Professional Documents
Culture Documents
Wettradesandwater Control concretesocietyFINAL
Wettradesandwater Control concretesocietyFINAL
net/publication/300131228
CITATIONS READS
0 1,053
2 authors:
All content following this page was uploaded by Derick Booyens on 02 December 2019.
ABSTRACT:
The purpose of this study is to try and increase the level of quality control for contractors in South Africa and
other countries especially in Africa over wet mixes for example concrete. Increasing the level of control through
simplifying the management process, one can ensure prevention of failures rather than to rectify defects at a later
stage of the project. Specific issues included are the contractors’ understanding of the effect of adding water to
mixtures, slump tests, test cubes and the ethics surrounding it.
In most circumstances it is difficult for building contractors to manage the quality of wet trades on constructions
sites and would typically include the mixing of concrete and mortar. As the contractor cannot be personally
involved in the quality assurance of everyday mixing on site, he has to rely heavily on the skills of his workforce
and/or sub-contractors performing these mixes and their understanding of the effects of adding water to these
mixes. The interference of staff with ready mix concrete mixes from reputable suppliers is often outside of the
contractor’s control. This lack of control over adding water in mixes can lead to minor or major defects and even
1. INTRODUCTION
As readymix concrete deliveries arrive on the construction site, a labourer will often jump up at the back of the
truck to see what the slump of the concrete is through the outlet of the truck and inform the supervisor of the
status of that concrete slump. If the slump is “undesirable” or not to his liking through this visible inspection, the
labourer is often instructed to add water to the mix through the outlet and thereby increasing the workability of
the concrete. This “undesirability” is measured and influenced by the whether the concrete is to be transported
over the site by means of wheelbarrows and placed by hand, all adding to the amount of effort that will be
required to do the pour. Under other circumstances, the plaster or brickwork sub-contractor would instruct the
team to mix a batch of plaster or mortar and after 30 minutes of work, would realise it is time for lunch and
everybody would down tools for an hour often leaving the mix to dry out, usually in the sun. As work resumes,
the plasterer or bricklayer would instruct the labourer to add water to the mix to make it workable again due to
the drying effect of the heat exposure. These are just some scenarios happening on a daily basis on construction
sites and making it very difficult for a contractor to control or effectively managing proper water control to
mixes. Even if curing of the final product is properly done after adding additional water, the desired strength
effect will be sacrificed. The aim of the study is to attempt in determining whether the abusive adding of water to
mixtures on site, can be more effectively managed from a contractors’ point of view. Thus ensuring that when
the correct quality of mixes is achieved and with the aid of proper curing methods, defects or failures can be
minimized or prevented.
2. LITERATURE REVIEW
Adding excessive water on the building site dilutes the paste while increasing the slump with the strength
decreasing significantly [1]. According to Pronto Readymix, a large concrete readymix supplier in South Africa,
this adverse effect on the concrete strength will even increase during summer times when temperatures and
As illustrated in the following Table I, as the standing time of the truck on site increases, the slump loss will
increase while the possibility of adding water will increase to improve the workability of the concrete. The table
further shows the approximate percentages of strength loss when adding specific amounts of water additionally
[2].
Table 1 - The extra addition of water to compensate for workability loss due to delays adversely affecting concrete strength.
(Source: Pronto Readymix).
60 50 10 Litre / m3 10%
90 60 12 Litre / m3 15%
Diagram 1 below illustrates what happens if excessive water is added to increase the slump, without adjusting the
concrete mix ratio.
Nil
10
20
Strenght reduction %
30
90mm
40 Standard 120mm 180mm
Slump
Collapse
0 ₊ 10 ₊ 20 ₊ 30
Water added - Litres per Cubic Meter
Diagram 1 – Effect of addition of excess water on concrete strenght and slump (Based on 25 MPa concrete at 90mm slump)
Readymix concrete suppliers in South Africa will not take responsibility for their product if water is added on
site. The truck driver will simply mark “water added” on the delivery note and thereby distance themselves from
any possible claims towards the compressions strength of the concrete delivered and not bear the liability from
One can add water to the truck, but these procedures is more complex and specific rules need to be adhered to.
