You are on page 1of 13

Applied Energy 260 (2020) 114249

Contents lists available at ScienceDirect

Applied Energy
journal homepage: www.elsevier.com/locate/apenergy

Production of synthetic natural gas from industrial carbon dioxide T


a b c b a,⁎
Remi Chauvy , Lionel Dubois , Paul Lybaert , Diane Thomas , Guy De Weireld
a
Thermodynamics and Mathematical Physics Unit, University of Mons, 20 Place du Parc, 7000 Mons, Belgium
b
Chemical and Biochemical Process Engineering Unit, University of Mons, 20 Place du Parc, 7000 Mons, Belgium
c
Thermal Engineering and Combustion Unit, University of Mons, 20 Place du Parc, 7000 Mons, Belgium

HIGHLIGHTS

• Power-to-gas has a strong potential in the transition to a renewable network.


• Advanced CO capture process allows to reduce the energy consumption.
• Heat
2
integration improves the competitiveness of the global Power-to-Gas chain.
• Attractiveness of Power-to-gas is economically sensitive to electricity cost.

ARTICLE INFO ABSTRACT

Keywords: The Power-to-Gas strategy has become a mainstream topic for decarbonization and development of renewables
Carbon capture and utilization and flexibility in energy systems. One of the key arguments for decarbonizing the gas network is to take ad-
Power-to-gas vantage of existing network infrastructure, gradually transitioning to lower fossil carbon sources of methane
Process simulation from Power-to-Gas.
Techno-economic evaluation
This work proposes the techno-economic investigation of an integrated system considering an advanced CO2
Heat integration
capture process, in terms of solvent and process configuration, to treat about 10% of a cement plant’s flue gas
and convert the captured CO2 into synthetic natural gas using renewable hydrogen generated from a large-scale
wind powered electrolyzer. An optimized heat recovery system is proposed, drastically decreasing the external
hot utility demand of the CO2 capture unit. In addition, it leads to the production of complementary electricity
(about 1.06 MW), reducing thus also the electrical demand of the integrated process.
The synthetic natural gas produced has a composition (CH4 92.9 mol.%, CO2 3.7 mol.%, and H2 3.4 mol.%)
and a Wobbe index (46.72 MJ/m3), corresponding to specification for gas grid injection at 50 bar in Germany.
With an overall system efficiency of 72.6%, the process produces 0.40 ton synthetic natural gas per ton of
captured CO2. The cost of the synthetic natural gas produced is higher when compared to the present natural gas
market price, but cost reductions and possible commercial use of coproducts like oxygen, represent a likely
alternative. Costs are mainly driven by high capital investments (the electrolyzer), and the price of renewable
electricity, which is expected to decrease in the coming years.

1. Introduction are therefore considering these two families of technologies, such as


Norway, Germany, and Denmark. Zappa et al. recently conducted a
Following the 2016 Paris Agreement (COP 21) to keep warming study investigating whether a 100% renewable European power system
below 2 °C above pre-industrial levels, pursuing efforts to limit the would be feasible by 2050 [1]. They concluded that a 100% renewable
temperature increase to 1.5° C, above pre- industrial levels, the power system would still require significant flexible zero-carbon sto-
European Union (EU) reaffirmed its goal to reduce greenhouse gas rage capacity to balance variable renewable energy generation, and
emissions by 80–95% compared to 1990 levels by 2050. In order to CCUS may still be required to achieved the EU’s ambitious climate
achieve these goals, large-scale implementation of low-carbon tech- objective.
nologies, such as renewable energy sources (RES), and carbon capture Nowadays, global wind power capacity is growing continuously
utilization and storage (CCUS), are necessary. Numerous EU countries (310 TWh per year in 2015 in European countries with an installed


Corresponding author.
E-mail address: guy.deweireld@umons.ac.be (G. De Weireld).

https://doi.org/10.1016/j.apenergy.2019.114249
Received 29 July 2019; Received in revised form 21 November 2019; Accepted 23 November 2019
Available online 18 December 2019
0306-2619/ © 2019 Elsevier Ltd. All rights reserved.
R. Chauvy, et al. Applied Energy 260 (2020) 114249

capacity of 136 GW [1]) as the cost of producing renewable electricity Greenhouse Gas R&D Programme [21] pointed out that among the
is sometimes even lower than the cost obtained from fossil fuels. Pe- different liquid absorbents that can be used for capturing CO2 (e.g.
netration of wind power in the electricity market is already high in aqueous amine (TRL 6–9), amino acid or mixed salts (TRL 6), ionic
several EU countries such as Denmark (51%), and Ireland (24%). Ger- liquids (TRL 4), water-lean absorbents (TRL 5), precipitating and de-
many also denotes a high share of solar-based electricity (6%) [2]. mixing solvents (TRL 4–6), etc.), aqueous solutions composed of amine
However, the penetration of renewable sources into the energy system blends (e.g. piperazine (PZ) mixed with another amine such 2-amino-2-
is often limited by the energy storage capability, mainly due to high methyl-1-propanol (AMP) or methyldiethanolamine (MDEA)) can be
costs. Therefore, for continuous availability and reliability, develop- considered as the new reference solvents in place of monoethanolamine
ment of other efficient grid storage alternatives is needed. (MEA), long time considered as benchmark for such CO2 capture pro-
In this context, the Power-to-Gas (PtG) strategy is of growing in- cesses [21]. These amines blends and especially activated solutions
terest for decarbonization and increasing development of renewables allow to reduce significantly the energy demand of the system. Re-
and flexibility in energy systems [3]. In PtG applications, when abun- garding the other post-combustion CO2 capture technologies, mem-
dant renewable energy is available, mainly (but not necessarily ex- brane systems (TRL 5–6) and solid sorbent processes (TRL 6) (e.g. Va-
clusively) excess electricity can be used to produce a storable gas, such cuum Pressure-Swing Adsorption (VPSA), calcium looping, etc.) have
as hydrogen produced by water electrolysis. Currently, only 4% of also received a growing interest [22–24]. The widespread deployment
hydrogen is produced by water electrolysis (overwhelmingly by steam of pilot and demonstration plants, including both large-scale demon-
reforming), where the total hydrogen production around the world is stration projects and commercial size amines-based post-combustion
about 500 bill·Nm3/year [4,5]. This renewable hydrogen is either used worldwide installations, such as Boundary Dam (Canada), Petra Nova
directly in industrial applications or in fuel cells [6]. Direct injection of (USA), and Shengli (China), were reviewed by Idem et al. [25].
hydrogen into the natural gas grid (up to 10%) or conversion into In the case of the post-combustion CO2 capture by absorption–re-
synthetic natural gas (SNG) by methanation and subsequent injection generation processes applied in a cement plant, the CO2 is separated
into the gas grid are widely considered in the literature [2,7,8,9]. In from the exhaust gases of the system by adding a unit to the tail-end of
addition to maintain the high heating value of the gas, methanation the clinker process. While this end-of- pipe mature technology achieves
denotes several advantages, as it avoids adaptation in the gas grid high absorption efficiency (usually 90%), the main disadvantage is the
equipment necessary for higher hydrogen contents. Furthermore, high energy demand for the scrubbing liquid regeneration (e.g. from
compared to pure hydrogen, SNG (87–97 wt% methane) has fewer 3.2 GJ/t CO2 to around 3.8 GJ/t CO2 with MEA 30 wt% as solvent
barriers to implementation, as it is safer, easier to transport and store, [26]). Nevertheless, the development of new solvents (new solutions or
and more suitable for industrial applications [10]. It overcomes the blends) [21,27], and new process configurations [28,29] are allowing
facility and energy density issues related to the use of hydrogen, while the global performances of the absorption-regeneration technology to
providing other services [11]. It has to be noticed that the conversion is reduce its energy consumption to be improved, so that this technology
limited in the term ‘Power-to-Gas’ to the production of hydrogen and remains attractive and competitive.
methane, the later in the form of SNG. Other converting forms of The Power-to-Gas process chain was first proposed in Japan in the
electrical energy to liquid energy carriers (hydrocarbons such as me- late 1980 s. Recently, a growing interest dealing with this technology
thanol, dimethyl ether, and Fischer-Tropsch products) are more likely has begun, especially in Europe. In a detailed review, Rönsch et al. give
to associate the term ‘Power-to-Fuel’ or ‘Power-to-Liquid’ [12]. Even an overview of methanation technology and research, focusing on
though hydrocarbons denote a higher volumetric density in comparison projects with methane as a product [30]. Chauvy et al. maintain that
to gases, PtG allows the use of the existing natural gas infrastructure as PtG is one of the best alternative processes for CO2 utilization among
transport and storage medium, offering a market availability of all the examined cases in the sensitivity analysis [31]. The interest is mainly
system-relevant components. Furthermore, wind-to-SNG offers an en- driven by the increasing share of renewable energy (wind and solar
ergy storage medium for the intermittent wind resource, where the power), where PtG may provide large-scale and long-term energy sto-
electricity generated by the renewable energy is merged into the grid rage [32]. Other field of applications include services to balance the
providing a more constant renewable energy supply, avoiding over- loads in electricity networks, a substantial source of fuel for heating and
supplying power grids with high production from renewable energy. transportation, and a significant contribution to emission reduction
Concurrently, many industrial processes look for possibilities to targets [33]. Pilot plants are under construction, or even in operation,
decrease their CO2 emissions, where CCUS is considered. Accounting in several countries, including Germany, Switzerland, Denmark, France,
for 2–2.5 GtCO2 per year (5–7% of the total anthropogenic CO2 emis- and Japan. In particular, the European Power-to-Gas Platform contains
sions) [13,14], the cement sector is investigating ways to cut its emis- a database of past, current and planned PtG projects in Europe [34].
sions through different levers such as modern dry-process technology, Numerous reviews of PtG projects present lab, pilot and demo plants for
clinker substitution, free-carbon alternative fuels and CCUS. It is esti- storing renewable energy and CO2 [7,35,36]. Quarton and Samsatli is
mated that only about one third of the CO2 released is due to com- particularly recommended for more detail on real-life PtG projects,
bustion, and this makes the cement industry a specific case compared economic assessments and systems modeling [7]. Bailera et al. detail
with other combustion industries. Clinker, main constituent of the ce- worldwide existing projects and present basic information together
ment, is made by heating a homogeneous mixture of raw materials at with qualitative descriptions of the plants, technical data, budget and
minimum temperature of 1450 °C. Two thirds of these released emis- project partners [35]. Wulf et al. reference about 130 demonstration
sions, i.e. 550 kgCO2 per ton of clinker, come from the limestone cal- projects in operation or planning in Europe (63 projects were in op-
cination during the decarbonation step in the clinker burning process, eration by end of May 2018), about 40% of which were developed in
and are then necessarily emitted [15,16]. Hence, the capture of CO2 Germany [36].
from cement plant’s flue gas and its conversion are key issues. This CO2 One example project that illustrates the concept of PtG is the e-Gas
can be a source for methanation. Project (Werlte, Germany) [8,35]. It demonstrates how renewable en-
Several technologies at different levels of maturity and perfor- ergy could be efficiently stored in the existing natural gas network. It
mances can be envisaged for capturing the CO2 from cement kilns (e.g. consists of methanation combined to an organic waste biogas plant,
oxy-fuel combustion, chilled ammonia technology, adsorptive pro- which produces about 1 kton methane-rich gas from concentrated CO2
cesses, calcium looping, etc.) [17–20]. The most mature technology is and renewable H2. Three alkaline electrolyzer stacks of 2 MW supplied
the absorption-regeneration amine-based process, which reached a TRL from a 14.4 MW capacity offshore wind park generate the H2. The
(Technology Readiness Level) of 9 compared to the lower TRLs of all annual SNG injection to the grid from this process is approximately 3
other technologies. More precisely, a recent study from the IEA million Nm3.

