You are on page 1of 13

Pekerjaan :

PEMANGUNAN RUMAH TINGGAL

LOKASI :

JL. MALIK SIRULLAH KEL. BUKIT WOLIO INDAH


KECAMATAN WOLIO KOTA BAUBAU

PEMOHON

SITI SARSINAH, S.Sos


REKAPITULASI BIAYA

PEMBANGUNAN : PEMBANGUNAN RUMAH TINGGAL


ATAS NAMA/PEMILIK : SITI SARSINAH, S.Sos
LOKASI : JL. MALIK SIRULLAH KEL. BUKIT WOLIO INDAH KEC. WOLIO
LUAS BANGUNAN : LANTAI I = 97.5 M2.
LANTAI I = 97.5 M2.

TOTAL HARGA
No. URAIAN PEKERJAAN
(Rp.)
1 2 3

I PEKERJAAN PERSIAPAN 1,150,000.00


II PEK. TANAH DAN PASIR 5,899,207.65
III PEK. PASANGAN DAN BETON 215,816,974.77
IV PEK. KUSEN, PINTU/JENDELA 25,157,814.00
V PEK. RANGKA ATAP DAN ATAP 16,168,309.47
VI PEK. ALAT - ALAT GANTUNG 4,371,750.00
VII PEK. SANITASI 4,996,860.00
VIII PEK. MENGECAT DAN FINISHING 6,439,396.64
REAL COST 280,000,312.53
DIBULATKAN 280,000,000.00

Terbilang : Dua Ratus Delapan Puluh Juta Rupiah

Baubau, Maret 2023

Pemohon : Dibuat Oleh :


Perencana

SITI SARSINAH, S.Sos KRESNA PUTRA M


RENCANA ANGGARAN BIAYA

PEMBANGUNAN : PEMBANGUNAN RUMAH TINGGAL


ATAS NAMA/PEMILIK : SITI SARSINAH, S.Sos
LOKASI : JL. MALIK SIRULLAH KEL. BUKIT WOLIO INDAH KEC. WOLIO
LUAS BANGUNAN : LANTAI I = 97.5 M2.
LANTAI I = 97.5 M2.