When adding water to the mix, the addition should not alter the water-cement ratio above the maximum
permitted level. To correct this ratio, cement needs to be added proportionality. Water must be added to the
entire batch otherwise it is impossible to try and guess the balance of m3 still remaining in the drum of the truck.
If water is added through the discharge section of the drum, the water will not be distributed evenly through the
mix. Water should be added at the head section of the drum, or by the head and discharge sections (dual
ratios in wet trades. Without these necessary skills the risk for the contractor increases with each mix, as the
contractor cannot be present at all times. The contractor can use a slump test and make use of test cubes, but
these two methods also have their short falls and cannot indicate immediately if mixes were compromised before
discharge or application. This leads to rectifying the problem after 7 to 28 days rather than to try and prevent it
Contractors use the slump test to measure consistency (stiffness, sloppiness or fluidity) of the mix. For the
contractor to be able to effectively handle, place and consolidate the concrete mix, the consistency of each batch
must be the same and within accordance to the South African National Standards (SANS 5862-1) [5] [6].
The slump test apparatus consists of a slump cone, base plate, tamping rod, scoop and metric ruler. When the
supervisor takes the concrete sample he must make sure that it happens in at least 9 increments and not during
When doing the actual test the following procedure needs to be adhered to:
sections,
• Rod each layer 25 strokes (make sure the rod penetrates the layer below),
• Transfer weight from foot pieces to handles and slowly lift the cone vertically straight up and off,
• Measure the distance between the underside of the trowel and the highest point of the top of the concrete,
The bigger measurement of the slump, will indicate the wetter and weaker the mix. The slump test is suitable for
a slump range of 5 to 175 mm. Hand tamping is normally between 100 to 150 mm and a poker vibrator between
50 to 120 mm.
b. Cube Test
In South Africa, the compressive strength of concrete is determined according with SANS 5860, 5861-2, 5861-3
and 5863 [5]. After the slump test the supervisor must prepare concrete test cubes. Test cubes are normally 150
mm x 150 mm in size and the supervisor needs to take 6 cubes per test. He will use 3 of these cubes for crushing
after 7 days and 3 for crushing after 28 days. It is required to take at least one set per day or for every 50 m3 of
The sampling procedure for a cube test is the same as for a slump test, although the apparatus and preparation
will differ:
• Tamp each layer 45 times (cube 150 mm) or 20 times (cube 100 mm), especially in the corners with rod,
• Once the concrete has hardened, place cubes submerged under water.
The cubes should be removed from the mould the next day, clearly marked (company name, reference number
and the date the cubes ware made) and placed inside the curing tank. When the cube is removed from the mould,
the supervisor must loosen all the nuts with a spanner. If the cube is stuck, the supervisor should slightly tap the
sides with a hammer. Cubes are marked with a lumber crayon and placed in the curing tank completely covered
by the water and the thermostat is set between 22 ⁰C– 25 ⁰C to regulate the water temperature [5] [6].
For the cube test to be valid, the range of strengths within the set of three cubes may not exceed 15% of the
average.
Concrete is readily used in the developing world and while the components are simple, mix design and quality
control during construction is critical to obtain an acceptable end product. However, the use of these tests
requires equipment and testing that is often not available for short-term projects [11].
The other problem with these tests is that the supervisor / team leader can easily take shortcuts while executing
these tests:
• Supervisor can take test cubes from the mixing truck that carries 30 MPa and write on the test cube 25
MPa
• Supervisor can take test cubes from the mixing truck and add water afterwards that will distort the final
result
• Supervisor may not be educated around the understanding and importance of taking, curing and
transporting the sample, thus not understand that what he is doing wrong and the results are skewed. The
contractor can either then request a Schmidt hammer test or core drilling that will add to extra cost
In most developing countries it is not required to do cube tests for mortar mixes.