2
R. Chauvy, et al. Applied Energy 260 (2020) 114249

Other CCUS route(s)

Raw materials A
Cement kiln CO2-separation unit
Fuel Depleted flue gas
Flue gas Amine scrubbing

Cement
Scrubbing liquid
regeneration

CO2 Heat Excess heat for other


application
Excess RE H2 B
Electrolysis Methanation
H2O
CO2/H2 Raw SNG
O2 H2O
Gas upgrading Grid injection
SNG

Fig. 1. Conceptual Flowsheet of the interconnected PtG system comprising (A) CO2 capture unit; (B) CO2 methanation unit.

In the meantime, many studies focus on thermodynamic con- part of CO2 coming from a cement plant into SNG, and comprises four
siderations, the development of new catalysts, the characterization of implementation steps: (i) an operational cement plant equipped with
the reaction kinetics and mechanisms of CO2 methanation [37,38]. For the Best Available Technique (BAT), where an advanced CO2 separating
instance, Su et al. proposed a review on the advances in catalytic CO2 unit for scrubbing CO2 contained in the flue gas was considered; (ii) an
hydrogenation to methane, discussing the structure of the catalysts, the electrolysis unit for splitting water by electrolysis to produce renewable
preparation methods, the pre-treatment conditions and their compo- H2 and O2; (iii) a methanation unit for converting the CO2 and the
nents in detail [37]. renewable H2 by a methanation reaction to a methane rich gas (SNG);
In addition, Eveloy and Gebreegziabher recently reviewed projected and (iv) a SNG upgrading unit to fulfil the requirements for further
PtG deployment scenarios at regional and distributed scales [39]. They injection into the gas grid. Finally, the possibility of heat integration
highlighted that even though many types of PtG energy/material in- through systematic process-to-process analysis is investigated to reach
tegrations are possible, few of them have been incorporated into PtG high energy efficiency and minimize utility costs. It is worth noting that
deployment modelling works. Furthermore, they identified that heat the produced SNG can also be converted into compressed renewable
recycling from catalytic methanation reaction products, feed compres- natural gas or liquefied renewable natural gas to serve as a transport
sion trains, and condensed water integrated with CO2 capture from fuel.
cement production and/or water electrolysis requirements have re- The size of the PtG process is based on a 90 MW large-scale wind-
ceived limited attention. This lack of experience with the whole PtG based electrolyzer, generating 40 ton of renewable H2 per day. The flue
system was also highlighted by Quarton and Samsatli [7], Ghaib and gas to be treated comes from a conventional BAT cement plant pro-
Ben-Fares [8], and Thema et al. [40]. It has to be pointed out that the ducing 3000 tons of clinker per day. It corresponds to a total flow rate
development of PtG technology is also subject to fundamental energy of 250,000 m3/h, at 1.20 bar and 40 °C after conditioning (after de-
and climate policy decisions. sulfurization, denitrification, dedusting and cooling), with a CO2 con-
Therefore, only a few studies attempt to evaluate large-scale in- tent of 20 mol.%, generating 2475 ton of CO2 per day [43]. Therefore,
tegrated PtG process performances, showing a large potential for im- 9.8% of the cement plant flue gas is treated where 90% of the CO2 is
provement, which helps the decision makers to justify their choices. captured, representing a CO2 production of about 219 ton per day. The
Becker et al. recently proposed a detailed SNG plant study case where CO2 capture unit can be upscaled in order to treat the entire cement
the synergies between large-scale reactors, thermal management and plant’s flue gas, where the captured CO2 can be geologically stored or
techno-economic considerations were provided [41]. Morosanu et al. converted into other products.
proposed a concept based on water electrolysis to produce hydrogen, Fig. 1 illustrates the conceptual flowsheet of this interconnected PtG
CO2 capture from ambient air using solid adsorption materials, catalytic system.
CO2 methanation, gas separation, and a single mixed refrigerant (SMR)
methane liquefaction process, where mass and energy balances at de-
monstration scale were provided [42]. 2.1. Process modeling and design
To this extent, in-depth modelling and economic analysis of PtG
systems are addressed in this paper. The integration of SNG production 2.1.1. Thermodynamics models and simulation tools
with an advanced CO2 capture process, mainly in terms of solvent and The units investigated in this study were implemented in
process configuration, and considering an optimized heat recovery AspenTech’s software. Concerning the CO2 capture unit, it was simu-
leading to a complementary electricity production, are especially in- lated using the Acid Gas Property Package in Aspen Hysys™ v10.0
novative and correspond to the purpose of the present study. The sug- software. More precisely, the thermodynamic models implemented in
gested PtG technology is flexible, easily up/down-scalable and modular such package are the Electrolyte Non-Random Two-Liquid (eNRTL)
in order to allow an adjustment to any specific boundary conditions of a activity coefficient model for electrolyte thermodynamics in the liquid
distinct application, such as end-product, source of CO2, use of potential phase [44] and the Peng-Robinson equation of state for the vapor phase
by-products, and main purpose of the system (utilization of excess re- [45]. The Acid Gas Package also includes the physicochemical prop-
newable energy, storage, etc.). erties of acid gases (CO2 and H2S), water, amines alone (e.g. MEA, DEA,
MDEA, PZ, etc.) as well as several mixtures (e.g. MDEA + PZ,
DEA + PZ, etc.). The CO2 capture modelling is based on a rate-based
2. Materials and methods calculation model and comprises a makeup unit operation to auto-
matically compensate water and amine losses, which was validated by
The present PtG integrated process plant was developed to convert a Laribi et al. [46].