HARGA SAT. JUMLAH HARGA


NO. URAIAN PEKERJAAN SAT VOLUME
( Rp. ) ( Rp. )
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi (Land Clearing) Ls 1.00 150,000.00 150,000.00
2 Pemasangan Bowplank Ls 1.00 500,000.00 500,000.00
3 Penyediaan Air Kerja Ls 1.00 500,000.00 500,000.00
JUMLAH 1,150,000.00
II PEK. TANAH DAN PASIR
1 Galian Tanah Pondasi M3 20.84 30,000.00 625,095.00
2 Urugan Tanah Kembali M3 5.21 14,400.00 75,011.40
3 Timbunan Tanah Bawah Lantai M3 68.64 37,500.00 2,573,812.50
4 Urugan Pasir Bawah Lantai M3 6.86 382,500.00 2,625,288.75
JUMLAH 5,899,207.65
III PEK. PASANGAN DAN BETON
1 Pasangan Pondasi Batu Gunung 1 : 3 M3 26.12 709,100.00 18,521,692.00
2 Pasangan Batubata merah M2 252.56 102,920.00 25,993,475.20
3 Rabat Lantai 1 : 3 : 5 M3 0.49 933,500.00 454,614.50
4 Pas. Sloof 20 x 20 Cm, 1 : 2 : 3 M3 2.43 3,983,340.00 9,681,109.54
5 Pek. Kolom Praktis 15 x 15 Cm, 1 : 2 : 3 M1 63.65 57,085.00 3,633,460.25
6 Pek. Kolom Utama 15 x 20 Cm, 1 : 2 : 3 M3 4.98 4,855,090.00 24,178,348.20
7 Pek. Ring Balok 15 x 20 cm 1 : 2 : 3 M3 2.18 4,401,075.00 9,609,307.16
8 Pek. Balok Utama 15 x 35 cm 1 : 2 : 3 M3 3.52 4,083,340.00 14,363,148.45
9 Pek. Balok 10 x 35 cm 1 : 2 : 3 M3 0.42 4,083,340.00 1,707,856.96
10 Pek. Balok Utama 15 x 20 plat atap cm 1 : 2 : 3 M3 0.60 4,083,340.00 2,450,004.00
11 Pek. Beton Plat Atap, 1 : 2 : 3 M3 3.76 4,401,075.00 16,526,036.63
12 Pek. Beton Plat lantai II, 1 : 2 : 3 M3 12.74 4,401,075.00 56,069,695.50
13 Pek. Plesteran Dinding 1 : 5 M2 505.12 41,430.00 20,927,121.60
14 Pekerjaan Acian Tembok M2 505.12 23,165.00 11,701,104.80
JUMLAH 215,816,974.77
IV PEK. KUSEN, PINTU/JENDELA
1 Pek. Kusen Pintu/Jendela Lubang 35.00 300,000.00 10,500,000.00
2 Pekerjaan Daun Pintu Panil Jati/Cendana Bh 18.00 500,000.00 9,000,000.00
3 Pekerjaan Daun Pintu Alumunium Km/Wc Bh 6.00 450,000.00 2,700,000.00
4 Pekerjaan Bingkai Jendela Kaca 5 mm Bh 12.00 200,000.00 2,400,000.00
5 Pekerjaan Kaca 5 mm M2 7.44 74,975.00 557,814.00
JUMLAH 25,157,814.00
V PEK. RANGKA ATAP DAN ATAP
1 Pekerjaan Kuda-Kuda Baja Ringan M2 85.47 135,329.41 11,566,604.67
2 Pas. Atap Alumunium Spandek M2 85.47 53,840.00 4,601,704.80
JUMLAH 16,168,309.47
VI PEK. ALAT - ALAT GANTUNG
1 Pasangan Kunci Tanam 2 Slag Bh 18.00 121,650.00 2,189,700.00
2 Pasangan Engsel Pintu Kuningan Bh 54.00 18,475.00 997,650.00
3 Pasangan Grendel Pintu Bh 18.00 22,300.00 401,400.00
4 Pasangan Engsel Jendela Bh 24.00 18,475.00 443,400.00
5 Pasangan Grendel Jendela Bh 12.00 22,300.00 267,600.00
6 Pasangan Kait Angin Bh 24.00 3,000.00 72,000.00
JUMLAH 4,371,750.00
1 2 3 4 5 6
VII PEK. SANITASI
1 Pas. Kloset Jongkok Bh 6.00 305,500.00 1,833,000.00
2 Pas. Kran Air dia. 1/2 " Bh 12.00 13,655.00 163,860.00
3 Pas. Septictank Bh 1.00 3,000,000.00 3,000,000.00
JUMLAH 4,996,860.00
VIII PEK. MENGECAT DAN FINISHING
1 Pekerjaan Cat Tembok M2 505.12 9,147.00 4,620,332.64
2 Pekerjaan Cat Kilap Kayu M2 63.40 23,960.00 1,519,064.00
3 Pekerjaan Angker, Baut, Begel Ls 1.00 200,000.00 200,000.00
4 Pekerjaan Pembersihan Bekas Pekerjaan Ls 1.00 100,000.00 100,000.00
JUMLAH 6,439,396.64

Baubau, Maret 2023

Pemohon : Dibuat Oleh :


