. POWER POWERCON Private Limited Company
— ee JN ANAT POAT PVA TTUNC
Yeka Sub City Kebele 11/12 House No909 — Tel. 0911-526656 — Addis Ababa, Ethiopia
Ref. No.: - AKKRP/O2/1158/16,
Date:- 20" of November, 2023
To: - The Resident Engineer
Ze G &Y Engineering Consult PLC
Ref:- Dabat-Keraker-Ketema Nigus Road Project; Contract 2:- Ajire-Keraker-Ketema Nigus
Subject: - Regarding Draft Minutes of Meeting
CC- ERA Gondar Project Management Office
Encl: - 12 pages of draft minutes of meeting
Dear Sirs,
In response to your letter G&Y/Aj-Ke/167/23 dated November 16th, 2023, regarding the
draft minutes of the meeting that was recorded at Gonder Area Construction Project
Management Office on the assessment of security improvement and the possibility of
resuming Project Activity, this is to provide you our comment on the recorded meeting
after the site visit of the referenced Project on November 8 & 9, 2023.
As a result, we have gone through and examined your record to determine if any
additional comments or corrections are needed but is acceptable for final. Aside from the
raised records, the site visit was also convoyed with military personnel across Dabat
woreda, and an armed engagement between federal forces and rebels is still ongoing at
approximately Km 22 and ahead. Meanwhile, the contractor will seek solutions to the
apparent impossibilities that have been imposed on him.
Your consideration on the Subject Matter is highly appreciated.
Sincerely Yours,
incerely Ves.
1
KS
ce
4 The General Manager, Powercon ple, Addis Abeba
+ Project file, Ajire
Tel-251-011-662-50-98/251-0930-01-40-43- Fax. 251-011-662-50-98a Gc yV ENGINEERING
. ANE Deb O7eF CONSULT PLC
'WE GO ABOVE AND BEYOND ON EVERY JOB, PERIOD!
Date: /6 / /, /20,23
Ref. No fe Lez
To: Ethiopian Roads Administration (ERA)
Gonder Area Construction Project Management Office
Gonder, Ethiopia
Re: — Consultancy Services for Continuation of Construction Supervision of Dabat Keraker —
Ketema Nigus Road Project; Contract 2: Ajire — Keraker — Ketema Nigus
Subject: Sending Draft Minutes of Meeting
Dear Sir,
Attached hereby please find Draft Minutes of Meeting which is record of the meeting conducted on
November 10, 2023 at Gonder Area Construction Project Management Office, Gondar in respect of
Resumption of Project Activities, for your review and comments if any.
Sincerely yours,
General
1 pages of Minutes of Meeting
» POWERCON PLC in JV with Tesfaye Legesse Construction
P Addis Ababa. Ethiopia
re
oho aPetppayeyge
omunn
raocwe op TE fis
rom me
theme hea i
AG DA__ Ethiopian Roads Administration
‘Minutes of Meeting on Resumption of Project Activities
_ _ Contract Details
Procurement Ref. No. : | Constract Description:
W/13/ICB/OC/GOE/2010 EFY | Consultancy Service for the Construction
Supervision of Dabat-Keraker-Ketema Nigus
Design and Build Road Project; Contract 2:
Ajire - Keraker - ketema Nigus
Funded By: Government of the Federal | Contract Value:
Democratic Republic of Ethiopia | ETB: 1,158,659,797.00 (including 15% VAT)
(FDRE)
Employer: Ethiopian Roads Administration | Commencement date: September 21, 2018
(ERA)
Contractor: POWERCON PLC in JV with | Contract duration: — 1095 Calendar Days
Tesfaye Legesse Construction
furs}
Consultant: _G & Y Engineering Consult Pic. | Revised Completion date: November 25,
2023.
Place, Date & Time of Meeting
‘Venue: Gonder Area Construction Project Date: November 10, 2023
Management Office, Gondar Time: 2:30 AM
Participants
Name Organization Position Signature
Ato Daniel Nigusse ERA, Gonder PMO. Team Leader
Ato YosefGoshu | ERA _ Senior Engineer
‘Ato Mesfin Kebede | ERA Project Engineer
‘Ato Mitiku Tefera. | G&YEngineering __| Assistant Resident Engineer
Consult Ple.
