Project Detail
Project Detail
DEVELOPER:-
M/S NANAL HYDRO POWER
1
CONSULTANCY PVT. LTD.
VARDAAN BUILDING, BELOW GITA MANDIR,
TUTIKANDI, SHIMLA – 171004 (H.P.)
INTRODUCTION
Hysrund SHP (3.30 MW) located in Tehsil Churah,
Distt. Chamba (H.P.) was allotted to M/s Nanal Hydro
Power Consultancy Pvt. Ltd. on boot basis. The main
components of the project such as (Desilting Tank,
Water conductor system, Forebay and Penstock) are
underground involving higher the construction cost.
Initially the Desilting Tank, Forebay and Penstock
were open structures, but due to steep terrain and non
availability of open space adjacent to HRT, the
Geological consultant recommended underground
structures. The cost of construction envisaged in the
approved DPR was Rs. 2788/- Lakhs, exceeded to Rs.
3915/- Lakhs. 2
Details of Project Structures from
Intake to Tail Race
PROJECT
Proposed Hysrund hydroelectric project is a run - of - the
river type development on Joiner Khad, tributary of Baira
River which in turn is a tributary of Ravi River. The
joiner khad is a perineal stream (Glassier Fed).
Project structures
The civil engineering structures of this project are
discussed as below:-
Trench weir
For diversion of Joiner khad inflows, drop type trench
weir is constructed at E1+ 1400.00 m. The size of weir is
25.00 m long and 1.80 wide to draw a design discharge of
6.15 cumecs. Shingle flushing system is provided at
intake chamber to flush the shingle back into khad
through Shingle flushing conduit.
3
Desilting arrangement
A underground desilting tank is provided at the end of
a 206 m long feeder tunnel downstream of trench
weir. The desilting tank is designed to exclude all silt
particles down to 0.25 mm size. The desilting tank
comprise one chamber of size 52m x 6.00 m x 6.20 m
with central silt gutter type silt flushing system.
Water conductor system
All the components are shown in the General Layout plan on next slide.
General Layout Plan
8
PHOTOGRAPHS
9
10
11
12
13
HYDROLOGY
POWER & ENERGY GENERATION IN 75% DEPENDABLE YEAR AS PER
APPROVED DPR
14
FINANCIAL STATUS AS ON ENDING NOV, 2023
FOR THE CONSTRUCTION OF THE PROJECT A TERM LOAN WAS ARRANGED FROM HP STATE CO
OPERATIVE BANK LIMITED, SHIMLA, THE PRESENT OUTSTANDING DETAILS OF LOAN & EQUITY A/W
LIABILITIES ARE SHOWN AS UNDER
Amount
S.No. Description
(in Crores)
Outstanding Term Loan including interest as on
1 31.12
ending 11/2023
Equity including unsecured loan as on November,
2 12.10
2023
Total 43.22
Net Balance 43.22
15
Annex-G4
HYSRUND SHEP(3.30MW)
Generation Details Jan-2023 to Dec-2023 - (Breakdown detail)
Generation (kwh)
Sr No Month Remarks
Unit#1 Unit#2 Total
1 2 3 4 5 (3+4) 6
Due to Low water
1 Jan-23 0 203110 203110 level, Grid Failure &
Earth Fault
Due to Low water
2 Feb-23 0 528493 528493 level, Grid Failure &
Earth Fault
3 Mar-23 30 531344 531374
Due to Grid Failure and
4 Apr-23 325991 770200 1096191 low discharge (29:29:00
hrs)
Due to Grid Failure, Due to
flood at weir site & 33KV
5 May-23 962590 702520 1665110 cable damage (48:04:00
hrs)
Due to flood debris in
6 Jun-23 867485 730665 1598150 Joiner river(122:58:00)
Due to Grid Failure and
7 Jul-23 344565 498255 842820 Flood in Joiner Nallah
(380:42:00 hrs)
Due to Grid Failure and
8 Aug-23 839958 925010 1764968 Flood in Joiner Nallah
(70:29:00 hrs)
9 Sep-23 943983 277709 1221692
10 Oct-23 592917 10296 603213
11 Nov-23 309613 896 310509
12 Dec-23 110802 110802
16
Total 5297934 5178498 10476432