Perencana

SITI SARSINAH, S.Sos KRESNA PUTRA M


DAFTAR ANALISA

PEMBANGUNAN : PEMBANGUNAN RUMAH TINGGAL


ATAS NAMA/PEMILIK : SITI SARSINAH, S.Sos
LOKASI : JL. MALIK SIRULLAH KEL. BUKIT WOLIO INDAH KEC. WOLIO

1 2.6.1 1 M 3 GALIAN TANAH BIASA KEDALAMAN s/d 1 M


0.4000 Pekerja 75,000.00 30,000.00
0.0400 Mandor - -
Total 30,000.00
2 2.6.9 1 M 3 URUGAN KEMBALI
0.1920 Pekerja 75,000.00 14,400.00
0.0190 Mandor - -
Total 14,400.00
3 2.6.10 1 M 3 PEMADATAN TANAH
0.5000 Pekerja 75,000.00 37,500.00
0.0500 Mandor - -
Total 37,500.00
4 2.6.11 1 M 3 URUGAN PASIR
0.3000 Pekerja 75,000.00 22,500.00
0.0100 Mandor - -
1.2000 M3 Pasir urug 300,000.00 360,000.00
Total 382,500.00
5 3.6.6 1 M 3 PASANG PONDASI BATU GUNUNG 1 Pc : 5 Ps
0.6000 Tukang Batu 80,000.00 48,000.00
0.0600 Kepala Tukang 90,000.00 5,400.00
1.5000 Pekerja 75,000.00 112,500.00
0.0750 Mandor - -
1.1000 M3 Batu Gunung 160,000.00 176,000.00
2.7200 Zak Cement Portland 50 Kg 75,000.00 204,000.00
0.5440 M3 Pasir Pasang 300,000.00 163,200.00
Total 709,100.00
6 3.6.14 1 M 3 PASANG PONDASI BATU KOSONG
0.3900 Tukang Batu 80,000.00 31,200.00
0.0390 Kepala Tukang 90,000.00 3,510.00
0.7800 Pekerja 75,000.00 58,500.00
0.0390 Mandor - -
1.2000 M3 Batu Gunung 160,000.00 192,000.00
0.3000 M3 Pasir Urug 300,000.00 90,000.00
Total 375,210.00
7 4.6.12 1 M 2 PASANGAN BATA MERAH 1/2 BATU 1Pc : 5Ps
0.1000 Tukang Batu 80,000.00 8,000.00
0.0100 Kepala Tukang 90,000.00 900.00
0.3200 Pekerja 75,000.00 24,000.00
0.0150 Mandor - -
70.0000 Buah Batu Merah 5/11/22 Cm 600.00 42,000.00
0.1936 Zak Cement Portland 50 Kg 75,000.00 14,520.00
0.0450 M3 Pasir Pasang 300,000.00 13,500.00
Total 102,920.00
8 5.6.3 1 M 2 PLESTERAN 1Pc : 3Ps TEBAL 15 MM
0.1500 Tukang Batu 80,000.00 12,000.00
0.0150 Kepala Tukang 90,000.00 1,350.00
0.2000 Pekerja 75,000.00 15,000.00
0.0100 Mandor - -
0.1296 Zak Cement Portland 50 Kg 75,000.00 9,720.00
0.0190 M3 Pasir Pasang 300,000.00 5,700.00
Total 43,770.00

9 6.6.1 1 M 3 PASANG KUSEN PINTU DAN JENDELA KAYU JATI


20.0000 Tukang Kayu 80,000.00 1,600,000.00
2.0000 Kepala Tukang 90,000.00 180,000.00
6.0000 Pekerja 75,000.00 450,000.00
0.3000 Mandor - -
1.1000 M3 Kayu Jati balok 5/12 3,500,000.00 3,850,000.00
Total 6,080,000.00
10 6.6.7 1 M 2 PASANG PINTU PANIL KAYU JATI
2.5000 Tukang Kayu 80,000.00 200,000.00
0.2500 Kepala Tukang 90,000.00 22,500.00
1.0000 Pekerja 75,000.00 75,000.00
0.0500 Mandor - -
0.0400 M3 Papan Jati 3,600,000.00 144,000.00
Total 441,500.00

11 6.6.9 1 M ² PASANG BINGKAI JENDELA KACA KAYU KLAS I


2.0000 Tukang Kayu 80,000.00 160,000.00
0.2000 Kepala Tukang 90,000.00 18,000.00
0.8000 Pekerja 75,000.00 60,000.00
0.0400 Mandor - -
0.0350 M3 Kayu Klas I, Papan 3,600,000.00 126,000.00
Total 364,000.00
12 4.2.1.22 Pes. 1 m2 atap pelana rangka atap baja ringan (canal dingin) profil c75
0.7340 Tukang Besi 80,000.00 58,720.00
0.0730 Kepala Tukang 90,000.00 6,570.00
0.7340 Pekerja 75,000.00 55,050.00
0.0370 Mandor - -
0.8730 Btg Baja Ringan Canal dingin C-75.75 17,000.00 14,841.00
0.1000 Peralatan 1,484.10 148.41
Total 135,329.41