Ato Addis Getahun | POWERCON _ Project Manager ead
‘The meeting was held following the Employer's call for tripartite meeting; and, the purpose of
the meeting is to discuss on pertinent project issues and actions required to resume the project
activities. The following agenda are addressed during the discussions.
1. Introduction
2. Joint Condition Survey Required to Resume Project Activities
3. Right of Way Issues
4, Security Issues
5. Contractor’s Request for Financial Assistange
6. Conclusions and Summary of the Discus:Ethiopian Roads Administration
‘The particulars of discussions made on each of the above agendas are as follows;
[ Item
Nur | Issues and Discussions Action by
1 | Introduction
The ERA, Gondar Project Management Office, Team Leader} All
welcomed all the participants of the meeting and chaired the
meeting. The team leader noted that about more than 5 months have |
‘been counted since the project closure due to security issues and the
entire Contractor's and the Employer's Representative staffs have
been idle.
v The team leader briefly discussed that he has been mobilized
| to the project site participants of the meeting and has
conducted meetings on November 08 and 09, 2023 with the
local administrations of Dabat Woreda and Tegede Woreda
respectively.
2 | Joint Condition Survey Required to Resume Project Activities
The Contractor Project Manager has reminded on the agreed
precondition to resume of Project Activities from last meeting on July All
31, 2023.
| > The PM has begun by addressing his point by inviting the
participant by reminding the cause for cessation of the
project and failed prevalence of secure environment to
| execute the work facing continuous looting, robbery, |
intimidation, harassment, physical assault etc usually |
involving arms, which robe avenues to mobilize resources
and execute the works unimpeded. From the notable causes
and failed prevalence of justice including:-
> Attack on contractor’s camp including the Project Manager.
> Armed robbery, damage to vehicle and physical assault to
the Contractor’s workmen.
| > Looting from the Employer's Representative mess hall,
Material robbery from Anssesa Bridge, construction raw
materials robbery including fuel, cement and etc from |
construction site, Radio communication device robbery,
physical assault and robbery on different roadway section |
especially at Aradie kebele including attack on the |
Employer's Representative staffs, lawlessness and failed |
legal protection of Contractor's staff.
> Continuous road blockage and disruption following belated
Row payment
> Difficulty to mobilize and demobilize his resources from the |;
project site
> Forsuch, the Conyefor has reqiested for solid action on =
> Establishment of secure environment for the well-being of
the Contractor's workinen. |
> Unhindered mobilization ands demobilization of resources,
| > Resolution of oltstandin; tight® of way issues and
NAN: ___ Page 2 of 11Ethiopian Roads Administration
v
vv
v
ag
v
Containment of individuals forceful stoppage of the works,
and
Partial recovery of the costs that the Contractor has incurred |
including idle costs of resources, time related overhead costs
and payment
In connection with the meeting that was held on July 31,
2023 with the availability of all Stakeholders, the Employer
was requested Dabat woreda and North Gondar zone to
provide and come up with a mitigation proposal on how
they fulfil their repetitive failed promises on handling of
security problem which is the reason of cessation of the
project. Task includes;
How to recover stolen property
How to bring killers and intruders to the law
How to stop repeated street robbery and
Remobilization of regional security forces to secure the
project environment
In general, the three parties requested, to get a proposal on
how the Contractor can carry out the work without any
security risk and disruption, and the later plan was to
evaluate it together.
‘Accordingly, one of the aims of the site visit was to assess
on such tasks that the woreda conducted and prevalence of
secure environment is established or not. But, none of all has
been witnessed so far according to our site visit. No one has
brought to justice system and didn’t get their proposal as
the Project Manager stated his opinion
In summary, The project cessation on June 06, 2023 was a
cumulative effect of two- or three-months lawlessness since
January 2023 including cessation for more than 45 days
starting from January 2, 2023 after an attack on Contractor's
project’ manager, administrator and other staffs by a
gunmen and such previous failed promises from the woreda
has caused severe financial and time losses. Effect of
repetitive cessation and remobilization to the project is still
at risk and couldn’t assure when to resume the work
without a solid effort from the woreda.
