RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN BREG DAN SIRTU CIMALAKA


PERUMAHAN PANORAMA ANJATAN VILLAGE

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN ANALISA SATUAN HARGA
(Rp) (Rp)
1 2 3 4 5 6 7=(3x6)

I. PEKERJAAN PEMASANGAN BREG Luas 888 M2


1 Pengadaan Breg Bambu 156.00 lbr - 130,000.00 20,280,000.00
2 Upah 156.00 lbr - 10,000.00 1,560,000.00

JUMLAH I 21,840,000.00

II. PEKERJAAN URUGAN SIRTU CIMALAKA Volume 266,4 M3


1 Pengadaan Sirtu 45.00 rit - 1,250,000.00 56,250,000.00
2 Upah 45.00 rit - 150,000.00 6,750,000.00

JUMLAH II 63,000,000.00

JUMLAH III 84,840,000.00

* DP 20%
Progress 100% dibayar 95%
Retensi 1 bulan 5%