13 6.6.28 1 M 3 PASANG KONSTRUKSI KUDA-KUDA KAYU KELAS II


12.0000 Tukang Kayu 80,000.00 960,000.00
1.2000 Kepala Tukang 90,000.00 108,000.00
4.0000 Pekerja 75,000.00 300,000.00
0.2000 Mandor - -
1.1000 M3 Kayu Balok 6/12 2,750,000.00 3,025,000.00
15.0000 Kg. Besi Strip 9,500.00 142,500.00
0.8000 Kg Paku Campur 12,000.00 9,600.00
5.0000 Buah Baut 5,000.00 25,000.00
Total 4,570,100.00
14 6.6.9 1 M 3 PASANG GORDING 6/12 KAYU KELAPI KLAS II
0.3000 Tukang Kayu 80,000.00 24,000.00
0.0300 Kepala Tukang 90,000.00 2,700.00
0.2000 Pekerja 75,000.00 15,000.00
0.0100 Mandor - -
1.1000 M3 Kayu Balok 6/12 2,750,000.00 3,025,000.00
0.5000 Kg Paku Campur 12,000.00 6,000.00
Total 3,072,700.00
15 6.6.39 1 M 2 PASANG RANGKA PLAFOND hollow 4 X 4 (60x60) Cm
0.2500 Tukang Kayu 80,000.00 20,000.00
0.0250 Kepala Tukang 90,000.00 2,250.00
0.1500 Pekerja 75,000.00 11,250.00
0.0750 Mandor - -
6.0000 Rangka Metal Hollow 40.40.2 MM 6,000.00 36,000.00
100% x Rgk Assesories (Perkuatan, Las Dll) 36,000.00 36,000.00
Total 105,500.00
16 6.6.52 1 M' PASANG LISPLANK UKURAN 2 X 2/20 CM
0.1000 Tukang Kayu 80,000.00 8,000.00
0.0100 Kepala Tukang 90,000.00 900.00
0.1000 Pekerja 75,000.00 7,500.00
0.0500 Mandor - -
0.0086 M3 Papan 2/20 2,750,000.00 23,650.00
0.0600 Kg Paku Campur 36,000.00 2,160.00
Total 42,210.00