3
R. Chauvy, et al. Applied Energy 260 (2020) 114249

Aspen Plus™ v10.0 was used for both the CO2 methanation and gas regenerated at higher temperature for optimal performances [29], a
upgrading units considering the Peng Robinson equation of state for the regeneration pressure (Pbottom of the stripper) of 5 bar was considered,
calculation of gaseous properties. Estimates were considered to model leading to a regeneration temperature of 140.8 °C, in contrast to a
the block unit for hydrogen generation. temperature Tregen of around 120 °C with a conventional MEA 30 wt%
solvent.
2.1.2. Renewable H2 production unit The RVC configuration (applied to the rich solution, i.e. after the
Water electrolysis is mainly characterized by the source of elec- absorption step) uses a heat pump effect. As described by Le Moullec
tricity, i.e. high temperature steam, solar or wind-based electrolysis, et al., the purpose of the RVC process modification is to increase the
and the solution used as electrolyte, i.e. alkaline (AE), proton exchange heat quality provided to the system by enabling the valorization of heat
membrane (PEM) or solid oxide (SOEC) electrolyzers. available at a lower quality level or when increasing the quality level is
An essential block for PtG, electrolyzers need to fulfil some special energetically interesting [28]. Thanks to the flashing of the solvent, a
requirements, including dynamic behavior to follow fluctuating power gaseous stream mainly composed of CO2 and H2O is produced. This
inputs, high efficiency to avoid energy losses, elevated pressure to re- stream is compressed and sent back to the regeneration column in order
duce compressor costs, as well as long lifetimes. Even though alkaline to reduce the steam demand at the reboiler. At the same time, with the
electrolyzer technology is fully mature, PEM water wind-based elec- vapor coming from the compressor following the flash tank being quite
trolysis, which is currently close to commercial deployment, was hot (which could lead to hot spot and degradation problems in the
chosen in this work as it is more compact and best suited to the dynamic stripper’s bottom if it is reinjected at such temperature level), a second
load balancing of electricity grids needed with use of intermittent re- internal heat exchanger is added in order to cool this vapor down to the
newable energy. Traditional alkaline electrolyzers, on the other hand, same temperature level at the bottom of the regeneration column
are typically used for continuous steady-state industrial production of (Tregen ). Such an operation also has the advantage of improving the
hydrogen [47,48]. The comparison of electrolyzer technologies is sum preheating of the rich solution before entering the stripper.
up in the Supporting Information (see SI.2). PEM electrolyzer produces Concerning Intercooling, this is a well-described technique which
hydrogen at 30 bar with a high purity level of 99.9 vol%, whilst the has already been applied in several pilot or industrial units. It can also
operating temperature is typically low (50–100 °C) [49]. The specific be considered in the “absorption enhancement” process modification
electrical power of these electrolyzers is estimated at 5 kWh per Nm3, category. The principle of intercooling is to withdraw the solvent
approximately 55.6 kWh per kg H2. A production cost of 4–5 € per kg (partially or totally) flowing in the absorber, at a stage n , to cool it
H2, and a total system cost, including power supply and installation down and to send it back to the absorber at the stage n 1. Such a
costs, of 1200 € per kW with an operation lifetime of 20 years are method enables a shift in the thermodynamic gas–liquid equilibrium,
considered [41,49]. The oxygen stream from the water electrolysis is and consequently increases the rich loading at the absorber bottom (at a
produced in high purity, and may be further used in the calcination same liquid flow rate) [28]. However, a lower temperature in the ab-
process to increase the CO2 partial pressure which facilitates CO2 se- sorber leads to reduced chemical kinetics and diffusivities which is
paration (partial oxy-combustion) [17,19,46]. This high purity by- mostly compensated by the increase of CO2 solubility leading globally
product can also be traded for many high-tech applications. to very little change to the overall mass transfer coefficient. Globally,
The electrolyzers are assumed to be co-located with the sources of such a technical option is expected to decrease the reboiler duty, as
renewable electricity and CO2, neglecting de facto the efforts to in- highlighted by Le Moullec et al. [28].
tegrate the different units, such as infrastructures, and avoid transport Regarding the water-wash sections, as described in the IEAGHG
needs. report prepared by CSIRO (Australia) [52], scrubbers are used for ex-
tracting condensable or soluble vapor from gases. Amine vapors and
2.1.3. CO2 capture unit their degradation products are conventionally captured by water wash
The implemented CO2 capture process was based on the works of or a scrubbing stage, or several stages with demineralized water, acidic
Dubois and Thomas [29,50] considering a Rich Vapor Compression water or with special reagents. In the present work, and in accordance
(RVC) process combined with an Inter-Cooled Absorber (ICA) and two with the CASTOR/CESAR pilot unit considered as a reference, two
Water-Wash (WW) sections, and the use of a MDEA 10 wt% + PZ 30 wt water-wash sections were added to the simulation flow sheet in com-
% blend as the solvent. The selection of the configuration and the sol- parison with the previous model described by Dubois and Thomas [29].
vent, specifically the use of PZ as absorption activator in comparison As such, one water-wash section was used at the top of the absorber,
with other ones (e.g. (piperazinyl-1)-2-ethylamine – PZEA), based on consisting of a packed column composed of three-stages of 1 m height
reaction mechanisms differences leading to different absorption-re- per stage, and another wash section was used directly inside the top of
generation performances, are derived from previous simulation results the stripper consisting of three stages of packing (same dimensional
(see Supporting Information for more details). Fig. 2 presents the im- parameters as for the main column section) below the condenser and
plemented flow sheet. above the rich solution inlet, in which the vapor coming from the re-
The installation was designed taking the pilot unit used in the generation meets the liquid coming from the condensation. In the ab-
CASTOR/CESAR European Projects as Ref. [51]. The CASTOR/CESAR sorber water-wash section, a freshwater make-up is added and also
unit was selected as a reference since all the design and operating serves as water make-up for the global flow sheet. Only a small com-
parameters in relation with the installation are available in literature plement is added into the make-up unit.
[51]. In the current study, this unit was upscaled (columns diameter) in It is assumed that the pre-treated flue gas (after de-SOx, de-NOx, de-
order to treat 24,660 m3/h of flue gas with a CO2 absorption ratio of dusting and cooling) entering the CO2 capture process (composition in
90 mol.%, corresponding to a production of 219 ton per day of CO2 Table 2) consists primarily of CO2, H2O, N2 and O2. This composition is
(98 mol.% purity). The upscaling was performed to keep the same gas based on average values coming from the Brevik Cement plant (Norcem
and liquid velocities, 1.29 m/s and 6.70 10−3 m/s, respectively, such as company) in Norway. It is important to note that the amount of CO2 in
the optimum value for the (L/G) vol ratio, namely around 5.19 10−3 m3/ the gas to be treated was maintained at 20.4% for all the simulated
m3. cases. Nevertheless, the influence of the inlet gas CO2 content on the
The dimensions of the absorber and the stripper, and the operating absorption–regeneration performances has been discussed in previous
conditions for each column are provided in Table 1. Note that Tabs works [29,53].
corresponds to the absorption temperature, at the top of the absorption A summary of the simulation results of the implemented process
column, while Tregen refers to the regeneration temperature, at the highlighting its energetical benefit in comparison with the conventional
bottom of the stripper. PZ-based solvents being conventionally process using MEA 30 wt% as solvent, is provided in the Supporting

4
R. Chauvy, et al. Applied Energy 260 (2020) 114249

Fig. 2. Aspen Hysys™ flow sheet of the RVC + ICA + WW configuration with MDEA + PZ as solvent.

Table 1 High pressure and low temperature enhance the CO2 methanation
Main process data equipment for the CO2 capture unit. process performance, as denoted in Fig. 3. Below 600 °C, only species
Parameter Absorber Stripper involved in the Sabatier reaction (see Eq.(1)) are present, with CO ap-
pearing only for higher temperatures (see SI.3.1). Gao et al. underline
Diameter (m) 2.6 2.6 that carbon deposition is not observed under these simulation condi-
Packing height 17 (17 × 1 m) 10 (10 × 1 m) tions for a H2/CO2 stoichiometric ratio of 4, as the water produced
(m)
Packing type Random packing IMTP Norton Metal 50 mm MELLAPACK,
during the methanation process reacts with solid carbon [55]. In this
SULZER, Standard, 125× (for the water wash section) work, operating conditions are chosen in such a way that CO and solid
Tabs (°C) 40 – C are not produced. In addition, this would allow the simplification of
Tregen (°C) – 140.8 the following gas upgrading step before injection into the grid [56].
Pbottom (bar) 1.2 5 The main detailed kinetic law was developed in 1989 by Xu and
Froment on the Ni/MgAl2O4 (Ni 15 wt%) commercial catalyst, defined
for temperatures between 300 and 400 °C and pressures between 3 and
Table 2
10 bar without dilution gas that is closer to the industrial im-
Composition of the conditioned gas to be treated
plementation of CO2 methanation [57]. A lower temperature (below
(G = 24,660 m3/h, 1.20 bar, 40 °C).
about 200 °C) may cause the formation of nickel carbonyl, while a high
Component mol frac. temperature above 500–650 °C may cause carbon deposition (coking),
N2 64.7%
which will deactivate the catalyst [58]. Modelling catalyst reactions in
CO2 20.4% a series of catalytic reactors has been considered, as it avoids the coking
O2 8.6% and sintering of the catalyst. At least two adiabatic reactors have to be
H2O 6.2% connected in series for a good control of the reaction temperature [59];
CO 1330 ppm
the usual approach relying typically on a series of two to five reactors
SO2 111 ppm
NO 474 ppm [60]. In this work, the methanation unit consists of four adiabatic multi-
NO2 2 ppm tube fixed bed reactors, featuring a multi-stage cooling system and gas
recirculation, allowing the outlet specifications to be achieved while
minimizing costs. The Gas Hourly Space Velocity (GHSV) was main-
Information, where the reactions that are included in the Acid Gas tained close to 4000 h−1.
Package for PZ and MDEA solvents reacting with CO2 are also presented The corresponding rate equations are therefore given by Eqs.
(see SI.1). (4)–(7), where the kinetic parameters and their implementation are
discussed in the Supporting Information (see SI.3.2).
2.1.4. CO2 methanation unit
4 ×p
Thermodynamics and kinetics. Methane production by catalytic pCH4 × pH22 O
pH
2 CO 2
k1
CO2 hydrogenation (Sabatier reaction) has been used since the begin- r1 = 3.5 ×
K1

ning of the 20th century. The reaction scheme is given by [54]: pH2 DEN 2 (4)

CO2 + 4H2 CH 4 + 2H2 O H0298 = 165 kJ/mol (1)


p H2 × pCO 2
k2 pCO × p H2 O K2
CO2 + H2 CO + H2 O 0
H298 = + 41 kJ/mol (2) r2 = ×
p H2 DEN 2 (5)
CO + 3H2 CH 4 + H2 O H0298 = 206 kJ/mol (3)

5
R. Chauvy, et al. Applied Energy 260 (2020) 114249

1.0 100%

0.8 80%

Molar composition
H₂

CH4 yield (%)


0.6 60% CO₂
H₂O
0.4 40% CH₄
CO

0.2 20% CH₄ yield (10 bar)


CH₄ yield (1 bar)

0.0 0%
200 300 400 500 600 700 800
Temperature (°C)
Fig. 3. Molar concentrations of CO2, H2, H2O, CH4 and CO at stoichiometric ratio H2/CO2 = 4, P = 10 bar, and CH4 yield at P = 1 and 10 bar).

