Professional Documents
Culture Documents
Introduction
Currently, untreated sewage regularly overflows into the River Thames from Londons Victorian sewerage system via combined sewer overflows (CSOs). The proposed Thames Tunnel would intercept these overflows through the use of a new storage and transfer tunnel, which would link west London and Abbey Mills Pumping Station. The sewage flow would then be transferred to Beckton Sewage Treatment Works via the Lee Tunnel. The reduction in untreated sewage entering the River Thames would bring long-term benefits for the environment and users of the River Thames. In order to deliver the project we need a number of sites along the route and this document identifies our current preferred site at King Edward Memorial Park Foreshore.
Key facts
Local authority: CSO name: CSO spill volume in an average year: Site type: Duration of main construction works: Tower Hamlets North East Storm Relief 780,000m (equivalent to approximately 312 Olympic swimming pools) CSO site Approximately three and a half years.
Thames Tunnel
1
Introduction
treet Cable S
North East Storm Relief CSO
Proposed tunnel route centreline Local authority boundary Existing sewer Existing CSO
y The Highwa
Glamis Road
Shadwell Basin
SOUTHWARK
N
Figure 1A: King Edward Memorial Park Foreshore location plan
Introduction
Preferred site King Edward Memorial Park Foreshore Other shortlisted site locations Local authority boundary
Site 4 Site 2
Site 1 Site 3
TOWER HAMLETS
SOUTHWARK
N
Figure 1B: Preferred and shortlisted sites
Related documents:
Q&A
Introduction
Preferred site King Edward Memorial Park Foreshore Site 2 Heckford Street Tunnel centre line (preferred site) Tunnel centre line (site 2) Local authority boundary Existing sewer Existing CSO
SOUTHWARK
Controlled (day time) crossing open unless road required by construction activities N
Figure 1C: Connecting North East Storm Relief CSO to the main tunnel
Construction
Construction
Drop shaft
Site setup
Figure reference
Typical working hours Utilities connected Utilities diverted or protected
Varies
Figure 2C
Standard
Pre-construction landscape works carried out Site cleared Temporary works in River Thames constructed Site facilities and access set up Drop shaft excavated and built Above and below ground structures constructed Mechanical and electrical equipment installed Temporary works in the River Thames removed Site restored and landscaped Temporary site facilities removed
Our typical working hours are expected to be: Standard: 8am-6pm weekdays, 8am-1pm Saturday* Extended standard: 6pm-10pm weekdays, 1pm-5pm Saturdays Continuous: 24 hours a day, seven days a week** Varies: Working hours for advanced works will depend on the nature of the works and will be agreed with the local authority
10
Construction
* Standard working hours would also include, subject to agreement with the local authority: a short period (up to one hour) before works start and after they have finished to allow our workers to prepare for work and check the site. equipment and machinery maintenance could also take place 1pm-5pm Saturday and 10am-4pm Sunday. ** The main activities taking place 24 hours a day are below ground or within an enclosure.
11
P1 P2
P3 P4
Figure 2B: Construction timeline showing approximate duration of works in phases (P)
12
Construction
Local authority boundary Site support/welfare Internal site road Site access Existing Thames Path Thames Path diversion Jack up barge servicing piling operations Barge TOWER HAMLETS SOUTHWARK
N
Figure 2C: Illustrative phase 1 construction plan
13
Piling rig
Local authority boundary Site support/welfare Excavated material storage and processing Maintenance workshop and storage Construction support Internal site road
Crane
Barge
Drop shaft
TOWER HAMLETS
SOUTHWARK N
14
Construction
Local authority boundary Site support/welfare Excavated material storage and processing Construction support Internal site road Site access
Cranes
TOWER HAMLETS
SOUTHWARK N
15
When
Type of works
Installation of equipment to monitor environmental matters such as noise, vibration and dust. Protection works to third party structures (such as buildings, bridges and tunnels).
What we would do
The locations of monitoring equipment would be agreed with the local authority and relevant landowners. We would undertake studies to identify any effects our construction work may have on third party structures. The studies may recommend particular construction methods or, in very limited instances, protection works. If protection works are required to the existing sewer, we would access the sewer network through existing manholes. If utility diversions are required, we would work with utility providers to undertake the necessary works. We expect to connect to water, sewer and phone supplies in Glamis Road or The Highway (A1203). We may need to connect to a power supply in Welclose Square, running cables long Cable Street and Glamis Road. However, we are still developing a route for electricity supply in discussion with the utility provider.