17 8.6.39 1 M' PASANG ATAP NOK SENG


0.0700 Tukang Kayu 80,000.00 5,600.00
0.0080 Kepala Tukang 90,000.00 720.00
0.1500 Pekerja 75,000.00 11,250.00
0.0060 Mandor - -
0.3000 Lbr Seng Plat 35,000.00 10,500.00
0.0400 Kg Paku Seng 15,000.00 600.00
Total 28,670.00
18 6.6.60 1 M' PASANG LIST PLAFOND KAYU PROFIL
0.0210 Tukang Kayu 80,000.00 1,680.00
0.0020 Kepala Tukang 90,000.00 180.00
0.0210 Pekerja 75,000.00 1,575.00
0.0010 Mandor - -
0.0100 Paku 12,000.00 120.00
1.0500 M' List Plafond 4,000.00 4,200.00
Total 7,755.00
19 6.6.1 1 M 2 MEMBUAT FLOOR T = 7 CM
0.1350 Tukang Batu 80,000.00 10,800.00
0.0135 Kepala Tukang 90,000.00 1,215.00
0.7200 Pekerja 75,000.00 54,000.00
0.3600 Mandor - -
0.3640 Zak Cement Portland 50 Kg 75,000.00 27,300.00
0.0440 M3 Pasir Pasang 300,000.00 13,200.00
Total 106,515.00
20 7.6.1 1 M 3 MEMBUAT BETON TUMBUK 1Pc : 3Ps : 5Kr
0.2500 Tukang Batu 80,000.00 20,000.00
0.0250 Kepala Tukang 90,000.00 2,250.00
1.6500 Pekerja 75,000.00 123,750.00
0.0800 Mandor - -
4.3600 Zak Cement Portland 50 Kg 75,000.00 327,000.00
0.5200 M3 Pasir Beton 300,000.00 156,000.00
0.8700 M3 Kerikil 350,000.00 304,500.00
Total 933,500.00
21 7.6.38 1 M 3 MEMBUAT PONDASI BETON BERTULANG (200 Kg Besi + Bekisting)
0.3500 Tukang Batu 80,000.00 28,000.00
1.0400 Tukang Kayu 80,000.00 83,200.00
1.0500 Tukang Besi 80,000.00 84,000.00
0.2450 Kepala Tukang 90,000.00 22,050.00
3.9000 Pekerja 75,000.00 292,500.00
0.1650 Mandor - -
0.2000 M3 Kayu Bekisting 1,700,000.00 340,000.00
1.5000 Kg Paku Campur 12,000.00 18,000.00
200.0000 Kg Besi Beton 9,500.00 1,900,000.00
3.0000 Kg Kawat Beton 9,500.00 28,500.00
6.4600 Zak Cement Portland 50 Kg 75,000.00 484,500.00
0.5200 M3 Pasir Beton 300,000.00 156,000.00
0.7800 M3 Kerikil 350,000.00 273,000.00
Total 3,709,750.00
22 7.6.39 1 M 3 MEMBUAT SLOOF BETON 1Pc : 2Ps : 3Kr
0.3500 Tukang Batu 80,000.00 28,000.00
1.5600 Tukang Kayu 80,000.00 124,800.00
1.4000 Tukang Besi 80,000.00 112,000.00
0.3310 Kepala Tukang 90,000.00 29,790.00
4.8500 Pekerja 75,000.00 363,750.00
0.1700 Mandor - -
0.2700 M3 Kayu Bekisting 1,700,000.00 459,000.00
2.0000 Kg Paku Campur 12,000.00 24,000.00
200.0000 Kg Besi Beton 9,500.00 1,900,000.00
3.0000 Kg Kawat Beton 9,500.00 28,500.00
6.4600 Zak Cement Portland 50 Kg 75,000.00 484,500.00
0.5200 M3 Pasir Beton 300,000.00 156,000.00
0.7800 M3 Kerikil 350,000.00 273,000.00
Total 3,983,340.00
23 7.6.40 1 M 3 KOLOM BETON BERTULANG
0.3500 Tukang Batu 80,000.00 28,000.00
1.5600 Tukang Kayu 80,000.00 124,800.00
1.4000 Tukang Besi 80,000.00 112,000.00
0.3310 Kepala Tukang 90,000.00 29,790.00
4.8500 Pekerja 75,000.00 363,750.00
0.1700 Mandor - -
0.4000 M3 Kayu Bekisting 1,700,000.00 680,000.00
4.0000 Kg Paku Campur 12,000.00 48,000.00
200.0000 Kg Besi Beton 9,500.00 1,900,000.00
4.5000 Kg Kawat Beton 9,500.00 42,750.00
6.4600 Zak Cement Portland 50 Kg 75,000.00 484,500.00
0.5200 M3 Pasir Beton 300,000.00 156,000.00
0.7800 M3 Kerikil 350,000.00 273,000.00
0.1500 M3 Kayu Balok Klas II 2,750,000.00 412,500.00
20.0000 Btg Dolken (bekesting) 10,000.00 200,000.00
Total 4,855,090.00
24 7.6.45 1 M MEMBUAT KOLOM PRAKTIS BETON 11/11 1Pc : 2Ps : 3Kr
0.0200 Tukang Batu 80,000.00 1,600.00
0.0200 Tukang Kayu 80,000.00 1,600.00
0.0200 Tukang Besi 80,000.00 1,600.00
0.0060 Kepala Tukang 90,000.00 540.00
0.0600 Pekerja 75,000.00 4,500.00
0.0030 Mandor - -
0.0020 M3 Kayu Bekisting 1,700,000.00 3,400.00
0.0100 Kg Paku Campur 12,000.00 120.00
