PROJECT PROJECT PROJECT END

PROJECT NAME
DURATION START DATE DATE
New Kitchen Renovation 27 Dec 01, 2017 Dec 28, 2017

Dec 01, 2017


Dec 02, 2017
Dec 03, 2017
Dec 04, 2017
Dec 05, 2017
Dec 06, 2017
Task
ID Task Description Duration Start Date End Date
Dec 01, 2017 Dec 05, 2017 x x x x x
1 Demolition 4
Dec 06, 2017 Dec 10, 2017 y
Dec 06, 2017 Dec 08, 2017 x
2 Install new tiles 2
Dec 08, 2017 Dec 13, 2017
Dec 09, 2017 Dec 11, 2017
3 Reroute current plumbing 2
Dec 08, 2017 Dec 09, 2017
Dec 12, 2017 Dec 14, 2017
4 Paint walls and ceiling 2
Dec 20, 2017 Dec 25, 2017
Dec 15, 2017 Dec 16, 2017
5 Install baseboards 1
Dec 17, 2017 Dec 18, 2017
6 Install fixtures 1
Dec 19, 2017 Dec 20, 2017
7 Place new appliances 1
Dec 21, 2017 Dec 24, 2017
8 Install new cabinetry 3
Dec 25, 2017 Dec 26, 2017
9 Install new lighting 1
Dec 27, 2017 Dec 28, 2017
10 Final delivery with customer 1
x
y
Dec 07, 2017

y
y
y
Dec 08, 2017

x
y
y
y
Dec 09, 2017

x
y
y
Dec 10, 2017

x
y
Dec 11, 2017

x
y
Dec 12, 2017

x
y
Dec 13, 2017

x
Dec 14, 2017

x
Dec 15, 2017

x
Dec 16, 2017

x
Dec 17, 2017

x
Dec 18, 2017

x
Dec 19, 2017

x
y
Dec 20, 2017

x
y

Dec 21, 2017

x
y

Dec 22, 2017

x
y

Dec 23, 2017

x
y

Dec 24, 2017

x
y

Dec 25, 2017


x
Dec 26, 2017
x
x Dec 27, 2017
Dec 28, 2017
Dec 29, 2017
Dec 30, 2017
Dec 31, 2017
Mar 01, 2024
Mar 02, 2024
Mar 03, 2024
Mar 04, 2024
Mar 05, 2024
Mar 06, 2024
Mar 07, 2024
Mar 08, 2024
Mar 09, 2024
Mar 10, 2024
Mar 11, 2024
Mar 12, 2024
Mar 13, 2024
Mar 14, 2024
Mar 15, 2024
Mar 16, 2024
Mar 17, 2024
Mar 18, 2024
Mar 19, 2024
Mar 20, 2024
Mar 21, 2024
Mar 22, 2024
Mar 23, 2024
Feb 12, 2024
Feb 13, 2024
Feb 14, 2024
Feb 15, 2024
Feb 16, 2024
Feb 17, 2024
Feb 18, 2024
Feb 19, 2024
Feb 20, 2024
Feb 21, 2024
Feb 22, 2024
Feb 23, 2024
Feb 24, 2024
Feb 25, 2024
Feb 26, 2024
Feb 27, 2024
Feb 28, 2024
Feb 29, 2024
Project Description Task Description Duration Start Date End Date

Clear and grub 2 Feb 12, 2024 Feb 14, 2024 x x x


Regravelling of 2km road Rip and compact bedding 5 Feb 13, 2024 Feb 18, 2024 y y y y y y
(Balfour Ward 3 Rissik
Street); Construction of wearing course 5 Feb 19, 2024 Feb 24, 2024 x x x x x x
Stormwater channelling and erosion protection 6 Feb 20, 2024 Feb 26, 2024 y y y y y y y
Saw cut defective areas 2 Feb 12, 2024 Feb 14, 2024 x x x
Resurfacing (tar and Clear and grub material 4 Feb 13, 2024 Feb 17, 2024 y y y y y
paving) of 0.5 km road Placement of asphalt 4 Feb 13, 2024 Feb 17, 2024 x x x x x
(Balfour Ward 4 Monarene Application of Slurry seal 4 Mar 04, 2024 Mar 08, 2024 y y y y y
Street); Remove damaged Paving bricks 1 Feb 19, 2024 Feb 20, 2024 x x
Reinstate Paving 3 Feb 20, 2024 Feb 23, 2024 y y y y
Saw cut defective areas 1 Feb 16, 2024 Feb 17, 2024 x x
Clear and grub material 3 Feb 19, 2024 Feb 22, 2024 y y y y
Reconstruction of access Construct base patches and place new asphalt surfacing 3 Feb 19, 2024 Feb 22, 2024 x x x x
and regravelling of 0.5 km Application of Slurry seal 4 Mar 11, 2024 Mar 15, 2024 y y y y y
road (Balfour Ward 4). REGRAVELLING
Rip and compact bedding 2 Feb 29, 2024 Mar 02, 2024 y y y
Construction of wearing course 2 Mar 04, 2024 Mar 06, 2024 x x x
Final works inspection and snag repair 5 Mar 16, 2024 Mar 21, 2024 x x x x x x
PROJECT COMPLETION
Project handover 1 Mar 23, 2024 Mar 23, 2024 y