3 ×p
pH CO
2 electrolysis, considering the stoichiometric ratio H2/CO2 of 4. A single-
k3 pCH4 × p H2 O
r3 = 2.5 ×
K3 stage CO2 compression step is considered technically appropriate to
pH2 DEN 2 (6) reach the working pressure of 10 bar, while hydrogen is brought to the
same pressure. They are then mixed with the recycle stream derived
where from the upgrading unit and pre-heated to 350 °C before feeding the
K H2 O p H2 O first adiabatic reactor (REA-1) where the methanation reactions occur.
DEN = 1 + K CO pCO + K H2 p H2 + K CH4 pCH4 + A fraction of the effluent, set at 0.7, is recycled to the inlet of REA-1 to
p H2 (7) lower the temperature below 650 °C in order to avoid catalyst sintering
and with ri referring to the rate of reactions i (reactions (1)–(3), re- [61]. Heat removal is ensured to counteract thermodynamic limitations
spectively), k1, k3, the rate coefficients of reactions (1) and (3) (kmol of the reaction as well as to prevent the catalyst bed from sintering the
bar1/2/kgcat h), respectively, k2 the rate coefficient of reaction (2) methanation reactors. The reaction mixture is therefore cooled down to
(kmol/bar kgcat h), K1, K3 the equilibrium constant of reactions (1) and 350 °C after each reactor to obtain high CO2 conversion. The heat of the
(3) (bar2), respectively, K2 the equilibrium constant of reaction (2), methanation reactions can be partly used to produce steam to re-
K CH4 , K CO , and K H2 the adsorption constants of reaction for CH4, CO and generate the scrubbing liquid in the CO2 capture unit. After methana-
H2 (bar−1), respectively, K H2 O the desorption constant of H2O, and p tion, water vapor has to be separated from the product gas. The outlet
the partial pressure (bar). of the last reactor (REA-4) is therefore cooled to a temperature of 25 °C
Process modelling. Fig. 4 shows the process flow sheet of the CO2 to condense the water. A purity of 99.99 vol% is then achieved in the
methanation unit including the upgrading section. H2O stream.
The CO2 coming from the CO2 capture unit is fed at 5 bar with Table 3 presents the main process data equipment for the CO2 me-
hydrogen coming at 30 bar from the PEM water wind-based thanation unit, while Table 4 introduces the specifications for the four

Fig. 4. Aspen Plus™ flow sheet of the CO2 methanation unit including the upgrading section.

6
R. Chauvy, et al. Applied Energy 260 (2020) 114249

Table 3 Table 5
Main process data equipment for the CO2 methanation unit. Gas specification for gas grid injection in Germany [56,69,70].
Parameter Specification Parameter Specification

3
Reactor operating Pressure (bar) 10 Wobbe Index (MJ/m ) 37.8–56.5
Pressure Loss (%) 2 CO2 < 6 vol%
Reactor operating Inlet Temperature (°C) 350 H2 < 5 vol%
Catalyst Ni/MgAl2O4 Dust Technically free
Catalyst density (kg/m3) 2350 water Traces (ppm)
Bed density (kg/m3) 790
Bed porosity 0.44
1 bar. Almost all H2 along with a certain amount of methane transport
across the membrane, was recirculated back to the reactor. The large
Table 4 amount of methane not crossing the membrane forms the retentate at
Main specifications for the four multi- tubular adiabatic reactors at a GHSV of
the identical pressure as the feed stream.
4000 h−1.
The product stream SNG was then supplied to the natural gas grid
Parameter REA-1 REA-2 REA-3 REA-4 usually at elevated pressures from 4 to 70 bar, by using a multistage
3
compressor [68]. The number of stages was determined by a pressure
Reactor volume (m ) 15.60 8.32 7.71 7.47
Mass of catalyst (ton) 22.00 5.87 5.44 5.27 ratio of 4, with equal pressure ratio among all stages. The isentropic
efficiency of each stage of 75%, and the inter-stage cooling temperature
was set at 40 °C. In the frame of this study, it was assumed that the SNG
multi- tubular adiabatic reactors. was delivered at 50 bar. Gas specification for gas grid injection in
Germany is presented in Table 5. The Wobbe index represents the in-
2.1.5. SNG upgrading unit terchangeability of fuel gases with respect to natural gas, which is
The raw-SNG, containing methane, CO2, water vapor and H2, is then usually used to compare the combustion energy output of different
upgraded to be injected into the grid where it can be stored, trans- composition fuels.
ported, or used as fuel (e.g. for CNG cars). Even though the flash unit
removed most of the water (see Fig. 4), the raw-SNG must be further 2.1.6. Heat recovery and utilities
dehydrated to comply with the water dew point requirements of the Systematic process-to-process heat recovery through data evalua-
pipelines, to control corrosion and prevent formation of solid hydro- tion, pinch analysis, and optimized heat exchanger network were per-
carbon/water hydrates. Currently, glycol dehydrators are widely used formed on the system to reach high energy efficiency and minimize
for natural gas dehydration. Despite their advantages, the system op- utility costs. Appropriate heat exchangers areas were designed using
eration is complex and requires solvent storage, replacement and dis- Aspen Plus™.
posal. Moreover, the vent streams from the dehydrators are a source of According to the present design, HX-1 was fed with pressurized
emissions of volatile organic compounds. According to Lin et al., boiled feed water at 110 °C and 125 bar. HX-2 was placed to extract
membrane technology appears to be an attractive alternative for nat- heat from the outlet of the first reactor (REA-1). The steam temperature
ural gas dehydration [62]. To this extent, a commercial Pebax®-based and pressure at the outlet of HX-2 was 505 °C and 125 bar, respectively.
membrane (poly ethylene oxide- based block copolymer) was con- A steam turbine unit was used to generate process power to cover a
sidered to dry the raw-SNG [63,64]. The performance is based on lit- portion of the electrical demand. This was expanded to 10 bar with an
erature values, using an estimated normalized permeability constant of isentropic efficiency of 0.85, generating 1055 kWe . After the exit of the
1000 GPU (1 GPU being 3.35 10−10 mol/m2 s Pa) [62,65], to determine turbine, the steam was fed to the condenser, where it released heat and
the size required using Eq.(8). In the Aspen Plus™ model, only the re- was condensed to 110 °C. The condensate returned to the system with a
tentate/permeate pressures are specified for given feed conditions, as flow rate equal to 7.5 t/h.
well as the split fractions of one of the stream. As previously mentioned, five additional heat exchangers (from HX-
The feed gas mixture is compressed in a multi-stage raw-SNG 3 to HX-7) were implemented to cool down the outlet of each reactor to
compression step to reach a pressure of 35 bar. A small one-stage the working temperature of 350 °C, to obtain high CO2 conversion.
system removes 90% of the water in the feed gas, producing a low- They were fed with boiled feed water at 110 °C and 8 bar, to generate a
pressure permeate gas representing 5–6% of the initial gas flow [66]. medium-pressured steam at 170 °C and 8 bar. This was done so that it
The permeate pressure containing the water is set to 1.1 bar [62,65]. could be brought to the reboiler heat duty of the CO2 capture unit,
which requires heat at 140 °C and 5 bar.
permeate flow rate
Amemb =
permeance × driving force (8)
2.2. Techno-economic analysis
where the permeate molar flux (mol/s) through the membrane is driven
by the partial pressure difference (Pa) of the component of interest H2O, 2.2.1. Technical analysis
namely the driving force, and the permeance is expressed as the ratio of Technical indicators, including the mass balance of individual in-
the permeability with the thickness of membrane, leading to the nor- puts and outputs, and the utilities demand (mainly heat and electricity
malized permeability constant (mol/m2 s Pa) taken to be a measure of duties), are direct results from the process modelling using the software
the membrane’s ability to permeate gas. Aspen Hysys™ and Aspen Plus™.
In addition, excess hydrogen also has to be separated in a gas up- In addition, the methanation efficiency is calculated according to
grading downstream of the dehydration membrane, and then fed back Eq. (9) using the general approach suggested by Salomone et al. [9]:
to the methanation reaction. A commercial membrane technology × XCO2 × MCH4 × LHVCH4
CH4
(polysolfone-based membrane) for hydrogen separation was chosen to CH4 =
H2 × MH2 × LHVH2 (9)
achieve a 90% hydrogen separation [67]. An estimated normalized
permeability constant of 100 GPU [66] was considered to approximate where XCO2 is the conversion of CO2 within the methanation unit, MCH4
the performance and determine the size required using Eq. (8). The and MH2 are the CH4 and H2 molar weights (kg/kmol), LHVCH4 and
stream is therefore expanded to reach a working pressure of 20 bar. The LHVH2 are the CH4 and H2 lower heating values (MJ/kg), CH4 and H2
permeate pressure containing the component of interest H2 was set to are the CH4 and H2 stoichiometric parameters, respectively. The

7
R. Chauvy, et al. Applied Energy 260 (2020) 114249

conversion of CO2 within the methanation unit is assumed to be su- The total product cost (TPC ) is calculated by Eq.(14).
perior to 98.9% to achieve the SNG quality [9]. n
To evaluate the process efficiency of the PtG plant, the PEM elec- TPC =
j=1
Cj
(14)
trolyzer, methanation unit, compressors, and heater are considered,
according to Eq. (10) [9]: with Cj the cost of item j based on Table 7.
nCH4 × MCH4 × LHVCH4
=
PtG
EPEM + Ecomp + Eheat (10) 3. Results and discussions