On the other hand, the Second aim of the site Visit was to
assess prevalence of secure environment, and checking of
opened road corridors for Contractor's resource
mobilization and smooth supply that result from armed
conflict sprouted throughout Amhara region due to the on-
going operations ensured by the government against rebel
groups. Such is still ongoing since 05% August 2023
following the state of emergency declared by the Council of
Ministers. For such, the general presumption about the
project area by lessors and workmiery is.unfavourable and
thus far we cannot be certain thél/sectire environment has
been restored to resume progressing he Works Land Road
corridors are still closed. Ve Sh Fe f
6 .
Page 3 of 11Ethiopian Roads Administration
Vv
v
Further to that recent operation around Km 22 between the
government and the rebel groups hasn’t assured the
resumption of the project with the prevalence of secure
environment rather still several forces are still operating
through the area.
Most notably, the Project Manager has given emphasis on
the impossibility of transporting Dynamite from Addis
Ababa which will affect the overall crushing activity which
is laid on the critical path of the project is at large and
resumption of work is unthinkable and on land since public
transportation is still closed.
The employer raised on the possibility of purchasing goods
from nearby area and will further communicate the
command post on the possibility of arranging protective
convey transportation together with defence forces presence
for the construction raw material from contractors preferred
resources.
The Employer stated to focus on other works other than
crushing until land transport for such convoy is permitted
by the government offices. But the Project manager insisted
project cost overrun and time related burden is high until
the project is executed according to the approved work
program,
The contractor PM replied on the limited and scarce
availability of construction raw material around Gonder and
stressed out the criticalness of dynamite mobilization for
Crusher. Aside from that the PM noted the possibility of
ambushing the convoy in which the conflict is more of
gorilla war type and noted the high risk and difficulty on
resumption of work.
However, the Employer stated that;
The Woreda administration has started executing his
assignments as discussed on July 31, 2023 to secure the
working environment which is presented by the
administrator at the project camp during site visit.
In connection to this, the Woreda has assigned Ten (10) new
security force members (Militia) on each Kebele in addition
to the previous number of security forces who are
responsible for preventing any illegal action by the local
residents, robbery and theft.
The general security condition én?and around 'the project
area including Gondar town is safe And'secured.
(Sis g
The current armed movement|gn \thé xégidiv isnot related |
over hastno experience
with the project work and the
Page 4 of 11Ethiopian Roads Administration
v
v
a
v
any problem due to the current condition of the region even
two projects (Beles-Mekanebirhan & Km 69+000-
Angereb/Ashere) under Gondar PMO are active/engaged
on their work.
However, since the corridor from Addis Ababa to Gondar
has been closed sometimes the Employer raised on the
possibility of purchasing goods from nearby area and will
further communicate the command post on the possibility of
arranging protective convey transportation together with
defense forces presence for the construction raw material
from Contractor's preferred resources.
To this end, since there is no fuel shortage on Gondar town,
the Contractor shall take the responsibility to find the means |
of transportation as how the town used and mobilize fuel,
cement and goods for community consumption.
In connection with Explosive transportation, it will be
difficult to transport under this circumstance; however,
since we have not requested the concerned Authority and
could not get their response we couldn't decide on the
situation. Hence, requesting the concerned authority is
better and until that we can use the available balance on the
project site.
The Employer will settle the Right of Way issue either by
effecting some amount of compensation or by
communicating the concerned authority and property
owners
The Contractor's requisition of financial support by the
Employer shall be administered through the Contract
requirement. Hence, the Contractor can submit his proposal
to the Employer's Representative.
Therefore, the Employer has given his stress to resume the
project work and all parties shall be performing their
responsibility in line with the requirement of the Contract.