Even if the contractor’s system are in place and is properly managed, he will only have an indication after 7 days
In South Africa a suspended concrete slab collapsed killing a man and severely injuring several more. Dr.
Roderick Rankine, an engineer and expert in construction materials specified that the contractor did not follow
engineering specifications. Although there were a number of factors mentioned by him, the forensic investigators
discovered that the strength of the concrete was less than 3MPa in compression. The contractor admitted that
they mixed their own concrete on site and did not prepare any test cubes for testing purposes.
Most of these buildings that collapsed happened during construction on the site [12] [13]:
• January 2013: Five storey building collapsed in in the central district, Kenya, Nairobi
• January 2013: Building adjacent to Imperial Hotel tumbled down, Kenya, Kisumu
• October 2011: Building under construction, Rand Airport Park, South Africa
• October 2008: Office block under construction collapsed, Roodepoort, South Africa
• Year of 2004: The Engineering Council of South Africa mentioned that seven buildings collapsed in
KwaZulu Natal
Again the investigations with each failure listed a number of reasons why these incidents and accidents
happened. Amongst them were concrete mix ratios not being correct, cost cutting by contractors, changing the
recommended concrete mix, poor workmanship, lack of supervision, poor inspection & monitoring. Even with
the National Building Regulations (NBR) in South Africa, these accidents still occur from time to time [12] [13].
Correct curing is necessary to ensure that the cement hydration process is prolonged to allow the concrete to
increase its strength, durability and some of the other mechanical characteristics. Price (1991) defines curing as
the process of protecting concrete for a specified period of time after placement, to provide moisture for
hydration of cement, to provide proper temperature and to protect the concrete from damage by loading or
Improper curing produces cracks, compromise strength and reduce long-term durability due to insufficient
moisture [15]. The different curing methods seemed to have a higher deterioration effect to the development of
compressive strength than to its flexural and split tensile strength [16] [17].
With an increase in water-cement-ratio and an increase in curing age, the growth rate of the concrete strength is
diminished. [16]. Research showed that the weight, density and compressive strength of the concrete test cubes
decreased with an increase of water-cement ratio, however the results also showed that the compressive strength
increased as the number of curing days increased [18]. The research results indicated that the water-cement ratio
was the main determinant of the crushing strength of the concrete test cubes [19].
Construction sites use colour in their health and safety to indicate dangerous areas or to close off specific
dangerous sections to emphasize the potential danger and make it more visible. Construction teams wear
different coloured hard hats, so it is easy for everybody to be identified. For example, white hard hats indicate
site agents, engineers, project managers; orange will indicate team leaders; red would be steel fixers; yellow the
Project Managers use colour in their programmes to indicate where the critical paths are, i.e. to indicate if the
project is ahead or behind schedule. Project Managers also use colour in delegation tools to assign
responsibilities to other team members. Even construction equipment is mostly yellow or red, common
aposematisms in nature. Yellow is a bright, colour and so is immediately noticed. Yellow is after all, the most
Normal concrete has a characteristic grey colour, because of the cement being the finest grey ingredient, with the
greatest surface area and therefore the greatest colouring power [5].
There are many methods currently in use to change normal grey concrete colour into reds, yellows, browns and
black. One of these methods is through the use of synthetic iron oxides. These pigments are not affected by
ultraviolet rays, are permanent but the biggest problem is to ensure uniformity through different batches leading
If these synthetic iron oxides can be designed on a nanometer scale to be a smart material, thus only reacting if
too much water was added to the mixture, changing the grey concrete colour into a red, so the same principle can
be applied to indicate when water has been added to an existing mix, changing the colour of the concrete. Most
smart materials can be controlled by external stimuli such as, stress, temperature, moisture, ph, electricity or
immediate corrective action can be taken. This can be a powerful tool to assist a construction manager in his
Through immediate identification the properties of the mixture can then be altered on site and prevent later
failures, thus minimizing the risk involved in adding to much water that will reduce the strength of mixtures.
