Professional Documents
Culture Documents
T Works 11 Sept 13 - Jonothan Mack - Keepmoat
T Works 11 Sept 13 - Jonothan Mack - Keepmoat
Date: 11.09.13
By: Jonothan Mack BEng (Hons)
Regional Temporary Works Coordinator
1
2
3
4
Course Contents
5
1.0) Summary of BS5975
6
1.1) What Does it Say about Ground Conditions?
a) The maximum allowable bearing pressure for any soil or rock should be selected to
provide adequate safety against ultimate failure and limit the settlement to an
acceptable value.
d) In cases where the filling material is variable in consistency and unable to receive
and transmit loads uniformly, a minimum depth of 0.5 m of the fill should be
removed and replaced by well compacted and stabilized granular material of known
bearing capacity.
7
1.2) Key Procedural Requirements?
8
2.0) The Design Brief
9
2.1) Establish Ground Conditions
10
NON - COHESIVE SOILS
No interparticle bonding.
COHESIVE SOILS
11
2.2) Ground Investigation and Test Results
The correct test for the identified soil type can be chosen from a
number of
12
Field Tests – a) Shear Vane Test
The vane equipment comprises four blades arranged in a cruciform on the end of
rods, which are extended from the ground surface to the test level. The vane is
pushed into undisturbed soil, and the rods are rotated by hand cranking via a worm
and pinion gear.
13
Field Tests – b) Dynamic Probe Test
14
15
16
17
2.3) Establishing Near by Hazards
Any hazards within the ground that may cause the crane to become
unstable should be considered if
18
Load from an outrigger plate or base may be assumed to spread down
through the ground at a slope of 1:1 (45 degrees) in both directions.
45 degrees
This means that the load from an outrigger or spreader can be transferred to
19
These examples show some failures due to the placement of the crane outriggers over
hazards or close to hazards. So what hazards may have been the cause?
20
21
22
So by ensuring that a designer is issued
23
24
3.0) Check Lists and Inspections
25
3.1) Lifting Plan Check List
A check list should be used to ensure that the lifting plan is compliant with
the information issued within the design brief. Items that are often missed
and should be included are as follows :-
Item Reason
26
27
3.2) Inspection form / Permit to Load
An inspection should be undertaken to ensure that the constructed
platform is compliant with the design.
28
Questions?
29
Influence of Load and Foundation Size on Soils
30
4.0) Piling and Piling Rigs
31
4.1) BRE R470
The BRE process considers the various loading conditions under two class
headings.
• CASE 1 LOADING
These loading conditions may apply when the rig or crane operator is
unlikely to be able to aid recovery from an imminent platform failure.
Operations in which this type of loading condition applies could include:
Standing
Travelling
32
• CASE 2 LOADING
These loading conditions may apply when the rig or crane operator
can control the load safely, for example by releasing the line load,
or by reducing power, to aid recovery from an imminent platform
failure.
Installing casing
Drilling
Extracting an auger
Extracting casing
33
4.2) FPS Rig Schedule
34
4.2) Working Platform
Certificate
35
HSE Enforcement
36
Questions?
37