The Contractor PM replied on the limited and scarce
availability of construction raw material around Gonder and
stressed out the criticalness of dynamite mobilization for
Crusher. Aside from that the PM noted the possibility of
ambushing the convoy in which the conflict is more of
gorilla war type and noted the high risk and difficulty on
resumption of work.
‘Thus far, it has been more than 5 months since the progress
of the works ceased and the Contfactos’s resources attached
herewith remain stranded exacérbating the alreddy inflicted
financial standing of the Contfactdr..More. worrisome is the
uncertainty when the Contractor may be able to resume the
works or have idled resources ngved wutinclyding those
Page 5 of 11Ethiopian Roads Administration
v
v
y
leas
Contrary to any assertion or assurances that may be offered
by the local administration regarding prevalence of enabling
environment in and around the project area and unfettered
movement of traffic to and from the project site to resume
the works; the Contractor's assessment of the security
situation in the broad area of the site and access thereto and
ease of movement of goods and machineries to and from the
project area gives a different picture. Most importantl
* Sporadic engagement between government forces and
rebels along the project access corridor and the site poses
significant risk and would not warrant remobilization of
needed resources and take out those that are no more
required or lease agreements terminated,
* Transporters would not wish to serve because of risks,
they would not wish to assume in connection with the
armed conflict for such risks are not indemnified by |
insurers, |
« Transport of dynamite is bitterly restricted thus
production of surfacing aggregate, one of the key activity,
shall remain ceased even if we could manage to have
presence of certain resources on site. Cognizant of surfacing
works are the main outstanding works, it would be futile to
have all other resources without commencing production of
surfacing aggregate,
* The security situation is still volatile and uncertainties
are abound. Under such circumstances and inconsideration
of significant number disruptions we have had dealt with in
the past, we do not have any more financial or moral
contingency to absorb the consequences that may eventuate,
* Absence of local police force to provide additional
security to the project area like it had been in the past,
wound mean we have to assume more risks than before
while our standing has diminished because of vast number
of traumatizing and derailing experiences we had been
through,
While the actual situation is as stated above, the local
administrations assurance of maintenance of a secure
environment to let remobilization commence must not be
taken undoubtedly. Such assurances destiny of getting futile
must not be ruled out since similar of them had ended uy
futile.
The Contractor is mindful that thé Security situation is. rf
beyond the reasonable ability of the Idcal‘administration and?
the overall _ security arrangement. yesourcing and |:
deployment is under the conlyol\ofa:'commiand post
established following state of cae declared. by the
_Page 6 of 11v
sg
Ethiopian Roads Administration
Council of Ministers in the Amhara National Regional State
on5 August 2023.
Mere assurance offered by the local administration must not
overshadow the gravity of the problem and similar
assurances offered by the local administration in the past
have always failed to pass the test of time, and hence the
latest assurance seems hasty and the likelihood of exposing
the Contractor to further damages is overwhelming.
Over the past couple of years, the Contractor had to assume
the burden and consequences disruptions all of which
scored considerable damages. The accrued damages, have
never been recuperated, gradually derailing the Contractor's
financial standing to even attempt to execute the works.
Following each incident of disruption,
¥ The Contractor must have to endure the consequences
of reorganization,
¥ The Contractor must have to remobilize both human
and material resources disorganized,
. ‘The Contractor had to bear the additional cost of each
incident of disruption/ disorder attracts.
Y Fach attempt that has been made to resume the
progress of the works following costly disruptions has never
been reciprocated with measures such as establishment of
secure environment and payment of the additional costs
incurred.
Thus far, the Contractor has been struggling not to give in
despite undergoing numerous killings, harassments,
physical assaults, robberies, lack of improvement in the
security situation, etc. Even though, we would have wished
to resume the works, however, you must not overlook the
fact that:
‘There are still significant number of unsettled complaints in
connection with compensation payments that would add
fuel to the insecure environment,
Transporters would not wish to serve delivery of fuel unless
special security arrangements are made and at significantly
higher cost,
The PM addressed our financial standing is so crippled we
would not be able to pay advance money for delivery of fuel
that is not less than 3.5 million ETB per each order.