where EPEM is the electrical energy used by the electrolyzer (MJ), Ecomp 3.1. Process performances
the energy spent for the compression (MJ), and Eheat represents the total
required heat (MJ). 3.1.1. CO2 capture unit results
Finally, the overall energy utilization factor is calculated with Eq. Table 8 summarizes the CO2 capture unit simulation results in terms
(11). of gas phase compositions.
Eheat An absorption ratio of 90 mol.% leads to the production of 211
=1
PtG
EPEM + Ecomp (11) kmol/h of CO2 (9.16 t/h) with 98 mol.% purity. In addition to nitrogen
(123 ppm) and oxygen (29 ppm), the produced CO2 flow still contains
The following parameters are also required for the produced SNG some water (around 2 mol.%) and some other components initially
stream: (i) composition, essential to achieve the gas requirements for present in the flue gas, namely SO2 (< 50 ppm), NO (< 5 ppm), NO2
injection into the networks (i.e. percentage of hydrogen); (ii) the Low (1 ppm) and CO (< 0.5 ppm). As a result of the water-wash sections,
Heating Value (LHV) and/or High Heating Value (HHV); and (iii) the the amines (MDEA and PZ) are only present as traces in the washed-gas
Wobbe index. and the produced CO2 flow.
Concerning the energy consumptions, the main energy consuming
2.2.2. Economic analysis unit is the reboiler of the regeneration column (5.75 MWth ), while the
Both operating and investment costs were evaluated. Most of the other thermal demands are for cooling (mainly condenser cooling en-
capital investment for the equipment was generated directly via ergy, −1.45 MWth , and lean solution cooling, −2.80 MWth ). The
AspenTech Economic Analyzer™. In addition, the cost of several in- cooling energy of the absorber intercooling is less significant (−0.72
dividual pieces of equipment was approximated when the cost of a si- MWth ) and the water-wash cooling energy is very low (−0.01 MWth ).
milar item of a different size or capacity was known, using expression Regarding the electrical demands, while the total pumping energy is
(12). The costs were estimated with a nominal accuracy of ± 30%. low (0.04 MWe ), the electrical consumption of the compressor used in
the RVC configuration is not negligible (0.91 MWe ). These results were
S
C = C0 obtained for the optimum operating parameters given in Table 9, where
S0 (12) the specific energy consumption per ton of captured CO2 is also pro-
where the incremental cost C decreases with larger capacities S , C0 and vided.
S0 being the reference characteristics values. The exponent takes the The specific solvent regeneration energy (2.28 GJ/tCO2) is drasti-
economy of scale effect into account, which is often approximated to cally reduced in comparison with conventional CO2 capture processes
0.6. The results were then updated from the original cost index to the using MEA 30 wt% as a solvent (generally estimated around 3.5 GJ/
year 2018 using the annual chemical engineering plant cost index tCO2 [26] and being precisely calculated at 3.36 GJ/tCO2 using the
CEPCI (CEPCI2018 = 603.1) to account for the price development effect present simulation model), which highlights the interest of using an
(Chemical Engineering magazine for latest values). advanced CO2 capture process such as the one considered in the present
The total capital investment (TCI ) was determined using the fac- study. All the simulation results in relation with the optimization of the
torial methodology, according to the recommended ratio factors for CO2 capture unit are provided in the Supporting Information (see SI.1),
fluid processing plant by Peter and Timmerhaus [71], and the capital where comparisons are also performed in terms of equivalent works and
investment (IE ) of the equipment (see Eq. (13)). utilities costs both for conventional process configurations (without
ICA) and for three different solvents (MEA 30 wt%, PZ 40 wt% and
( )
n
TCI = IE × 1 +
i=1
RFi (13) MDEA 10 wt% + PZ 30 wt%).

where RF is the ratio factor for direct, indirect and working capital, i
being the items summarized in Table 6. 3.1.2. CO2 methanation and SNG upgrading units’ results
The CO2 methanation unit simulation results in terms of outlet gas
Table 6 compositions are summarized in Table 10.
Estimation of the total capital investment (TCI ) [71,72]. Based on the simulations and the present process design, material
and energy streams were estimated and summarized in Table 11.
Type Item (i ) Ratio Factor (RF )
In order to meet the pipeline quality standards, the CH4 mole
Direct cost 1 Purchased equipment (delivered) 1.00 fraction in the raw SNG of about 70% has to be increased to more than
2 Purchased equipment installation 0.47 90% in order to meet the natural gas grid requirements. Table 12
3 Piping 0.36 presents the technical features of the utilized membranes.
4 Instrumentation and Controls 0.68
A membrane’s size of 62 m2 was therefore required to achieve a
5 Electrical systems 0.11
6 Buildings (including services) 0.18 90% water separation, using Eq. (8). To achieve a 90% H2 separation,
7 Yard improvements 0.10 the size of the second membrane was estimated to 244 m2. The elec-
8 Service facilities 0.70 trical consumption of the compressor used to reach the working pres-
Indirect cost 9 Engineering and supervision 0.33 sure of the dehydration membrane is of importance (0.36 MWe ).
10 Construction expenses 0.41 In addition, the SNG was brought to 50 bar to meet the pressure
11 Legal expenses 0.04 pipelines, leading to a consumption of 0.25 MWe . It is worth mentioning
12 Contractor’s fee 0.22
that for some local or regional grid injections, this elevated pressure is
13 Contingency 0.44
14 Working Capital 0.89 not necessary, as these pipelines mostly operate in the pressure range of
4 to 40 bar.

8
R. Chauvy, et al. Applied Energy 260 (2020) 114249

Table 7
Economic assumptions for operating cost estimation (TPC ).
Item ( j ) Assumptions

1 Raw material Solvent: 1 €/kg(1); Catalyst: 90 €/kg(2); Process water: 1 €/ton(3); Demineralized water: 3 €/ton(4); Renewable
H2: onsite production(5); SNG selling price: 21 €/ton(6); O2 selling price: 87.4 €/ton(7); CO2 credit tax: 25.2
€/ton(8)
2 Utilities Cooling water: 0.025 €/ton(9); Electricity: 40 €/MWh(10); Steam: self-produced(11)
3 Operation and Operating labor and supervisory 60 labors/shift, 3 shift/day, 54,000 € per labor per year(12) + 20% of operating labor
maintenance labor
Maintenance and repairs 6% of capital investment
Operating supplies 15% of Maintenance and repairs
Laboratory charges 15% of operating labor
4 Depreciation Annual depreciation cost, with an assumption of a 20-year recovery period and 0 € salvage value, linear
5 General expenses 15% of total product cost

(1)
Amine solvent considered: PZ 30% + MDEA 10% (+60% water): 2.16 €/kg PZ × 0.3 + 1.7 €/kg MDEA × 0.1 + 0.001 €/kg H2O × 0.6 = 0.818 €/kg ≈ 1
€/kg solvent cost estimated from de Medeiros et al. [73].
(2)
Catalyst cost considered from own estimation.
(3)
Process water cost considered from Michailos et al. [74].
(4)
Demineralized water cost considered from Li et al. [75].
(5)
Renewable H2 considered produced onsite. Only the cost of demineralized water is taken into account in the calculation of TPC .
(6)
SNG selling price estimated from natural gas price (≈ 4.56 €/1000 ft3 in April 2019).
(7)
Oxygen selling price from Michailos et al. [74].
(8)
CO2 credit tax (€/ton) in April 2019, according to European Emission Allowances (EUA).
(9)
Cooling water cost considered from Michailos et al. [74].
(10)
Electricity considered from renewable energy (wind power). Cost considered from Glenk and Reichelstein [76] supported by www.eex.com.
(11)
Steam considered self-produced. Only the cost of process water is taken into account in the calculation of TPC .
(12)
Operating labor and supervisory labor costs considered from Zhang et al. [72].

Table 8 Table 10
Composition of the gas to be treated, washed-gas and produced CO2 (mol frac. Composition of the outlet streams (mol frac. Basis).
basis).
Component Inlet REA-1 REA-2 REA-3 REA-4 Raw-SNG SNG
Component Gas to be treated Washed-gas Produced CO2
CO2 19.9% 7.5% 4.3% 2.4% 1.5% 3.7% 3.7%
N2 64.7% 69.9% 123 ppm H2 79.9% 31.8% 19.0% 11.5% 8.1% 21.3% 3.4%
CO2 20.4% 2.2% 98.0% H2O 0.2% 40.5% 51.1% 57.4% 60.3% 0.3% Traces
O2 8.6% 9.3% 29 ppm CH4 0% 20.2% 25.6% 28.7% 30.2% 74.8% 92.9%
H2O 6.2% 18.5% 1.98% CO 0% Traces – – – – –
CO 1330 ppm 100 ppm 0.4 ppm
Total mol 1038.12 745.23 692.67 664.94 653.05 268.54 214.22
SO2 111 ppm 112 ppm 43 ppm
flow
NO 474 ppm 512 ppm 3 ppm
(kmol/
NO2 2 ppm 2 ppm 1 ppm
h)
MDEA 0 Traces Traces
Total mass 10.84 10.79 10.79 10.79 10.79 3.78 3.60
PZ 0 Traces Traces
flow (t/
Total mol flow (kmol/h) 1124 1040 211 h)
Total mass flow (t/h) 34.85 27.90 9.16

Table 11
Table 9 Material and energy consumptions of the PtG plant.
Optimum operating parameters and specific energy consumptions of the CO2
Indicator Specification Value
capture unit.
Indicator Specification Value CO2 methanation inputs H2 (t/h) 1.65
CO2 (t/h) 9.09
Operating conditions (L/G) vol,opt (m3/m3) 5.19 10−3 Energy consumptions CO2 compressor (MWe ) 0.14
Recycle compressors (MWe ) 0.19
L opt (m3/h) 128
Membrane compressor (MWe ) 0.36
Intercooling temp. (°C) 40
SNG compressor (MWe ) 0.25
Intercooling stage 8
Pump (MWe ) 0.07
Flash p (bar) 4
Turbine (MWe ) −1.06
CO 2, rich (mol/mol) 0.98
CO 2, lean (mol/mol) 0.33 PtG outputs SNG (t/h) 3.60
SNG Wobbe Index (MJ/m3) 46.72
Energy consumption Eregen (GJ/tCO2) 2.28 Total Output HHV (MW) 50.4

Efficiency Methanation efficiency ( CH4 ) 83.4


PtG plant HHV ( PtG ) 72.6
3.1.3. Process integration results
Overall energy utilization factor ( PtG ) 75.7
The methanation efficiency was estimated at 83.4%, while the
process efficiency of the PtG plant ( PtG ) equaled 65.5% (72.6% on HHV
basis), based on Eq.(9) and (10), respectively, with a comprehensive Table 5). These results are summarized in Table 11.
usage of excess heat and technical assumptions. The overall energy Stream data (temperature, composition, heat capacities, etc.) com-
utilization factor ( PtG ) reached 75.7%. A Wobbe Index of 46.72 MJ/m3 puted by Aspen Plus™ are available in the Supporting Information (see
was calculated, which is in the range of Wobbe Indices in Germany (see SI.4). A minimum pinch point temperature of 30 °C was defined for the

