Project Name:-

Hysrund SHP (3.30 MW),


Tehsil Churah, Distt. Chamba (H.P.)

DEVELOPER:-
M/S NANAL HYDRO POWER
1
CONSULTANCY PVT. LTD.
VARDAAN BUILDING, BELOW GITA MANDIR,
TUTIKANDI, SHIMLA – 171004 (H.P.)
INTRODUCTION
Hysrund SHP (3.30 MW) located in Tehsil Churah,
Distt. Chamba (H.P.) was allotted to M/s Nanal Hydro
Power Consultancy Pvt. Ltd. on boot basis. The main
components of the project such as (Desilting Tank,
Water conductor system, Forebay and Penstock) are
underground involving higher the construction cost.
Initially the Desilting Tank, Forebay and Penstock
were open structures, but due to steep terrain and non
availability of open space adjacent to HRT, the
Geological consultant recommended underground
structures. The cost of construction envisaged in the
approved DPR was Rs. 2788/- Lakhs, exceeded to Rs.
3915/- Lakhs. 2
Details of Project Structures from
Intake to Tail Race
PROJECT
Proposed Hysrund hydroelectric project is a run - of - the
river type development on Joiner Khad, tributary of Baira
River which in turn is a tributary of Ravi River. The
joiner khad is a perineal stream (Glassier Fed).
 Project structures
The civil engineering structures of this project are
discussed as below:-
 Trench weir
For diversion of Joiner khad inflows, drop type trench
weir is constructed at E1+ 1400.00 m. The size of weir is
25.00 m long and 1.80 wide to draw a design discharge of
6.15 cumecs. Shingle flushing system is provided at
intake chamber to flush the shingle back into khad
through Shingle flushing conduit.
3
 Desilting arrangement
A underground desilting tank is provided at the end of
a 206 m long feeder tunnel downstream of trench
weir. The desilting tank is designed to exclude all silt
particles down to 0.25 mm size. The desilting tank
comprise one chamber of size 52m x 6.00 m x 6.20 m
with central silt gutter type silt flushing system.
 Water conductor system

For carrying the inflows from desilting tank to forebay


power tunnel is provided. The length of power tunnel
is 1288 m. The water conductor system carry design
discharge of 6.15 cumec at 2.03 m/sec velocity with a
bed slope of 1:750. 4
Forebay
At the end of water conductor system, an underground
forebay is provided to cater for the sudden
acceptance/rejection of load. The capacity of forebay is +
1200 cum to provide peaking/balancing storage for +3
minutes. The size of forebay has been proposed at 120 m
x 6.00 m x 4.00 m rectangular and it will be provided
with suitable spilling arrangement.
 Penstock
The water from forebay will be led to power house
through a underground penstock of 1300 mm diameter
and ± 125 m long. The penstock pipe is fabricated from
steel plates confirming to IS 2062 with welded joints.
Suitable anchor blocks are provided to support the
penstock pipe. The penstock pipe carry the design
discharge of 6.15 cumecs at 4.33 m/sec velocity. Inlet
Valve is provided to regulate the flow to power house.
The length of main penstock will be + 125 m, which
bifurcate near power house into two branch penstocks to
feed two turbines.
5
Power house
A surface power house is provided on left bank
of Joiner khad with normal tail water level at E1 +
1330.00 m. The power house have two no’s,
horizontal axis Francis turbines driven generating
units of 1650 KW each. The outflow from turbine
shall be led through a tail race channel of RCC box
section to Joiner khad. A switchyard is provided
along the side of power house building.
The power generated from this project is
evacuated in joint mode with Upper Joiner
SHEP(12MW) to HPSEBL sub-station at Kurthala
at about 15.50 Km distance. On the suggestion by
upper joiner consultant a joint pooling station at
Ganed has been established to record the generation
from upper joiner and Hysrund Project before
feeding into the joint mode evacuation system. 6
DEVIATION REPORT OF FEATURES IN
HYSRUND SHEP
Description As per DPR As Built Remarks

Trench Weir 25.00mlongx1.50m wide 25.00m long x 1.80m Width increased by


wide designer

Desilting Arrangement (60.00mx5.00mx5.50m) (52.00mx6.00mx6.20m) Changed at detail design


with inlet and outlet excluding inlet and outlet stage
transition – Open transitions –
structure Underground structure
Water conductor system (1.90mx2.10m) D-Shaped (1.80mx2.10m) D-shaped Changed by designer
HRT-1032mlong HRT-1288 m long

Forebay (120mx5.0x4.00m) – (120x6x4)m - Changed at detail design


Underground structure Underground structure stage

Power House Underground ( Surface (30.60x10.60) Changed by geologist as


30x8.50x13) m per site conditions

Tail Race 1.80m, D-shaped, 50 m (1.80x1.80) m RCC Changed by geologist as


long conduit, 35 m long per site conditions 7

All the components are shown in the General Layout plan on next slide.
General Layout Plan

8
PHOTOGRAPHS

9
10
11
12
13
HYDROLOGY
POWER & ENERGY GENERATION IN 75% DEPENDABLE YEAR AS PER
APPROVED DPR

14
FINANCIAL STATUS AS ON ENDING NOV, 2023
FOR THE CONSTRUCTION OF THE PROJECT A TERM LOAN WAS ARRANGED FROM HP STATE CO
OPERATIVE BANK LIMITED, SHIMLA, THE PRESENT OUTSTANDING DETAILS OF LOAN & EQUITY A/W
LIABILITIES ARE SHOWN AS UNDER

Amount
S.No. Description
(in Crores)
Outstanding Term Loan including interest as on
1 31.12
ending 11/2023
Equity including unsecured loan as on November,
2 12.10
2023
Total 43.22
Net Balance 43.22

1. Present cost of the project ending November, 2023 = 43.22 Crores


2. Assured Revenue at new rates with trading of power in open market Rs. (5.00/kwh)
and with saleable energy of 11.66 MU = 5.83 Crores
3. Monthly O&M Charges about Rs. 7 Lakhs per month = 84 Lakhs
4. Net revenue generated = 5.83 – 84 = 4.99 Crores
5. The present cost of construction as approved by HPERC is Rs. 11.5 crores per MW.

15
Annex-G4

HYSRUND SHEP(3.30MW)
Generation Details Jan-2023 to Dec-2023 - (Breakdown detail)
Generation (kwh)
Sr No Month Remarks
Unit#1 Unit#2 Total
1 2 3 4 5 (3+4) 6
Due to Low water
1 Jan-23 0 203110 203110 level, Grid Failure &
Earth Fault
Due to Low water
2 Feb-23 0 528493 528493 level, Grid Failure &
Earth Fault
3 Mar-23 30 531344 531374
Due to Grid Failure and
4 Apr-23 325991 770200 1096191 low discharge (29:29:00
hrs)
Due to Grid Failure, Due to
flood at weir site & 33KV
5 May-23 962590 702520 1665110 cable damage (48:04:00
hrs)
Due to flood debris in
6 Jun-23 867485 730665 1598150 Joiner river(122:58:00)
Due to Grid Failure and
7 Jul-23 344565 498255 842820 Flood in Joiner Nallah
(380:42:00 hrs)
Due to Grid Failure and
8 Aug-23 839958 925010 1764968 Flood in Joiner Nallah
(70:29:00 hrs)
9 Sep-23 943983 277709 1221692
10 Oct-23 592917 10296 603213
11 Nov-23 309613 896 310509
12 Dec-23 110802 110802
16
Total 5297934 5178498 10476432