We cannot go on to hiring workmen ands commence | >
reorganization before secure environment is established and
unfettered movement of trucks and. machineries imand out
of the project site isensured, | O/,° \a\
Lessors continuous declination |to. lease machines can only
be abated through establishmentlof secure'envirohment
Page 7 of 11The PM concluded on the fact that significant number of past
incidents the Contractor have been through have poured their toll on
the Contractor and the accrued consequences have had translated to
flattening out the Contractor's ability to execute the works and no
more attempt is likely forthcoming to resume the works this time
unless the Employer's considerate and helping measures are taken
for certain requests, we list out hereunder.
> The establishment of secure environment for the wellbeing,
safety and security of the Contractor's workmen,
v
Unhindered mobilization and demobilization of resources,
v
Resolution of outstanding right of way issues and
containment of individual's forceful stoppage of the works.
Vv
Advance loans are offered for the procurement of material
such as fuel, Cement, Reinforcement and explosive that may
be paid out to suppliers directly.
v
Partial of recovery of the costs the Contractor incurred
including idle costs of resources, time related overhead costs
and payment for the continued provision and maintenance
of the Employer's Representative facilities
> Most significantly, individuals who killed contractors’ staff,
lotted contractors property, attacked contractor camp
including PM and disrupted work by force on the roadway
must be prosecuted and his property must be returned.
Finally the Pm addressed the Contractors financial incapability to
supply construction goods without an immediate support from the
employer due security problem cessation and remobilization of
resources on different occasion
The Assistance Resident Engineer briefly discussed the Joint
Condition Survey Required to Resume Project Activities site visit and
has conducted meetings with the local administrations of Dabat
Woreda has been told by the local administration that the security is
improved and some of the police forces are established in three (3)
kebeles that is Ayrefeda, Arade and Aditewle by each group of 10
members totally prepared 30 police forces,
The Assistance Resident Engineer noted no improvement by Dabat
woreda administration security situation only promising to the
resumption of site activities. Because of the above paragraph states
that the Woreda has assigned 30 local polices (Melisha).
Y Contractors request fox justice on those who killed
his staff, lotted cghirgcto#s property, attacked
contractor camp including PM.and disrupted work
by force on the roadwe¥-yet Hot prosecuted
¥ __his property not returheg dx atthe time of site visit
Ethiopian Roads Administration
i BVP.
Oo gi aye]
: |
; 3
{ -
‘ 5
‘ ?
\ é/
¢
Page 8 of 11Ethiopian Roads Administration
Y Previously failed method of securing environment
while the contractor requests a regional force the
option of arranging such Milisha didn’t guaranty the
security of the area as witnessed from past efforts
rather it’s a promising effort.
The Assistance Resident Engineer briefly discussed the Joint
Condition Survey to Resume Project Activities and will not give
assurance for resumption of work on both work fronts following the
conducted meetings with the local administrations of both Dabat and
Tegede Woreda following. the local administration need 20 days to
aware the delay of compensation payment to the local peoples and
confirm the possibility of commencement of work in written and the
same promise of engaging to secure the work environment and
expect further notice from both woredas in written on the possibility
of when to resume the work.
The Assistance Resident Engineer further stated that, in order to be
more sure for creating secure environment the Woreda shall control
and exercise rule of law by taking legal action on robberies and
armed groups and return the looted properties to the Contractor. In
addition to this, as the administration head of Tegedie Woreda stated
on the discussion, the Woreda will require 15-20 days to discuss with
the property owners whom couldn't get their compensation payment
until now. Hence, the Woreda administration will inform the
Employer via letter.
In connection with the Contractor's request on the above six points,
the Employer has given his response as follows;
» In order to create safe and secure environment on the project
site, the Woreda administration has assigned additional 10
security forces on each kebele as discussed above. To this
end, the Woreda administration has assigned security force
to take legal action on the man who was killed the
Contractor's worker. As we observe during site visit, this
force is led by Deputy Officer of Dabat Woreda Peace and
Security Office who is a member of Police force and has
Inspector rank, Hence, the Woreda is performing his
assignment.