9
R. Chauvy, et al. Applied Energy 260 (2020) 114249

Table 12 the total product cost, it was estimated at 61.60 M€ per year. Fig. 6
Technical features of the membranes system. displays the operational expenses distribution, based on the previously
Parameter Dehydration membrane H2 separation membrane mentioned assumptions (see Table 7). The expected indirect revenues
were 407.9 € per ton SNG, considering SNG, oxygen and CO2 trading.
At present, the estimated cost of SNG is therefore 1587 €/ton SNG,
2
Membrane area (m ) 62 244
Feed pressure (bar) 35 20
about 115 €/MWh, which is in the cost range evaluated by Guilera et al.
Permeate pressure (bar) 1.1 1
Temperature (°C) 40 90
[2]. It is about 3.5 times higher than fossil natural gas (33 €/MWh in
Permeance (GPU) 1000 100 Germany [2]). The annual operating costs amount to around 7% of the
Compressor (MWe ) 0.36 – investment, which is in accordance with the values reported for cata-
lytic processes [78]. It is worth noting that the amortized CAPEX of the
electrolyzers is taken into account in “Hydrogen production”.
600 A sensitivity analysis was carried out regarding the parameters that
500
most influence the SNG cost, derived from Table 15. One input variable
at a time was changed to its low or high value, while the other variables
Temperature (°C)

400 were maintained at their base values. Fig. 7 illustrates the sensitivity
300 analysis.
The electricity price therefore has a huge influence on the cost of
200
SNG, especially due to the fact that H2 production derived directly from
100 it, represents about 70% of the cost of SNG. The additional expenses
and CAPEX, the electrolyzer efficiency, and the O2 selling price have an
0
0 2 4 6 8 10 12 14 influence higher than 10% on the final SNG cost. In particular, the in-
Heat load (MW) come obtained from the sale of oxygen in the PtG plant represents an
Hot composite curve Cold composite curve interesting economic incentive, especially in the current context of low
prices for carbon emissions trading (CO2 credit tax) that have an almost
Fig. 5. Hot and cold composite curves. negligible effect.

heat exchanger with gaseous streams [77]. 4. Conclusion and outlook


The total recovered heat from the plant amounts to about 13.25
MWth , which is available between 25 and 615 °C (see Fig. 5). A fraction The present work has assessed the production of SNG from in-
of the heat recovered at 170 °C can be brought to the reboiler of the CO2 dustrial CO2 in the context of PtG technology. The PtG plant was im-
capture unit, accounting for 5.75 MWth , so that the heat integration plemented in AspenTech’s software, both in Aspen HYSYS™ and Aspen
compensates the hot utility requirement of the CO2 capture unit. Plus™, to extract mass and energy balances in order to investigate its
In addition, the electricity produced in the steam turbine was used economic viability. An advanced CO2 capture process was proposed to
to cover internal demand (see Table 11). Thus, no external electrical treat 10% of a BAT cement plant’s flue gas. Together with renewable
requirement was required for both the CO2 methanation and SNG up- H2, they were converted to SNG through methanation reaction, pro-
grading units. The total external electrical requirement of the whole ducing 0.40 ton SNG per ton of captured CO2. In the suggested process
suggested process designed is therefore linked to the compressor used in design, a dry methane mole fraction of 92.9 mol.% in the final SNG was
the RVC configuration, equal to 0.90 MWe . achieved, together with a CO2 and H2 content of 3.7 mol.% and 3.4 mol.
%, respectively, which are the most critical aspects of the SNG quality
and compatibility.
3.2. Economic performances Systematic process-to-process analysis was investigated to reach
high energy efficiency and minimize utility costs. Thermal integration
Based on the simulation results, the capital investment and oper- led to an overall system HHV-based efficiency equal to 72.6%.
ating costs of the integrated process plant were evaluated. Table 13 lists As seen in this work, SNG is currently not competitive with natural
the estimated capital investment for the equipment. gas. The estimated cost of SNG was about 115 €/MWh, about 3.5 times
Table 14 presents the main costs for all the units. higher than fossil natural gas. Costs are mainly driven by the high initial
The TCI of the integrated process was therefore evaluated to investment costs, as well as the production of H2, which depends di-
166.85 M€ (excluding the capital investment of H2 production), where rectly on the price of renewable electricity. Thus, a reduction of the
the CO2 conversion unit itself represents 58%, mainly due to the electrolyzer investment costs combined with a higher electrolyzer ef-
complex network of heat exchangers that had been implemented to ficiency and higher revenues, could result in a profitable business case
integrate the heat. The final TCI was estimated at 804.92 M€, where for large-scale deployment of this PtG technology. In future scenarios,
about 79% was dedicated to the renewable production of H2. Regarding the cost of SNG can be therefore reduced. Specific costs for PEM tech-
nologies are for instance expected to fall from about 1200 €/kW in
Table 13 2017 to 500 €/kW in 2050 [40]. Furthermore, when applying a time-of-
Cost estimation of main equipment (M€). use retail electricity price of approximately 10 €/MWh, the costs of SNG
Main equipment CO2 Capture CO2 methanation Gas Upgrading decrease to about 40 €/MWh, which is really close to the current price
of fossil natural gas. Several studies also point out that with ongoing
Columns (absorber/stripper) 1.24 – – trends in 10–20 years, PtG might be economically profitable [33].
Reactors – 3.50 –
Moreover, in regions where a natural gas infrastructure exists, the ex-
Compressors 3.36 2.28 3.91
Turbine – 0.45 – isting network for grid gas injection is a major advantage of the PtG
Heat Exchangers (heaters/ 2.40 9.35 0.15 technology. By utilizing excess energy to produce hydrogen via water
coolers) electrolysis, energy can be stored and distributed in the existing system
Flash tanks 0.18 0.09 – for use when and where it is needed. Despite the fact that the use of
Membranes – – 0.68
(excess) renewable energy introduces a seasonal and daily component
Total Purchased equipment 7.18 16.22 4.74
cost (delivered) into H2 production, Gahleitner highlighted that the use of such fluctu-
ating power sources is satisfying, and is currently in use in a lot of PtG

10
R. Chauvy, et al. Applied Energy 260 (2020) 114249

Table 14
Estimation of the total capital investment (M€).
Main cost H2 production CO2 Capture CO2 methanation Gas Upgrading

(1)
Total Direct Cost 387.36 25.84 58.40 17.05
Total Indirect Cost 154.94 10.34 23.36 6.82
Fixed Capital Investment (FCI ) 542.30 36.17 81.76 23.88
Total Capital Investment (TCI ) 638.07 42.56 96.20 28.09

(1)
Calculation based on specific electrical power of approximatively 55.6 kWh per kg H2 and an investment cost of 1200 € per kW (installed) for the production of
40 ton per day of renewable H2 [49,76], and Table 6 to estimate the Total Direct Cost.

Fig. 6. Operational expenses in € per ton SNG.

Table 15 targets, and high renewable energy availability and penetration in the
Input variable for the sensitivity analysis. market. Additionally, several actions could be taken to foster the de-
Input variables Low value Base value High value
ployment of PtG technologies. A key action is the development and
deployment of cheap low carbon electricity, which is necessary to re-
(1)
Electricity price (€/MWh) 0 40 120 duce the costs for PtG. The transition to low-carbon depends on the cost
Electrolyser efficiency(2) (%) 65 75 85 for conventional fossil choices, such as the gas price. Thus, additional
Additional expenses & CAPEX(3) −30% Nominal +30%
taxes on fossil resources could promote a shift to PtG technologies.
CO2 credit tax(4) (€/ton) 0 25.2 50.4
Oxygen price(5) (€/ton) 43.7 87.4 131.1 Direct subsides is also a measure that can be used to improve the
business case for private investors. Creating a green hydrogen market
(1)
Electricity ranging from 0 €/MWh (free renewable electricity) to 120 would also be necessary, giving a premium in the selling price of hy-
€/MWh (own assumption). drogen. Finally, to overcome the seasonal component of PtG, nuclear,
(2)
Electrolyser efficiency commonly considered in the literature [74,76]. geothermal, biomass, and hydro energy are necessary, also increasing
(3)
Additional expenses and CAPEX accuracy with a ± 30% fluctuation. the flexibility of the whole system.
(4)
Electricity considered CO2 credit tax in April 2019, according to European
By applying these actions, combined with a policy penalizing new
Emission Allowances (EUA).
(5) investment in industries using fossil resources, the suggested process
Oxygen selling price from Michailos et al. [74], with a ± 50% fluctuation.
will likely play a certain role for the transition to a renewable network,
integrating large fractions of renewables that require balancing power
Electricity price
and seasonal energy storage, and introducing considerable flexibility
Additonal expenses & CAPEX into the energy system. Furthermore, additional energy and environ-
mental policy challenges can be solved by the enlargement of the per-
Electrolyser efficiency
centage of alternative fuels in the mobility or heating sector. In a
O₂ selling price longer-term perspective, with markets characterized by cheap elec-
CO₂ credit tax tricity and high fuel prices, PtG shall gradually eliminate fossil fuels,
transitioning to a low carbon economy. PtG may also have higher ac-
0 50 100 150 200 250 300 ceptance in society, denoting advantages over the existing alternative
SNG cost (€/MWh) storage technologies as well as over network expansion, representing a
non-negligible component in the future prospects of the technology.
Low value High value

Fig. 7. Sensitivity analysis on the cost of SNG in €/MWh (base cost 115 €/MWh
CRediT authorship contribution statement
SNG).