The interference of staff with ready mix concrete mixes from reputable suppliers is often outside of the
contractor’s control. This lack of control over adding water in mixes can lead to minor or major defects and even
Good site practice in both curing and cement-water ratio is key to ensure the desired compressive strength and
There are several different curing methods and they all have different effects on the compressive strength of
concrete. The most common used in South Africa is water curing. Most contractors don’t understand the effect
of spraying cold water on warm concrete or alternating wetting and drying cycles that causes crazing, cracking &
Both curing and the water-cement ratio are very important factors to understand and properly managed on site to
ensure the desired durability and compressive strength of concrete, although water-cement ratio is critical and
Education and training will reduce these problems surrounding the water-cement ratio, with the use of colour
change to indicate an alteration in the water-cement ratio; it will be easier for supervisors to manage this problem
effectively.
This method will assist in avoiding the water-cement ratio issue, thus ensuring preventative control measures,
rather than to focus on corrective action, that is costly and time consuming.
Through the change in colour, even unskilled people will be able to take note of the problem and inform the
relevant supervisor. The supervisor can then either phone the engineer for assistance or he himself can do the
necessary adjustments and ensure that the concrete reach the required compressive strength or take other
corrective action.
3. BIBLIOGRAPHY
[2] Pronto Readymix Concrete. Effect of addition of excess water on concrete strength and slump. Retrieved
[3] Suprenant, B.A. (1994). Adjusting Slump in the Field. Concrete Construction. The Aberdeen Group.
http://www.concreteconstruction.net/Images/Adjusting%20Slump%20in%20the%20Field_tcm45-
342700.pdf
[4] CEMEX USA-Technical Bulletin. The effects of water addition to concrete:”What’s a little water going to
[5] Owens, G. (2012). Fundamentals of concrete (2nd ed.).Cement and Concrete Institute, Midrand, South
Africa.
[6] Hauptfleisch, A.C. (2014). Basic Construction Technology. Construction Economics Associates (Pty) Ltd.
ISBN: 978-0-620-590-59773-9
[7] SABS Standard Method 860:1994. Concrete tests. Dimensions, tolerances and uses of cast specimens.
[8] SABS Standard Method 861-3:1994. Concrete tests. Making and curing of test specimens.
[9] SABS Standard Method 862-1:1994. Concrete tests. Consistence of freshly mixed concrete. Slump test.
[10] SABS Standard Method 863:1994. Concrete tests. Compressive strength of hardened concrete.
[11] Jon Fripp, P.E., Phuc Vu, P.E.,& David Cruz, P.E. Concrete Construction Field Techniques for the use in
2015].
[13] Kioko, J.M. (2014). Causes of building failures in Africa: A case study on collapsing structure in Kenya.
IOSR Journal of Mechanical and Civil Engineering, Volume 11, Issue 3, Ver. VII (May-Jun. 2014), PP
[14] Price, W.H. (1991). Factors influences concrete strength. J.Am. Concrete Institute.
[15] Zain, M.F.M.,Safiuddin.M., & Yusof, K.M. (2000). Influenece of different curing conditions on the
strength and durability of high performance concrete. In the proceedings of the Fourt ACI International
Conference on Repair, Rehabilitation and maintenance, ACI SP-193, American Concrete Institute.
[16] Goel, A., Narwal, J., Verma, V., Sharma, D., & Singh, B. (2013). A Comparative study on the effect of
curing on the strength of concrete. International Journal of Engineering and Advanced Technology,
[17] Soyingbe, A.A., & Emenike, A.J. (2013). Effects of curing Methods on Density and Compressive Strength
of Concrete. International Journal of Applied Science and Technology, Vol 3, No 4. Building Department,
[18] Zhang, X.B., Kuang, C.G., & Fang, Z. (2011). The effect of water-cement ratio and curing age on the
Workability of Concrete and Lateritic Concrete Mixes. The Pacific Journal of Science and Technology,
[20] Jani, J.M., Leary, M., Subic, A., & Gibson, M.A. (2013). A review of shape memory alloy research,