Professional Documents
Culture Documents
complete (SR) was $425. The remainder, after subtracting $425 from
$3,075, $2,650, should be broken down into components for a more
thorough analysis, i.e., what part of the $2,650 represents net profit
prevented, what part represents costs incurred up to the breach and, of
those costs incurred, what part is variable and what part is fixed
(overhead) costs? Suppose, then, that the value of the total costs incurred
(TCI) at the time of breach was $2,500. The net profit prevented should
be determined by subtracting from $3,075 (KP) the sum of $425 (SR) and
$2,500 (TCI) for a profit figure of $150. When this is added to the TCI
figure of $2,500, the total recovery for breach of contract is still $2,650. A
more thorough breakdown might try to distinguish between fixed and
variable costs in the $2,500 TCI figure, especially since Owner may claim
that Contractor did not exercise reasonable efforts to salvage materials
purchased or to reallocate labor after the breach. If Owner is correct, the
TCI figure might be reduced in the amount that would have been realized
if a reasonable salvage had been effected. For a fuller exploration of these
complexities, see Colorado Environments, Inc. v. Valley Grading Corp.,
105 Nev. 464 (1989).
In the example above, the damages, whether expressed in a lump
sum or components, protect both the expectation and the reliance
interests. Put more directly, Contractor cannot be put in the place
Owner’s full performance would have put it unless it recovers both net
gains prevented and unreimbursed expenses in part performance. In
addition, Contractor should have the opportunity to plead and prove
consequential damages resulting from the breach that were foreseeable
by the defendant at the time of contracting. See Independent Mechanical
Contractors, Inc. v. Gordon T. Burke & Sons, Inc., 1388 N.H. 110 (1993)
(profits lost in other ventures).
Burden of Proof. Who has the burden of proving what the cost of
completion would have been, the plaintiff or the defendant? In a case
where the plaintiff was a terminated contractor who left a construction
job that was later completed by others, it was held that the initial burden
of coming forward with evidence (and, perhaps, the ultimate risk of non-
persuasion) was on the defendant. United States v. Merritt-Meridian
Constr. Corp., 2000 WL 272177 (S.D.N.Y. 2000). The court analogized the
cost to complete to a set-off, which is traditionally treated as an
affirmative defense. In addition, the court concluded that the burden
should be on the party with superior access to information about
completion costs and who seeks to take advantage of them. In both cases,
that was the defendant.
Britton v. Turner
Supreme Court of Judicature of New Hampshire, 1834.
6 N.H. 481.
PAY wut &r The d ed the common counts, and among them a
Sevvicet fendered count in or the labor, averring it to be worth one
, hundred dollars.
At the trial in the C.C. Pies the plaintiff proved the performance of
the labor as set forth in the declaration.
Nor 96Cec & * The defence was that it was performed under a special contract—
<a Por a that the plaintiff agreed to work , from some time in March,
for 1831, to March 1832, and that the defendant was to pay him for said
year’s labor the sum of one hundr nd the
7fer
{Pbed] Wolfe. defendant offered evidence te that such was the contract
Q Monthy under which the work was done.
ag hee acy Evidence was also offered to show that the plaintiff left the
defendant’s service wi and it was contended by the
dotgndant that the in hi
The court ETRE TS the jury, that if they were satisfied from the
evidence that the labor was performed, under a contract to labor a year,
ib Sta no for the sum of one hundred and twenty dollars, and if they were satisfied
Dyas al that the plaintiff labored only the time specified in the declaration, and
then left the defendant's s service, SHES oe consen d without any
A party who contracts to perform certain specified labor, and who lg unjug
breaks his contract in the first instance, without any attempt to perform
it, can only be made liable to pay the damages which the other party has
sustained by reason of such non performance, which in many instances
may be trifling—whereas a party who in good faith ha
at he should pay
for the
Serie value
ac buceer es of the house.
“Selevee eee
**x*
ClauRe thaz
RleeLuclCC Porpntag
SECTION 3 DAMAGES 1077
ee,
This rule, by binding the employer to pay the value of the service he
actually receives, and the laborer to answer in damages where he does
not complete the entire contract,
Applying the principles thus laid down, to this case, the plaintiff is
entitled to judgment on the verdict.
The defendant sets up a mere breach of the contract in defence of the
action, but this cannot avail him. He does not appear to have offered
evidence to show that he was damnified by such breach, or to have asked
that a deduction should be made upon that account. The direction to the
jury was therefore correct, that the plaintiff was entitled to recover as
much as the labor performed was reasonably worth, and the jury appear
to have allowed a pro rata compensation, for the time which the plaintiff
labored in the defendant’s service. * * *
Judgment
onthe verdict.
NOTES
(1) As one court put it:
Because the application of the [divisibility] doctrine depends on
evidence of ‘agreed equivalents,’ the use of the contract price to
determine entitlements when the contract has not been fully
performed is defensible only when the contract itself can be said to
specify the price for partial performance.... That condition will
rarely be satisfied. If an employment contract is for a year and the
employee quits after his first week on the job, it is artificial to
suppose that the contract entitles him to one week’s wages, for had
he insisted in the contract that he be free to leave after a week the
1078 REMEDIES CHAPTER 6