3.0000 Kg Besi Beton 9,500.00 28,500.00
0.4500 Kg Kawat Beton 9,500.00 4,275.00
0.0800 Zak Cement Portland 50 Kg 75,000.00 6,000.00
0.0060 M3 Pasir Beton 300,000.00 1,800.00
0.0090 M3 Kerikil 350,000.00 3,150.00
57,085.00
25 7.6.42 1 M 3 MEMBUAT BALOK BETON 1Pc : 2Ps : 3Kr (150 Kg Besi + Bekisting)
0.3500 Tukang Batu 80,000.00 28,000.00
2.8000 Tukang Kayu 80,000.00 224,000.00
1.0500 Tukang Besi 80,000.00 84,000.00
0.4200 Kepala Tukang 90,000.00 37,800.00
5.8000 Pekerja 75,000.00 435,000.00
0.1850 Mandor - -
0.3200 M3 Papan Bekisting 1,700,000.00 544,000.00
3.2000 Kg Paku Campur 12,000.00 38,400.00
150.0000 Kg Besi Beton 9,500.00 1,425,000.00
2.2500 Kg Kawat Beton 9,500.00 21,375.00
6.4600 Zak Portland Cement 50 Kg 75,000.00 484,500.00
0.5200 M3 Pasir Beton 300,000.00 156,000.00
0.7800 M3 Kerikil 350,000.00 273,000.00
0.1200 Kayu Balok Klas II 2,750,000.00 330,000.00
32.0000 Btg Dolken Dia 8 Cm/4m 10,000.00 320,000.00
Total 4,401,075.00
26 8.6.38 1 M 2 PASANG ATAP Alumunium Spandek
0.0600 Tukang Kayu 80,000.00 4,800.00
0.0060 Kepala Tukang 90,000.00 540.00
0.1200 Pekerja 75,000.00 9,000.00
0.0060 Mandor - -
0.7000 Lbr Alumunium Spandek 56,000.00 39,200.00
0.0200 Kg Paku Seng 15,000.00 300.00
Total 53,840.00
27 9.6.13 1 M 2 PASANG PLAFOND Gypsum
0.1000 Tukang Kayu 80,000.00 8,000.00
0.0100 Kepala Tukang 90,000.00 900.00
0.0700 Pekerja 75,000.00 5,250.00
0.0035 Mandor - -
0.3750 Lembar Gypsum 150,000.00 56,250.00
0.0300 Kg Paku/Baut 15,000.00 450.00
Total 70,850.00
28 10.6.2 1 BUAH PASANG KLOSED JONGKOK STANDARD
1.5000 Tukang Batu 80,000.00 120,000.00
0.1500 Kepala Tukang 90,000.00 13,500.00
1.0000 Pekerja 75,000.00 75,000.00
0.1600 Mandor - -
1.0000 Klosed Jongkok INA 85,000.00 85,000.00
0.1200 Zak Portland Cement 50 Kg 75,000.00 9,000.00
0.0100 M3 Pasir Pasang 300,000.00 3,000.00
Total 305,500.00
29 10.6.8 1 BUAH PASANG BAK MANDI BATU BATA 0.3 M 3
3.0000 Tukang Batu 80,000.00 240,000.00
0.3000 Kepala Tukang 90,000.00 27,000.00
6.0000 Pekerja 75,000.00 450,000.00
0.3000 Mandor - -
2.8800 Zak Portland Cement Kg 75,000.00 216,000.00
0.3000 M3 Pasir Pasang 300,000.00 90,000.00
6.0000 Kg Semen Nat 5,000.00 30,000.00
330.0000 Buah Bata 600.00 198,000.00
360.0000 Buah Porselen 11/11 800.00 288,000.00
Total 1,539,000.00
30 10.6.26 1 M' PASANG PIPA PVC DIA 3/4"
0.0600 Tukang Batu 80,000.00 4,800.00
0.0060 Kepala Tukang 90,000.00 540.00
0.0360 Pekerja 75,000.00 2,700.00
0.0018 Mandor - -
1.2000 M' Pipa PVC Dia 3/4 " 30,000.00 36,000.00
0.3500 Perlengkapan (35 % Harga Pipa) 10,500.00 3,675.00
Total 47,715.00
31 10.6.35 1 BUAH PASANG KRAN DIA 1/2" - 3/4"
0.1000 Tukang Batu 80,000.00 8,000.00
0.0100 Kepala Tukang 90,000.00 900.00
0.0100 Pekerja 75,000.00 750.00
0.0050 Mandor - -
1.0000 Buah Stok Kran 4,000.00 4,000.00
0.0250 Buah Seal Tape 200.00 5.00
Total 13,655.00
32 12.6.2 1 BUAH PASANG KUNCI TANAM 2 X SLAAG
0.5000 Tukang Kayu 80,000.00 40,000.00
0.0100 Kepala Tukang 90,000.00 900.00
0.0100 Pekerja 75,000.00 750.00
0.0050 Mandor - -
1.0000 Buah Kunci Tanam 80,000.00 80,000.00
Total 121,650.00
33 12.6.5 1 BUAH PASANG ENGSEL PINTU
0.1500 Tukang Kayu 80,000.00 12,000.00
0.0150 Kepala Tukang 90,000.00 1,350.00
0.0150 Pekerja 75,000.00 1,125.00
0.00075 Mandor - -
1.0000 Buah Engsel Pintu 4,000.00 4,000.00
Total 18,475.00
34 12.6.17 1 M 2 PASANG KACA, T=5 MM
0.1500 Tukang Kayu 80,000.00 12,000.00
0.0150 Kepala Tukang 90,000.00 1,350.00
0.0150 Pekerja 75,000.00 1,125.00
0.00075 Mandor - -
