Professional Documents
Culture Documents
FFM15, CH 13 - Real Op - , Chapter Model, 2-08-18
FFM15, CH 13 - Real Op - , Chapter Model, 2-08-18
28 CASE 1: If the expected NPV without the growth option is positive, then
ds) 3
4
5
6 NPV@
7 12%
8 $603
9 -$358
10 $122
11 $480
12 3.93
13
14
15 NPV@
16 12%
17
18
19 $3,364
20 -$358
21 $1,503
22 $1,861
23 1.24
24
25
26 $1,503
27 $122
28
29 $1,381
30
31
32 NA
33
uld not be undertaken.
34
35
36 $1,381
Figure 13.2. Analysis of an Abandonment Option (Dollars in Thousands) 2/08/2018
CASE 1: If the expected NPV without the abandonment option is positive, then
CASE 2: If the expected NPV without the abandonment option is negative, then
Note: If a negative NPV project does not have an abandonment option, then it would not be
undertaken. In these cases, the expected NPV without the abandonment option is zero.
Part II. Delay the Decision Until We Know the Market Conditions
Cash Flow at End of Period NPV@
Outcome Prob. 0 1 2 3 12%
Good 50% $0 -$3,000 $2,000 $2,000 $339
Bad 50% $0 $0 $0 $0 $0
Expected NPV $170
Standard Deviation (σ) $170
Coefficient of Variation = CV = σ / Expected NPV 1.00
CASE 1: If the expected NPV without the timing option is positive, then
CASE 2: If the expected NPV without the timing option is negative, then
Expected NPV with the
Value of the Option = ‒ 0 $170
timing option
Note: If a negative NPV project does not have a timing option, then it would not be undertaken. In these
cases, the expected NPV without the timing option is zero.
Note: Under the Delay situation, we must find the NPV as of t = 0. If we set the cash flow for t = 0 at $0,
then using a calculator or Excel we automatically find the NPV at t = 0. However, if we let
CF0 = -3000, CFj = 2000, Nj = 2, and I/YR = 12, we get an NPV = $380 under the Good outcome and an
expected NPV of $190. Note, though, that these NPVs are as of t = 1, so we must discount them back
one year at 12% to achieve comparability with the NPV calculated for not delaying the project and arrive
at the correct answer.
Figure 13.4. Analysis of a Flexibility Option (Dollars in Thousands) 2/08/2018
Part I. Project without the Flexibility Option Cash Flow at End of Period NPV@
Outcome Prob. 0 1 2 3 12%
Strong demand 50% -$5,000 $2,500 $2,500 $2,500 $1,005
Weak demand 50% -$5,000 $1,500 $1,500 $1,500 -$1,397
Expected NPV -$196
Part II. Project with the Flexibility Option Cash Flow at End of Period NPV@
Outcome Prob. 0 1 2 3 12%
Strong demand 50% -$5,100 $2,500 $2,500 $2,500 $905
Weak demand Switch products 50% -$5,100 $1,500 $2,250 $2,250 -$366
Expected NPV $270
CASE 1: If the expected NPV without the flexibility option is positive, then
Expected NPV
Value of the Expected NPV with
‒ without the flexibility NA
Option = the flexibility option
option
CASE 2: If the expected NPV without the flexibility option is negative, then
Note: If a negative NPV project does not have a flexibility option, then it would not be undertaken. In
these cases, the expected NPV without the flexibility option is zero.
25%
20%
WACC
15%
10%
IRR
5%
0%
$100 $600 $1,100 $1,600 $2,100
Capital Budget
2. Suppose a project's expected "cannot abandon" NPV is -$14 and its "can
abandon" expected NPV is $214. How much is the abandonment option worth?