1.0 OBJECTIVE
The purpose of this method shall be used for the construction of concrete structures.
2.1.1 Cement
The cement to be used shall be from an approved manufacturer described. Under
Ordinary Portland Cement, Rapid Hardening Portland Cement, Moderate Sulphate
Resisting Portland Cement and Sulphate Resisting Portland Cement.
Transportation of the cement to the site shall be in a covered vehicle to protect water
again. Storages of the cement shall be inside the waterproof store or in silo for the
material delivered in bulk.
2.1.2 Aggregate
Aggregates shall be naturally occurring sand, gravel, or stone, washed or unwashed which
comply with the specification and obtained from a source approved by the Engineers.
Aggregates shall be free from adhering coatings and shall not contain any harmful
material that affects the strength, durability, and impermeability of the concrete.
Separate storage shall be provided for each different size of aggregates used and shall be
handled and stored to minimize segregation and contamination.
2.1.3 Water
METHOD OF STATEMENT
Water shall be cleaned and free from material deleterious to concrete in the plastic and
shall comply with the specification requirement. The source of water shall obtain approval
from the Engineers.
2.1.4 Admixtures
Approved admixtures may be used in the concrete mixed if required by the Engineer’s or
Clients.
All requirements and sampling, acceptance test, uniformity tests, independent test,
chloride content, information provided by manufactured including compliance certificates
and marking shall be in accordance with specification.
Cold worked and hot rolled bar shall not be straightened once have been bent. In case to
bent mild steel reinforcement already cast in concrete, the internal radius of bend shall be
not less than twice the diameter of bar.
Steel reinforcement shall be placed according to the number, size, length, form and
position as specified on drawing.
All intersecting bars shall be tied together with binding wire. Spacer from concrete blocks
shall be placed between bars and formworks with the thickness of the spacer block as
specified on drawings.
Completed rebar shall be inspected by the Engineer’s for the approval prior to place with
concrete.
2.2 Formwork
2.2.1 The formwork shall be so erected to comply with the following requirements: -
2.2.2 The formwork material shall be correctly selected in compliance with the provision of the
finished surface in the specification.
2.2.3 Where applicable, the inside surface of forms shall be coated with mould oil to prevent the
adhesion of concrete.
2.2.4 The removal of the falsework and formwork shall be carried out according to
specifications. Where necessary, the formwork shall be so arranged that the soffit from,
METHOD OF STATEMENT
properly supported, can be retained in position for such period as may be required by the
condition of maturing concrete or the specification.
2.2.5 After the removal of the formwork, the formwork components shall be cleaned and made
good for the next stage of work.