INTERNAL & EXTERNAL VALUATIONS: SIMPLIFIED SCENARIO

CONTRACT SUMMARY OF
PARTICULARS: EXTERNAL INTERNAL
FACTS
VALUATION VALUATION

(1) Payment Application: Cost/Value reconciliation (CVR):


(1) Job: Excavation (900m3 qty) During performance, 5 days
of delay occurred as a result IPAs to the employer are based on
of delays caused by the contractual rates and (not the (1) Value of work done:
(2) Contract duration: 30 days actual charges the contractor was
authorities.. Based on the external valuation, as per
paying) + 20% margin:
(3) Method statement: the contractual rates:

An EOT has been granted Cost = 30 days x [$60 + (2 x $60) + Cost of work done = 30 days x [$60 +
Method: Excavate and load using and the contractor completed
$60] = $7,200 (2 x $60) + $60] = $7,200
loader, and transport using using the job in 35 days.
dump trucks. profit = 20% x $7,200 = $1,440 profit = 20% x $7,200 = $1,440

Value of work done = $7,200 + Value of work done = $7,200 + $1,440


Plant: 1 loader @ $60/day, and 2 The actual charges the $1,440 = $8,640 = $8,640
dump trucks @ 2 x $60/day contractor was paying for
resource throughout the (2) Contractor Claim:
Labor: 1 gang @ $60/day contract period were: (2) Cost of work done
Ascertained by the Engineer based
on the actual cost incurred during Based on the actual cost/charges the
Output per day: 30m3 Plant: 1 loader @ $70day, and contractor was paying for resource
2 dump trucks @ 2 x $70/day the delay
(4) Contract Sum (priced at 20% Cost = 5 days x [$70 + (2 x $70) +
= 30 days x [$70 + (2 x $70) + $70] =
margin) Labor: 1 gang @ $70/day $8,400
$70] = $1400

Cost = $240/day x 30 = $7200 (3) Final Account =


Contract Sum = 1.2 x 7,200 = (3) Profit statement
The contractor submitted a $8,640 + $1400 = $10,040
$8,640 cost claim established on the Forecasted Profit = $1,440
actual costs incurred as a
(5) Clause x.xx [Delays caused by result of the delay. Loss due to increased cost = $1,200
authorities] gives the contractor
entitlement to claim cost in the Actual Profit = $8,640 - $8,400 = $240
event.