You are on page 1of 19

process 3 are the items to be sold to customers.

For February 2021, Masipag Company presented the foll


processes:
Required:

Costs incurred: Process 1 Process 2


Materials 30,000 23,000
Direct Labor 14,800 11,680
Overhead 8,880 8,760
Total 53,680 43,440

50% at the beginning of the


Materials are added at Beginning of the process. process, and remaining 50% at
60% of the process.

Started/Transferred In 6,000 units 5,800 units

300 units, 50% materials, 20%


200 units, 100% materials, 40% converted. Cost from Process 1
converted. Materials P1,000; is P2,700; Materials P600, Labor
In process, beginning Labor P200; Overhead P120 P120, Overhead P90.
Completed 5,800 units 5,700 Units

In Process, end 300 units 50% complete 200 units 50% complete
Normal Loss 100 units, 50% complete. 100 units, 50% complete.
Abnormal loss 100 units, 50% complete.

Quality Control Inspection Made At 60% stage of production. At 60% stage of production.
A. Compute the following:

1. Equivalent units of materials and conversion for Process 1, 2 and 3 (6 points)

2. Unit costs of materials, labor and overhead for process 1, 2 and 3 (6 points)

3. Cost of completed and transferred out, and in-process inventories for process 1, 2 and 3. (6 points)

4. Unit costs of completed and transferred goods to process 2, 3 and to finished goods. (3 points)

B. Journalize the transactions for process 1, 2 and 3 (6 points)

C. How much is the total manufacturing cost? Finished Goods Inventory? Work-in Process Invento
g Company presented the following costs on three

Process 3
17,145
11,320
8,490
36,955

50% at the beginning of the


process, another 30% at 70% of
the process and the remaining
20% at 90% of the process.

is P1650; 5,700 units


Materials P240; Labor
P160; Overhead P120.

150 units, 50% materials, 60%


converted. Cost from Process 2
is P2475; Materials P225; Labor
P180; Overhead P135.
5,550 Units

200 units at 70% complete


100 units, 50% complete.
100 units, 50% complete.

At 60% stage of production.

s 1, 2 and 3. (6 points)

goods. (3 points)

ry? Work-in Process Inventory? (3 points)


Cost of Production Report - Average

PROCESS 1
Materials Labor & Overhead
Quantity Schedule Actual Work Done EUP Work Done
Units Started 6,000
In Process, beginning 200
Units Transferred In 0
TUTAF 6,200

Units completed 5,800 100% 5,800 100%


Units in Process 300 100% 300 50%
Units lost, 50% complete - normal 100 100% 100 50%
Units lost, 50% complete - abnormal 0

TUAF 6,200 6,200

Cost charged to the Process:


Cost from preceding process
Cost added in this process: In Process This Month Total
Materials 1,000 30,000 31,000
Labor 200 14,800 15,000
Overhead 120 8,880 9,000

Total cost to be accounted for 1,320 53,680 55,000

Cost accounted for as follows:


Units completed 5,800
Factory Overhead - Abnormal
Units In Process, end:
Cost from preceding department
Materials 300
Labor 150
Overhead 150
Subtotal
Total costs as accounted for
PROCESS 2
Labor & Overhead Materials Labor & Overhead
EUP Actual Work Done EUP Work Done
0
300
5,800
6,100

5,800 5,700 100% 5,700 100%


150 200 50% 100 50%
50 100 50% 50 50%
100 50% 50 50%

6,000 6,100 5,900

2,700.00 52,900.00 55,600.00


In Process This Month Total
5.00 600.00 23,000.00 23,600.00
2.50 120.00 11,680.00 11,800.00
1.50 90.00 8,760.00 8,850.00

9.00 3,510.00 96,340.00 99,850.00

52,900.00 9.12 5,700


100

200
1,500.00 100
375.00 100
225.00 100
2,100.00
55,000.00
PROCESS 3
Labor & Overhead Materials Labor & Overhead
EUP Actual Work Done EUP Work Done
0
250
5,700
5,950

5,700 5,550 100% 5,550 100%


100 200 80% 160 70%
50 100 50% 50 50%
50 100 50% 50 50%

5,900 5,950 5,810

9.11 4,125.00 95,990.57 100,115.57

4.00 465.00 17,145.00 17,610.00


2.00 340.00 11,320.00 11,660.00
1.50 255.00 8,490.00 8,745.00

16.61 5,185.00 132,945.57 138,130.57

95,990.57 16.84 5,550


1,286.48 100

1,822.95 200
400.00 160
200.00 140
150.00 140
2,572.95
99,850.00
r & Overhead
EUP

5,550
140
50
50

5,790

16.83

3.03
2.01
1.51

23.38
1,624.09 147.30 98.21 73.66 FG
58.53 4.25 2.48 1.86 WIP
131,709.52
2,010.37 5,550 5,550 5,550 5,550
1,682.61 151.55 100.69 75.52 2,010.37
3,423.75 200 160 140 140
489.21 4343.57 65.11226383 WIP
284.41 129766.26 1945.260456 FG
213.31 134109.83
4,410.68
138,130.57
1,943.26
67.11
2,010.37
Particulars Debit Credit Remarks
WIP - Process 1 30,000.00 Materials
WIP - Process 2 23,000.00 Labor
WIP - Process 3 17,145.00 Overhead
Raw Materials 70,145.00 Total Manufacturing Cost
Add WIP, beginning
WIP - Process 1 14,800.00 WIP, - Process 1 1,320.00
WIP - Process 2 11,680.00 WIP, - Process 2 3,510.00
WIP - Process 3 11,320.00 WIP, - Process 3 5,185.00
Accrued Payroll 37,800.00 Total Cost Put Into Process
Factory Overhead
WIP - Process 1 8,880.00 WIP - Process 1 2,100.00
WIP - Process 2 8,760.00 WIP - Process 2 2,572.95
WIP - Process 3 8,490.00 WIP - Process 3 4,410.68
Applied Factory Overhead 26,130.00 Cost of Goods Manufactured (FG)