1.1000 M2 Kaca Polos 55,000.00 60,500.00
Total 74,975.00
35 12.6.7 1 BUAH PASANG GERENDEL
0.2000 Tukang Kayu 80,000.00 16,000.00
0.0200 Kepala Tukang 90,000.00 1,800.00
0.0200 Pekerja 75,000.00 1,500.00
0.0010 Mandor - -
1.0000 Buah Gerendel/Selot 3,000.00 3,000.00
Total 22,300.00
36 13.6.68 1 M 2 PASANG DINDING KERAMIK 25/25 CM
0.1000 Tukang Batu 80,000.00 8,000.00
0.0450 Kepala Tukang 90,000.00 4,050.00
0.6000 Pekerja 75,000.00 45,000.00
0.0300 Mandor - -
17.0000 Buah Keramik 20/20 6,000.00 102,000.00
1.5000 Kg Semen Nat 5,000.00 7,500.00
0.1860 Zak Portland Cement 50 Kg 75,000.00 13,950.00
0.0180 M3 Pasir Pasang 300,000.00 5,400.00
Total 185,900.00
37 14.6.8 1 M 2 PENGECATAN BIDANG KAYU BARU
(1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
0.0090 Tukang Cat 80,000.00 720.00
0.0060 Kepala Tukang 90,000.00 540.00
0.0700 Pekerja 75,000.00 5,250.00
0.0025 Mandor - -
0.2000 Kg Cat Meni Kayu 6,000.00 1,200.00
0.1500 Plamir 8,000.00 1,200.00
0.1700 Kg Cat Dasar Gloteks 35,000.00 5,950.00
0.2600 Kg Cat Penutup Gloteks 35,000.00 9,100.00
Total 23,960.00
38 14.6.11 1 M 2 PELABURAN BIDANG KAYU DENGAN POLITUR
0.0600 Tukang Cat 80,000.00 4,800.00
0.0160 Kepala Tukang 90,000.00 1,440.00
0.0025 Mandor - -
0.1500 Ltr. Politur 20,000.00 3,000.00
0.3720 Ltr. Politur Jadi 20,000.00 7,440.00
2.0000 Lbr. Amplas 2,500.00 5,000.00
Total 21,680.00
39 14.6.12 1 M 2 PELABURAN BIDANG KAYU DENGAN RESIDU/TER
0.1000 Pekerja 75,000.00 7,500.00
0.0060 Mandor - -
0.3500 Liter Residu atau Ter 8,000.00 2,800.00
Total 10,300.00
40 14.6.14 1 M 2 PENGECATAN TEMBOK BARU
(1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.0630 Tukang Cat 80,000.00 5,040.00
0.0063 Kepala Tukang 90,000.00 567.00
0.0200 Pekerja 75,000.00 1,500.00
0.0025 Mandor - -
0.1000 Kg Plamir Jadi 6,000.00 600.00
0.1000 Kg Cat Dasar Tembok 4,000.00 400.00
0.2600 Kg Cat Penutup Tembok 4,000.00 1,040.00
Total 9,147.00
41 1 M2, PEK. ACIAN TEMBOK
0.100 Portland Cement (PC) 75,000.00 7,500.00
0.020 Kg Kapur Tonasa 1,000.00 20.00
0.100 Kg Plamur 6,000.00 600.00
0.150 Lbr Amplas 2,500.00 375.00
0.030 Tukang Cat 80,000.00 2,400.00
0.003 Kepala Tukang Cat 90,000.00 270.00
0.160 Pekerja 75,000.00 12,000.00
23,165.00
42 14.6.15. 1 M 2 PENGECATAN TEMBOK LAMA/PENGECATAN PLAFON
(1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.0420 Tukang Cat 80,000.00 3,360.00
0.0042 Kepala Tukang 90,000.00 378.00
0.0280 Pekerja 75,000.00 2,100.00
0.0025 Mandor - -
0.1200 Kg Cat Dasar Tembok 4,000.00 480.00
0.1800 Kg Cat Penutup Tembok 4,000.00 720.00
Total 7,038.00
43 1 M2, PEKERJAAN BINGKAI PINTU / BINGKAI JENDELA
0.035 M3 Papan Jati 3,600,000.00 126,000.00
0.820 M2 Kaca Bening t = 3 mm 55,000.00 45,100.00
4.000 M' List Kaca 1 x 1 Cm 550.00 2,200.00
1.500 Tukang Kayu 80,000.00 120,000.00
0.200 Kepala Tukang Kayu 90,000.00 18,000.00
1.000 Pekerja 75,000.00 75,000.00
0.050 Mandor - -
386,300.00
44 1 M2 Pemasangan Konstruksi Kuda-Kuda Baja Ringan
0.20 Pekerja 90,000.00 18,000.00
0.20 Tukang Besi 80,000.00 16,000.00
0.20 Kepala tukang 90,000.00 18,000.00
0.01 Mandor - -
4.60 M1 Truss C.75.75. Chord 13,000.000 59,800.00
3.80 M1Reng Batten U.38.045 8,000.000 30,400.00
0.50 M1Trap Bracing 4,000.000 2,000.00
8.50 Bh Screw 12 - 14 - x 20 HDG 500.000 4,250.00
12.50 Bh Screw 12 - 16 - x 16 HDG 400.000 5,000.00
0.10 M1 Valley Gitter 30,000.000 3,000.00
0.50 Bh Anchor Bolt M10 x 77 1,500.000 750.00
157,200.00
DAFTAR UPAH KERJA DAN HARGA BAHAN