Remi Chauvy: Conceptualization, Methodology, Investigation,


pilot plants [79]. Validation, Writing - original draft, Writing - review & editing,
In the context of CCUS, the main drivers for methanation deploy- Visualization. Lionel Dubois: Methodology, Investigation, Validation,
ment are limited and/or unwanted CO2 storage, high CO2 reduction Writing - original draft, Writing - review & editing. Paul Lybaert:

11
R. Chauvy, et al. Applied Energy 260 (2020) 114249

Resources, Validation. Diane Thomas: Writing - review & editing, [19] Ditaranto M, Bakken J. Study of a full scale oxy-fuel cement rotary kiln. Int J
Supervision. Guy De Weireld: Validation, Writing - review & editing, Greenh Gas Control 2019;83:166–75. https://doi.org/10.1016/j.ijggc.2019.02.008.
[20] Voldsund M, Gardarsdottir SO, De Lena E, Pérez-Calvo JF, Jamali A, Berstad D,
Supervision. et al. Comparison of technologies for CO2 capture from cement production—Part 1:
Technical evaluation. Energies 2019;12. https://doi.org/10.3390/en12030559.
Declaration of Competing Interest [21] IEAGHG. Further assessment of emerging CO2 capture technologies for the power
sector and their potential to reduce costs; 2019.
[22] Abanades JC, Arias B, Lyngfelt A, Mattisson T, Wiley DE, Li H, et al. Emerging CO2
The authors declare that they have no known competing financial capture systems. Int J Greenh Gas Control 2015;40:126–66. https://doi.org/10.
interests or personal relationships that could have appeared to influ- 1016/j.ijggc.2015.04.018.
[23] Younas M, Sohail M, Kong LL, Bashir MJK, Sethupathi S. Feasibility of CO2 ad-
ence the work reported in this paper. sorption by solid adsorbents: a review on low-temperature systems. Int J Environ
Sci Technol 2016;13:1839–60. https://doi.org/10.1007/s13762-016-1008-1.
Acknowledgements [24] Criado YA, Arias B, Abanades JC. Calcium looping CO2 capture system for back-up
power plants. Energy Environ Sci 2017;10:1994–2004. https://doi.org/10.1039/
c7ee01505d.
The authors gratefully acknowledge the European Cement Research [25] Idem R, Supap T, Shi H, Gelowitz D, Ball M, Campbell C, et al. Practical experience
Academy (ECRA) for its technical and financial support. The authors in post-combustion CO2 capture using reactive solvents in large pilot and demon-
thank Marc Frère for his help and scientific guidance. stration plants. Int J Greenh Gas Control 2015;40:6–25. https://doi.org/10.1016/j.
ijggc.2015.06.005.
[26] Van Der Spek M. Methodological improvements to ex-ante techno-economic mod-
Appendix A. Supplementary material elling and uncertainty analysis of emerging CO2 capture technologies. Utrecht
University; 2017.
[27] Singh P, Van Swaaij WPM, (Wim) Brilman DWF. Energy efficient solvents for CO2
Supplementary data to this article can be found online at https:// absorption from flue gas: vapor liquid equilibrium and pilot plant study. Energy
doi.org/10.1016/j.apenergy.2019.114249. Procedia 2013;37:2021–46. https://doi.org/10.1016/j.egypro.2013.06.082.
[28] Le Moullec Y, Neveux T, Al Azki A, Chikukwa A, Hoff KA. Process modifications for
solvent-based post-combustion CO2 capture. Int J Greenh Gas Control
References 2014;31:96–112. https://doi.org/10.1016/j.ijggc.2014.09.024.
[29] Dubois L, Thomas D. Comparison of various configurations of the absorption-re-
[1] Zappa W, Junginger M, van den Broek M. Is a 100% renewable European power generation process using different solvents for the post-combustion CO2 capture
system feasible by 2050? Appl Energy 2019;233–234:1027–50. https://doi.org/10. applied to cement plant flue gases. Int J Greenh Gas Control 2018;69:20–35.
1016/j.apenergy.2018.08.109. https://doi.org/10.1016/j.ijggc.2017.12.004.
[2] Guilera J, Ramon Morante J, Andreu T. Economic viability of SNG production from [30] Rönsch S, Schneider J, Matthischke S, Schlüter M, Götz M, Lefebvre J, et al. Review
power and CO2. Energy Convers Manag 2018;162:218–24. https://doi.org/10. on methanation – from fundamentals to current projects. Fuel 2016;166:276–96.
1016/j.enconman.2018.02.037. https://doi.org/10.1016/j.fuel.2015.10.111.
[3] Wang L, Rao M, Diethelm S, Lin T-E, Zhang H, Hagen A, et al. Power-to-methane via [31] Chauvy R, Meunier N, Thomas D, De Weireld G. Selecting emerging CO2 utilization
co-electrolysis of H2O and CO2: The effects of pressurized operation and internal products for short- to mid-term deployment. Appl Energy 2019;236:662–80.
methanation. Appl Energy 2019;250:1432–45. https://doi.org/10.1016/j.apenergy. https://doi.org/10.1016/j.apenergy.2018.11.096.
2019.05.098. [32] Artz J, Müller TE, Thenert K, Kleinekorte J, Meys R, Sternberg A, et al. Sustainable
[4] Zu MY, Liu PF, Wang C, Wang Y, Zheng LR, Zhang B, et al. Bimetallic carbide as a conversion of carbon dioxide: an integrated review of catalysis and life cycle as-
stable hydrogen evolution catalyst in harsh acidic water. ACS Energy Lett sessment. Chem Rev 2018;118:434–504. https://doi.org/10.1021/acs.chemrev.
2018;3:78–84. https://doi.org/10.1021/acsenergylett.7b00990. 7b00435.
[5] Nagasawa K, Davidson FT, Lloyd AC, Webber ME. Impacts of renewable hydrogen [33] Lewandowska-Bernat A, Desideri U. Opportunities of power-to-gas technology in
production from wind energy in electricity markets on potential hydrogen demand different energy systems architectures. Appl Energy 2018;228:57–67. https://doi.
for light-duty vehicles. Appl Energy 2019;235:1001–16. https://doi.org/10.1016/j. org/10.1016/j.apenergy.2018.06.001.
apenergy.2018.10.067. [34] European power to gas platform. Online; n.d. http://europeanpowertogas.com/
[6] Mattioda RA, Antonucci V, Azzaro-Pantel C, Cao H, Cellura M, De Felice F, et al. [accessed March 4, 2019].
Hydrogen economy: supply chain, life cycle analysis and energy transition for [35] Bailera M, Lisbona P, Romeo LM, Espatolero S. Power to Gas projects review: lab,
sustainability. 1st ed. Elsevier Ltd.; 2017. pilot and demo plants for storing renewable energy and CO2. Renew Sustain Energy
[7] Quarton CJ, Samsatli S. Power-to-gas for injection into the gas grid: What can we Rev 2017;69:292–312. https://doi.org/10.1016/j.rser.2016.11.130.
learn from real-life projects, economic assessments and systems modelling? Renew [36] Wulf C, Linßen J, Zapp P. Review of power-to-gas projects in Europe. Energy
Sustain Energy Rev 2018;98:302–16. https://doi.org/10.1016/j.rser.2018.09.007. Procedia 2018;155:367–78. https://doi.org/10.1016/j.egypro.2018.11.041.
[8] Ghaib K, Ben-Fares FZ. Power-to-Methane: a state-of-the-art review. Renew Sustain [37] Su X, Xu J, Liang B, Duan H, Hou B, Huang Y. Catalytic carbon dioxide hydro-
Energy Rev 2018;81:433–46. https://doi.org/10.1016/j.rser.2017.08.004. genation to methane: a review of recent studies. J Energy Chem 2016;25:553–65.
[9] Salomone F, Giglio E, Ferrero D, Santarelli M, Pirone R, Bensaid S. Techno-eco- https://doi.org/10.1016/j.jechem.2016.03.009.
nomic modelling of a Power-to-Gas system based on SOEC electrolysis and CO2 [38] Miguel CV, Soria MA, Mendes A, Madeira LM. A sorptive reactor for CO2 capture
methanation in a RES-based electric grid. Chem Eng J 2018:1–20. https://doi.org/ and conversion to renewable methane. Chem Eng J 2017;322:590–602. https://doi.
10.1016/j.cej.2018.10.170. org/10.1016/j.cej.2017.04.024.
[10] Toro C, Sciubba E. Sabatier based power-to-gas system: heat exchange network [39] Eveloy V, Gebreegziabher T. A review of projected Power-to-Gas deployment sce-
design and thermoeconomic analysis. Appl Energy 2018;229:1181–90. https://doi. narios. Energies 2018;11. https://doi.org/10.3390/en11071824.
org/10.1016/j.apenergy.2018.08.036. [40] Thema M, Bauer F, Sterner M. Power-to-Gas: electrolysis and methanation status
[11] Gutiérrez-Martín F, Rodríguez-Antón LM. Power-to-SNG technologies by hydro- review. Renew Sustain Energy Rev 2019;112:775–87. https://doi.org/10.1016/j.
genation of CO2 and biomass resources: a comparative chemical engineering pro- rser.2019.06.030.
cess analysis. Int J Hydrogen Energy 2018:1–10. https://doi.org/10.1016/j. [41] Becker WL, Penev M, Braun RJ. Production of synthetic natural gas from carbon
ijhydene.2018.09.168. dioxide and renewably generated hydrogen: a techno-economic Analysis of a
[12] Lehner M, Tichler R, Steinmüller H, Koppe M. Power-to-Gas: technology and Power-to-Gas strategy. J Energy Resour Technol 2018;141:021901. https://doi.org/
business models. Cham: Springer International Publishing; 2014. doi: 10.1007/978- 10.1115/1.4041381.
3-319-03995-4. [42] Morosanu EA, Saldivia A, Antonini M, Bensaid S. Process modeling of an innovative
[13] Aresta M, Dibenedetto A, Angelini A. The changing paradigm in CO2 utilization. J power to LNG demonstration plant. Energy Fuels 2018;32:8868–79. https://doi.
CO2 Util 2013;3–4:65–73. https://doi.org/10.1016/j.jcou.2013.08.001. org/10.1021/acs.energyfuels.8b01078.
[14] Benhelal E, Zahedi G, Shamsaei E, Bahadori A. Global strategies and potentials to [43] Meunier N, Chauvy R, Mouhoubi S, Thomas D, De Weireld G. Alternative produc-
curb CO2 emissions in cement industry. J Clean Prod 2013;51:142–61. https://doi. tion of methanol from industrial CO2. Renew Energy 2020;146:1192–203. https://
org/10.1016/j.jclepro.2012.10.049. doi.org/10.1016/j.renene.2019.07.010.
[15] Corcoran R. Technical report – ECRA project – report about CO2 reuse from cement [44] Song Y, Chen C-C. Symmetric electrolyte nonrandom two-liquid activity coefficient
production/MeOH and methane synthesis. Dublin; 2013. model. Ind Eng Chem Res 2009;48:7788–97. https://doi.org/10.1021/ie9004578.
[16] Meunier N, Laribi S, Dubois L, Thomas D, De Weireld G. CO2 capture in cement [45] Peng D-Y, Robinson DB. A new two-constant equation of state. Ind Eng Chem
production and re-use: first step for the optimization of the overall process. Energy Fundam 1976;15:59–64. https://doi.org/10.1021/i160057a011.
Procedia 2014;63:6492–503. https://doi.org/10.1016/j.egypro.2014.11.685. [46] Laribi S, Dubois L, De Weireld G, Thomas D. Study of the post-combustion CO2
[17] Granados DA, Chejne F, Mejía JM. Oxy-fuel combustion as an alternative for in- capture process by absorption-regeneration using amine solvents applied to cement
creasing lime production in rotary kilns. Appl Energy 2015;158:107–17. https:// plant flue gases with high CO2 contents. Int J Greenh Gas Control 2019;90:102799.
doi.org/10.1016/j.apenergy.2015.07.075. https://doi.org/10.1016/j.ijggc.2019.102799.
[18] Carrasco-Maldonado F, Spörl R, Fleiger K, Hoenig V, Maier J, Scheffknecht G. Oxy- [47] Muradov N. Liberating energy from carbon: introduction to decarbonization vol.
fuel combustion technology for cement production - State of the art research and 22. New York (NY): Springer New York; 2014. doi: 10.1007/978-1-4939-0545-4.
technology development. Int J Greenh Gas Control 2016;45:189–99. https://doi. [48] IRENA. Hydrogen from renewable power – technology outlook for the energy
org/10.1016/j.ijggc.2015.12.014. transition. Abu Dhabi; 2018. doi: 978-92-9260-077-8.