WIP - Process 2 52,900.00


WIP - Process 1 52,900.00

WIP - Process 3 95,990.57


WIP - Process 2 95,990.57

Finished Goods 131,709.52


WIP - Process 3 131,709.52

FOH Control 3,296.85


WIP - Process 1
WIP - Process 2 1,286.48
WIP - Process 3 2,010.37
70,145.00
37,800.00
26,130.00
134,075.00

10,015.00
144,090.00
3,296.85

9,083.63
131,709.52
Cost of Production Report - FIFO

PROCESS 1
Materials Labor & Overhead
Quantity Schedule Actual Work Done EUP Work Done
Units Started 6,000
In Process, beginning 200
Units Transferred In 0
TUTAF 6,200

Units completed
In Process, beginning & Complete 200 0% 0 60%
Started and Completed 5,600 100% 5,600 100%
Units In Process 300 100% 300 50%
Units Lost - Normal 100 100% 100 50%
Units Lost - Abnormal
TUAF 6,200 6,000

Cost charged to the Process:


In Process, beginning 1,320.00 1,320.00
Cost from preceding process
Cost added in this process: This Month Total
Materials 30,000 30,000
Labor 14,800 14,800
Overhead 8,880 8,880
Adjusted for lost units
Total cost to be accounted for 55,000 55,000

Cost accounted for as follows:


In Process, beginning & completed 200
Beginning cost 1,320
Materials 0
Labor 300
Overhead 180
Started and Completed 5,600
Factory Overhead
Units In Process, end:
Cost from preceding department 300
Materials 1,500
Labor 375
Overhead 225
Subtotal
Total costs as accounted for
PROCESS 2
Labor & Overhead Materials Labor & Overhead
EUP Actual Work Done EUP Work Done
0
300
5,800
6,100

120 300 50% 150 80%


5,600 5,400 100% 5,400 100%
150 200 50% 100 50%
50 100 50% 50 50%
100 50% 50 50%
5,920 6,100 5,750

3,510.00 3,510.00
52,900.00 52,900.00
This Month Total
5.00 23,000.00 23,000.00
2.50 11,680.00 11,680.00
1.50 8,760.00 8,760.00

9.00 99,850.00 99,850.00

300
3,510
600
480
1,800.00 9.00 360
51,100.00 9.13 5,400
100

200 1824.137931
400
200
150
2,100.00
55,000.00
PROCESS 3
Labor & Overhead Materials Labor & Overhead
EUP Actual Work Done EUP Work Done
0
250
5,700
5,950

240 250 38% 95 68%


5,400 5,300 100% 5,300 100%
100 200 80% 160 70%
50 100 50% 50 50%
50 100 50% 50 50%
5,840 5,950 5,655

5,185.00 5,185.00
9.12 95,988.79 95,988.79
This Month Total
4.00 17,145.00 17,145.00
2.00 11,320.00 11,320.00
1.50 8,490.00 8,490.00

16.62 138,128.79 138,128.79

250
5,185.00
288.02
337.02
4,950.00 252.77
91,038.79 16.84 5,300
1,287.07 100

200 3426.60
489.34
279.99
209.99
2,574.14
99,850.00
r & Overhead
EUP

170
5,300
140
50
50
5,710

16.840139

3.031830
1.982487
1.486865

23.341321

6,062.81
125,650.98 23.732216
2,009.07 1,684.01 151.59 99.12 74.34 2,009.07
5,550 5,550 5,550 5,550 1625.439517
1,625.44 147.34 96.69 72.51 1,941.98
200 160 140 140 2,009.07
58.57 4.25 2.44 1.83 67.09
4,405.92
138,128.79 143,678.79
Particulars Debit Credit Remarks FIFO
WIP - Process 1 30,000.00 Materials
WIP - Process 2 23,000.00 Labor
WIP - Process 3 17,145.00 Overhead
Raw Materials 70,145.00 Total Manufacturing Cost
Add WIP, beginning
WIP - Process 1 14,800.00 WIP, - Process 1 1,320.00
WIP - Process 2 11,680.00 WIP, - Process 2 3,510.00
WIP - Process 3 11,320.00 WIP, - Process 3 5,185.00
Accrued Payroll 37,800.00 Total Cost Put Into Process
Factory Overhead Control
WIP - Process 1 8,880.00 WIP - Process 1 2,100.00
WIP - Process 2 8,760.00 WIP - Process 2 2,574.14
WIP - Process 3 8,490.00 WIP - Process 3 4,405.92
Applied Factory Overhead 26,130.00 Cost of Goods Manufactured (FG)

WIP - Process 2 52,900.00


WIP - Process 1 52,900.00

WIP - Process 3 95,988.79


WIP - Process 2 95,988.79

Finished Goods 131,713.80


WIP - Process 3 131,713.80

FOH Control 3,296.14


WIP - Process 1 0.00
WIP - Process 2 1,287.07
WIP - Process 3 2,009.07
IFO Average
70,145.00 70,145.00
37,800.00 37,800.00
26,130.00 26,130.00
134,075.00 134,075.00

1,320.00
3,510.00
10,015.00 5,185.00 10,015.00
144,090.00 144,090.00
3,296.14 3,296.85
2,100.00
2,572.95
9,080.06 4,410.68 9,083.63
131,713.80 131,709.52

You might also like