The Employer will settle the problem related with
Contractor's mobilization and demobilization of resources,
if the Contractor properly inform the Employer through
Employer's Representative.
> The Employer will solve the right of way issues either by
effecting partially or by making detail discussion with
concerned authorities and the public.
Any financial support request like material advance and
cost claim will be administered..under the pertinent
provisions of the contract; henee,/ the: Contractor shall
submit his proposal to the Employer's Representative.
| Hence, resumption of the project is nena Mhotlet to answer the
public request. \
v
oe
PEAS
Page 9 of 11Ethiopian Roads Administration
Right of Way (RoW) Issues
| The ARE of the project noted that the local people is frequently
stopping us while we travel along Contract I due to delayed |
compensation payment for RoW. On the other hand, the ARE noted |
that the office activities of the RoW clearance activities is being
executed by both the Employer and the Engineer to finalize
outstanding RoW activities.
The Employer noted that RoW compensation payment for Contract I
is already paid for some road stretches to the owners and advised the
Contractor to work closely with the woreda administration in
handling RoW issues as complaints have been heard from the woreda
side for the failure to work closely with the local woreda.
The Employer pledged to handle any outstanding issues in
collaboration with both woredas.
>» Tegede woreda has requested for more than 15-20 days to
convince land owners to convince them on delay of ROW
payment and commencement of the work on the back front
and this showed the impossibility of directly commencing the
site work following the continuous disruption and road
blockage due delay of compensation for ROW payment,
» The Contractor was also requested for full settlement of ROW
payment to avoid disruption and delay to the progress of the
work and avoid further financial losses from idle resources
The employer requested for the assurance of commencement
of work but the woreda complied the difficulty unless public
awareness is created
v
Employer and
Engineer
| justice is served to the deceased staf.
Security Issues
The Contractor has noted the need for serious attention on timely
solving any security issues and the need for prompt handling of
payment for compensation of RoW clearance activities as the local
peoples are very sensitive in this regard.
The Contractor also noted that the person who killed his loader
operator last time is not yet under custody of the police and as this
still frustrates his project workers, the Contractor requested the
Employer to communicate with the local woreda so that appropriate
The Employer noted to solve the serious security issues withj|
communicates local admiration of woreda, Zone and Region and it is
to be noted that the Woreda administration is on process to do same
as discussed above.
Employer
Page 10 of 11Ethiopian Roads Administration
Financial Assistance Requested by the Contractor
‘The Contractor discussed that most of his equipment and manpower
has been idle. But, the Contractor has been paying their salary.
Furthermore, the Contractor is happy to resume the project after
conducting the above preconditions. However, the Contractor
requested to consider some financial assistance in order to pay salary
for his workers and use the money for purchasing fuel, cement etc to
commence the project.
The Employer noted his no objection pursuant to the conditions of |
the Contract; but, this will be considered after the Contractor
submitted his proposal to the Engineer. In this regard, the Employer
has advised the Engineer to check any possibility to generate
payment to the Contractor in line with the requirements of the
Contract.
All
Conclusion and Summary of the Discussion
Y The employer yet didn't receive from the dabat Woreda
written proposal and will forward to both the engineer and
contractor as soon when they received.
Y The employer will further notify from both Woreda with
formal letter to get the prevalence of secure environment and
list of returned lotted properties within short period.
Y We can't resume site project activity immediately because no
improvement the security condition and full fill the requested
preconditions raised by all parties
Y Participants agreed to wait both woredas letter to finalize
their assignment.
vY The Employer pledged to settle the ROW issues that the
Contractor has raised either by effecting the compensation or
convincing the public (property owners).
Y Regarding the request made by the Contractor for financial
assistance, the Employer agreed on principle, but this can be
answered pursuant to the conditions of the contract.
All
4
The meeting is adjourned at 6:00 AM and the above forms a true and accurate record of the
meeting held on 10 November 2023.
Page 11 of 11