January 6, 2014 | 4 minute read
Follow 40 61 83,180
1. Control cycle
2. Supply area
First of all supply area will be created with storage location and responsible
person.
Go to MMSC
Exclude the storage location from planning(as this is not required to plan through
MRP). We can exclude the storage location from customizing also. In this case all
the material in the storage location will be excluded for planning.
Now the control cycle has to be created.
T code PK01
This can be done through control cycle maintenance also. T code PKMC. To
create new click on
Total stock is 63 and is excluded from MRP. This stock will be consumed in
subsequent stage(in next stage)
In actual situation bins are being scanned through RF device and scanning is
being done one the Bins are empty or Full.
Now check MD04. One Production order created (as empty means one proposal
will be created).
Make another Bin empty is same process and see MD04 screen.
PK31: Error in KANBAN can be checked. Select any error line and click on Bell.
You can change the error status.
Alert Moderator
Assigned Tags
Synchronous Goods Receipt for Kanban: Kanban for in-house production strategies ‘working with production
orders' in S/4 HANA 2020 Embedded EWM
By shailesh mishra Apr 23, 2021
Related Questions