PEMBANGUNAN : PEMBANGUNAN RUMAH TINGGAL


ATAS NAMA/PEMILIK : SITI SARSINAH, S.Sos
LOKASI : JL. MALIK SIRULLAH KEL. BUKIT WOLIO INDAH KEC. WOLIO

No JENIS BAHAN/UPAH SATUAN HARGA (Rp)


1 2 3 4

HARGA SATUAN UPAH


1 Kepala Tukang OH 90,000.00
2 Mandor OH -
3 Pekerja OH 75,000.00
4 Tukang Batu OH 80,000.00
5 Tukang Besi OH 80,000.00
6 Tukang Cat OH 80,000.00
7 Tukang Kayu OH 80,000.00

BAHAN MATERIAL GALIAN LOKAL


1 Batu Bata Buah 600.00
2 Batu Gunung M3 160,000.00
3 Kapur Kg 1,000.00
4 Kerikil M3 350,000.00
5 Pasir Beton M3 300,000.00
6 Pasir Pasangan M3 300,000.00
7 Pasir Urug M3 300,000.00
8 Tanah Urug M3 65,000.00
BAHAN/MATERIAL KAYU
1 Balok Kelas I (Jati, Bayam) M3 3,500,000.00
2 Papan Kelas I M3 3,600,000.00
3 Balok Kelas II (Wola) M3 2,750,000.00
4 Papan Kelas II M3 3,000,000.00
5 Kaso Kalapi Kelas II M3 2,250,000.00
6 Papan Klas III M3 1,700,000.00
7 Dolken Btg 10,000.00

BAHAN/MATERIAL TOKO
1 Semen 50 Kg Zak 75,000.00
2 Semen Nat Kg 5,000.00
3 Besi Beton Kg 9,500.00
4 Kawat Bendrat Kg 9,500.00
5 Baut/Begel Buah 5,000.00
6 Keramik 10/20 Buah 1,500.00
7 Keramik 20/25 Buah 2,500.00
8 Keramik 20/20 Buah 2,000.00
9 Semen Warna Kg 5,000.00
10 Pc Abu-Abu 20/20 Buah 2,000.00

BAHAN/MATERIAL ATAP
1 Alumunium Spandek Lbr 56,000.00
2 Seng Plat BJLS 0.20 Lbr 35,000.00
3 Karet Talang M 9,000.00

BAHAN MATERIAL PAKU


1 Paku Campur Kg 12,000.00
2 Paku Seng Kg 15,000.00
3 Paku Tripleks Kg 15,000.00
No JENIS BAHAN/UPAH SATUAN HARGA (Rp)
1 2 3 4

BAHAN/MATERIAL TRIPLEKS
1 Tripleks 3 mm Lembar 60,000.00
2 Papan Gypsum Lembar 150,000.00
3 List Plafond Kayu Profil M 4,000.00
4 Lem Fox Kg 10,000.00

BAHAN/MATERIAL CAT
1 Cat Tembok Kg 4,000.00
2 Cat Kayu Gloteks Kg 35,000.00
3 Teak Oil Liter 4,000.00
4 Many Kayu/Besi Kg 6,000.00
5 Dempul Kayu Kg 8,000.00
6 Minyak Cat Kg 6,000.00
7 Ter Kg 8,000.00
8 Vernis Kg 20,000.00
9 Amplas Kayu Lembar 2,500.00
10 Plamir Tembok Kg 6,000.00
11 Cat Atap Kg 10,000.00

BAHAN/MATERIAL PINTU DAN JENDELA


1 Kunci Tanam Buah 80,000.00
2 Engsel Pintu Kuningan Buah 4,000.00
3 Engsel Jendela Kuningan Buah 3,000.00
4 Kait Jendela 6" Buah 3,000.00
5 Grendel Pintu Kuningan Buah 3,000.00
6 Grendel Jendela Kuningan Buah 2,500.00
7 Besi Strip 3/30 mm Batang 2,000.00
8 Besi Strip 3/30 mm Kg 9,000.00
9 Baut Buah 2,000.00
10 Kaca Polos 3 mm M2 55,000.00
11 List Kaca M' 550.00
12 Pintu Baja/Folding Gate M2 800,000.00

BAHAN/ MATERIAL SANITASI


1 Kloset Jongkok Standar Buah 85,000.00
2 Septic Tank 3 M3 Buah 1,000,000.00
3 Pipa PVC dia.3/4" Batang 30,000.00
4 Pipa GI dia.1/2" Batang 55,200.00
5 Stok Kran 1/2" L. Panjang Buah 5,000.00
6 Stok Kran 1/2" Buah 4,000.00
7 Seal Tape Buah 200.00

Baubau, Maret 2023


Dibuat Oleh :
-

KRESNA PUTRA M
-