Revised Report on the progress (including social and economic development schemes) of Sardar

Sarovar Project for the month ending July-2021

1.0 BRIEF DESCRIPTION


PROJECT: Sardar Sarovar Project Benefits
(1) Irrigation : 1.855 Mha (75% area drought prone) in Gujarat.
: 0.246 Mha in desert districts of Rajasthan
(2) Drinking Water : 25 Million population (by 2011) & 30 Million population (by
2021)
: 9490 villages + 173 urban centers in Gujarat
: 1336 villages & 3 towns in Rajasthan to a population of
approx. 4.58 million
(3) Hydro Power : Installed capacity : 1450 MW
(4) Irrigation : Through RWS & PIM, maximum water use efficiency can be
Strategy achieved. Water hazards due to over watering – salinity and
water logging – can be prevented leading to sustainable
agricultural benefits to small and marginal farmers in the
command area.

2.0 PROGRESS OF MAJOR COMPONENTS OF THE PROJECT


2.1 Main Dam
a) The construction of Main Dam has been completed. Due to huge inflow on
account of heavy rain in the catchment area during Monsoon 2019 and Monsoon
2020, the Sardar Sarovar Reservoir was filled stage wise and safely upto FRL i.e
138.68 m having live storage capacity 5800 MCM. The water level as on 31-07-
2021 is 116.51 mt. with live storage 719.51 MCM.
b) Construction of Irrigation Bye Pass Tunnel has already been completed.
c) Garudeshwar Weir :
The work of Garudeshwar weir is almost completed. The work of protection wall is
under progress. The progress of Excavation is 11.5106 LCM and concrete is 8.438
LCM up to July-2021.
2.2. Power Generation
Cumulative
Upto July- During 2021-22
Particular Unit upto July
Mar-2021 2021 (upto July 2021)
2021
(A) RBPH Million
40461.654 17.366 779.946 41241.60
(River Bed Power House) Units
(B) CHPH Million
9260.477 28.479 207.352 9467.829
(Canal Head Power House) Units
Total(A+B): MU 49722.131 45.845 987.298 50709.429
(C) Solar Power Million
231.042 3.3502 17.2486 248.2912
(35 MW Canal Bank/Top) Units
(D)Small Hydro Power MU 189.627 7.6343 16.5690 206.1960

2.3 Progress of Canal System & Irrigation Potential Created


Upto Cumulative
Sr. July - During 2021-22
Particular Unit Total March upto July
No. 2021 (upto July 2021)
2021 2021
(I) Canal System
(A) Main Canal Km 458 458 - Completed - 458
(B) Branch Canal Km 2726 2648 1 13 2661
(C) Distributary Km 4633 4423 0 12 4434
(D) Minor Km 15666 14331 5 80 14411
(E) Sub-Minor Km 46347 40572 28 232 40805
Total: Km 69830 61557 34 337 62769
(II) Irrigation Potential
(A) Up to Minor Ha. 1792328 1680938 648 6965 1687903*
(B) Up to Sub-Minor Ha. 1792328 1502905 3867 16014 1518918*

* includes 30639 hectares of Kutch Branch Canal where pipelines are laid for minors and
subminors but they are yet to be connected.Over and above,pipelines for 18416.4363 hectares are
laid for minors and subminors during March-2019 to July-2021, which are yet to be connected, and
hence not included in this progress.
2.4 Registration of Water Users Associations
Phase-I : 1191 Phase-II : 2302 Total : 3493

3.0 ENVIRONMENTAL SAFEGUARD MEASURES


During the month, advance works of current year 2021-22 plantation- 160 ha and maintenance
of previous years plantation along the canal bank continued.

4.0 AGRICULTURAL EXTENSION AND MONITORING:


For the benefits of farmers, 12 - demonstrations on research stations and 145 - on farmers field
was conducted; 23- Training programs, 3 FIG/SHG/field day and also 345- soil samples were
collected for soil testing followed by providing soil health card. Sampling was carried out at
144 locations, for ground water depth and quality.