12
R. Chauvy, et al. Applied Energy 260 (2020) 114249

[49] Schmidt O, Gambhir A, Staffell I, Hawkes A, Nelson J, Few S. Future cost and through the rubbery polymer PEBAX® 1074. J Memb Sci 2009;338:11–6. https://
performance of water electrolysis: an expert elicitation study. Int J Hydrogen doi.org/10.1016/j.memsci.2009.03.051.
Energy 2017;42:30470–92. https://doi.org/10.1016/j.ijhydene.2017.10.045. [65] Lin H, Thompson SM, Serbanescu-Martin A, Wijmans JG, Amo KD, Lokhandwala
[50] Dubois L, Thomas D. Optimization of the post-combustion CO2 capture process KA, et al. Dehydration of natural gas using membranes. Part II: Sweep/counter-
applied to cement plant flue gases: parametric study with different solvents and current design and field test. J Memb Sci 2013;432:106–14. https://doi.org/10.
configurations combined with intercooling. Int conf greenh gas control technol, 1016/j.memsci.2012.12.049.
Melbourne. 2018. [66] Baker RW. Gas separation. Membr technol appl 2nd ed.Chichester (UK): John Wiley
[51] Knudsen JN, Jensen JN, Vilhelmsen PJ, Biede O. Experience with CO2 capture from & Sons, Ltd; 2004. p. 301–53. https://doi.org/10.1002/0470020393.ch8.
coal flue gas in pilot-scale: testing of different amine solvents. Energy Procedia [67] Sanders DF, Smith ZP, Guo R, Robeson LM, McGrath JE, Paul DR, et al. Energy-
2009;1:783–90. https://doi.org/10.1016/j.egypro.2009.01.104. efficient polymeric gas separation membranes for a sustainable future: a review.
[52] IEAGHG. Gaseous emissions from amine based post-combustion CO2 capture pro- Polymer (Guildf) 2013;54:4729–61. https://doi.org/10.1016/j.polymer.2013.05.
cesses and various methods for their deep removal; 2012. 075.
[53] Dubois L, Thomas D. Simulations of various Configurations of the Post-combustion [68] Scholz M, Frank B, Stockmeier F, Falß S, Wessling M. Techno-economic analysis of
CO2 capture process applied to a cement plant flue gas: parametric study with hybrid processes for biogas upgrading. Ind Eng Chem Res 2013;52:16929–38.
different solvents. Energy Procedia 2017;114:1409–23. https://doi.org/10.1016/j. https://doi.org/10.1021/ie402660s.
egypro.2017.03.1265. [69] Fendt S, Buttler A, Gaderer M, Spliethoff H. Comparison of synthetic natural gas
[54] Bremer J, Rätze KHG, Sundmacher K. CO2 methanation: optimal start-up control of production pathways for the storage of renewable energy. Wiley Interdiscip Rev
a fixed-bed reactor for power-to-gas applications. AIChE J 2017;63:23–31. https:// Energy Environ 2016;5:327–50. https://doi.org/10.1002/wene.189.
doi.org/10.1002/aic.15496. [70] Molino A, Migliori M, Ding Y, Bikson B, Giordano G, Braccio G. Biogas upgrading
[55] Gao J, Wang Y, Ping Y, Hu D, Xu G, Gu F, et al. A thermodynamic analysis of via membrane process: modelling of pilot plant scale and the end uses for the grid
methanation reactions of carbon oxides for the production of synthetic natural gas. injection. Fuel 2013;107:585–92. https://doi.org/10.1016/j.fuel.2012.10.058.
RSC Adv 2012;2:2358. https://doi.org/10.1039/c2ra00632d. [71] Peters MS, Timmerhaus KD. Plant design & economics for chemical engineers.
[56] Schildhauer TJ, Biollaz SMA. Synthetic natural gas from coal, dry biomass, and McGraw-Hill Publishing Company; 1991.
Power-to-Gas applications. Hoboken (NJ, USA): John Wiley & Sons, Inc.; 2016. doi: [72] Zhang C, Gao R, Jun K-W, Kim SK, Hwang S-M, Park H-G, et al. Direct conversion of
10.1002/9781119191339. carbon dioxide to liquid fuels and synthetic natural gas using renewable power:
[57] Xu J, Froment GF. Methane steam reforming, methanation and water-gas shift: I. techno-economic analysis. J CO2 Util 2019;34:293–302. https://doi.org/10.1016/j.
Intrinsic kinetics. AIChE J 1989;35:88–96. https://doi.org/10.1002/aic. jcou.2019.07.005.
690350109. [73] de Medeiros JL, de Oliveira Arinelli L, Teixeira AM, Araújo O de QF. Offshore
[58] Kao YL, Lee PH, Tseng YT, Chien IL, Ward JD. Design, control and comparison of processing of CO2-rich natural gas with supersonic separator. Springer International
fixed-bed methanation reactor systems for the production of substitute natural gas. Publishing; 2019. doi: 10.1007/978-3-030-04006-2.
J Taiwan Inst Chem Eng 2014;45:2346–57. https://doi.org/10.1016/j.jtice.2014. [74] Michailos S, McCord S, Sick V, Stokes G, Styring P. Dimethyl ether synthesis via
06.024. captured CO2 hydrogenation within the power to liquids concept: A techno-eco-
[59] Schaaf T, Grünig J, Schuster MR, Rothenfluh T, Orth A. Methanation of CO2 – nomic assessment. Energy Convers Manag 2019;184:262–76. https://doi.org/10.
storage of renewable energy in a gas distribution system. Energy Sustain Soc 1016/j.enconman.2019.01.046.
2014;4:1–14. https://doi.org/10.1186/s13705-014-0029-1. [75] Li K, Leigh W, Feron P, Yu H, Tade M. Systematic study of aqueous mono-
[60] Götz M, Lefebvre J, Mörs F, McDaniel Koch A, Graf F, Bajohr S, et al. Renewable ethanolamine (MEA)-based CO2 capture process: techno-economic assessment of
Power-to-Gas: a technological and economic review. Renew Energy the MEA process and its improvements. Appl Energy 2016;165:648–59. https://doi.
2016;85:1371–90. https://doi.org/10.1016/j.renene.2015.07.066. org/10.1016/j.apenergy.2015.12.109.
[61] Ducamp J, Bengaouer A, Baurens P, Fechete I, Turek P, Garin F. Statu quo sur la [76] Glenk G, Reichelstein S. Economics of converting renewable power to hydrogen.
méthanation du dioxyde de carbone: une revue de la littérature. Comptes Rendus Nat Energy 2019. https://doi.org/10.1038/s41560-019-0326-1.
Chim 2018;21:427–69. https://doi.org/10.1016/j.crci.2017.07.005. [77] Bejan A, Tsatsaronis G, Moran M. Thermal design and optimization. 1st ed. Wiley-
[62] Lin H, Thompson SM, Serbanescu-Martin A, Wijmans JG, Amo KD, Lokhandwala Interscience; 1996.
KA, et al. Dehydration of natural gas using membranes. Part I: Composite mem- [78] Gutiérrez-Martín F, Rodríguez-Antón LM. Power-to-SNG technology for energy
branes. J Memb Sci 2012;413–414:70–81. https://doi.org/10.1016/j.memsci.2012. storage at large scales. Int J Hydrogen Energy 2016;41:19290–303. https://doi.org/
04.009. 10.1016/j.ijhydene.2016.07.097.
[63] Sijbesma H, Nymeijer K, van Marwijk R, Heijboer R, Potreck J, Wessling M. Flue gas [79] Gahleitner G. Hydrogen from renewable electricity: an international review of
dehydration using polymer membranes. J Memb Sci 2008;313:263–76. https://doi. power-to-gas pilot plants for stationary applications. Int J Hydrogen Energy
org/10.1016/j.memsci.2008.01.024. 2013;38:2039–61. https://doi.org/10.1016/j.ijhydene.2012.12.010.
[64] Potreck J, Nijmeijer K, Kosinski T, Wessling M. Mixed water vapor/gas transport

13

You might also like