the receipt of the application under
‘sub-section (2), by an order-
w
(ii)
(0)-s2n(noy2017
Admit the application and communicate such decision
to the operational creditor and the corporate debtor if-
(a)
(o)
(e)
(d) No notice of dispute has been received by the
operational creditor or ..
Reject the application and communicate such
decision to the operational creditor and the corporate
debtor, if
(a.
0...
o
8(a) Notice of dispute has been received by the
operational creditor or there is a recerd of dispute
in the information utility; or
(Josen®
(Emphasis given }
45. In the present case notice under Section 8 was duly
replied within the period prescribed by bringing to the notice
of the operational creditor the existence of dispate. There is
substance and plausible contention in the replies and notices
of the respondent, which necessitates investigation. In fact,
the claim of loss and the prayer for its recovery are sub judice
in a court of law.
46. The provisions of Section 9 (5) (ii) (d) of the Code clearly
mandates that Adjudicating Authority shall reject the
application when notice of dispute has been received by the
applicant operational creditor.
47. In the line of aforesaid provisions of the Code, Hon'ble
Supreme Court has also held that the moment there is
existence of a dispute the operational creditor gets out of the
clutches of the Code,
Ze
»
ia}-saainov/201748. For the reasons stated above the application fails and
therefore the same is rejected.
49. It is made clear that any observations made in this order
shall not be construed as an expression of opinion on the
merit of the controversy and the right of the applicant before
any other forum shall not be prejudiced on account of
dismissal of instant application.
50. Let the copy of the order be communicated to the parties
immediately in accordance with Section 9 (5) (i) of the Code.
=. = Cf
(S. K, Mohapatza) (Ina Mathotra)
Member Technical Member Judicial
20
ie)s2xinoV2017