Diversion of utilities.
16
Construction
When
Type of works
Traffic management works.
What we would do
These may need to extend beyond our site and could include relocating kerb lines, repainting road lines and modifying traffic signals. There is a possibility that as the detailed design is developed we may need to undertake dredging to allow barges to get to and from our site. We may need to carry out works to strengthen the river bed to avoid scour.
We would reconfigure and relocate the multi-purpose sports area, childrens playground and memorial benches within the park. The Landscaping works memorial benches would be moved to a new permanent location as completed in advance of the shown in Figure 3D. We would dismantle the bandstand and store it main construction works. so that it can be re-erected at the end of construction works. Paving and landscaping works to the seating area next to the Rotherhithe Tunnel ventilation shaft would also be undertaken. Permanent connection to utilities (such as water, phone and electricity supply) for the operational tunnel. Landscaping works. We expect to connect to utilities in Glamis Road or The Highway (A1203). The multi-purpose sports area would be reinstated in its existing location. We would relocate the childrens playground to a new permanent location within the park, as shown in Figure 3E.
17
13 lorries 2 barges
Table 2.3: Average daily lorry and barge visits during the peak months
18
Construction
The Highway
Rotherhithe Tunnel
TOWER HAMLETS
SOUTHWARK
Glamis Road
Figure 2F: Proposed access route to the site from the nearest major road
Draft limit of land to be acquired or used Internal site road Site access
Local authority boundary Transport for London (TfL) road network Proposed lorry access to TfL road network
19
Issue
Permanent relocation of the childrens playground, currently located in the south western corner of the park. Temporary loss of part of the multi-purpose sports area and some tennis courts, located in the south western corner of the park. Potential loss of and damage to trees within the park.
Our response
Prior to the main construction phase, the playground would be relocated within the park. We would work with park users and the London Borough of Tower Hamlets to agree the relocation and design of the playground.
During construction, some of the tennis courts would be used to provide a temporary replacement multi-purpose sports area. The multi-purpose sports area would be reinstated in its existing location and in an improved condition following completion of construction. We have sought to minimise tree loss and damage where possible, and will propose careful root protection, pollarding and trimming methods. Proposals for permanent site landscaping incorporate the planting of more trees than the number expected to be lost during construction. Where possible it is intended that landscaping would be undertaken in advance of the main construction works commencing.
20
Construction
Issue
Temporary diversion of the Thames Path, restricted access to the riverfront and possible loss of river views.
Our response
Access to the Thames Path next to the River Thames beside the Rotherhithe Tunnel ventilation shaft would be maintained throughout construction. Gated access across the internal site road would allow access from the ventilation shaft to the rest of the park when it is not being used by construction vehicles. Views over the River Thames would be temporarily affected during construction. However, access will be maintained to the river front from parts of the park including the new seating area beside the Rotherhithe Tunnel ventilation shaft. Since phase one consultation, site access has been relocated to the south west side of the park, off Glamis Road to reduce the effects of construction traffic on the major road network and provide safer site access. We would manage the effects of road transport through our traffic management plans, which will seek to limit the number of vehicle movements and hours of operation, identify the most suitable site access points and any necessary highway management arrangements. As already set out, we also propose to use barges to bring in and take away the majority of material used to fill the cofferdam, which would significantly reduce the number of lorry movements from this site over the construction period. The extent and duration of the suspension of any coach bays during construction would be minimised as far as possible. We are investigating options for temporary replacement parking provision during construction where necessary. Since phase one consultation, we have reduced the area of temporary cofferdam foreshore extension by relocating those construction activities that do not need to be located immediately adjacent to the main tunnel site to the areas of hardstanding on the western side of the park, near Glamis Road. We have undertaken modelling to test the effect that the structure has on the flow of the river. The modelling has shown the proposed structure to be satisfactory and the Port of London Authority and other key stakeholders are satisfied the permanent works have a minimum effect on river navigation. A full navigational risk assessment will be undertaken for the temporary and permanent works. Existing moorings may have to be temporarily relocated.
Possible effect of construction vehicles on the capacity and operation of the local road network.
Temporary suspension or relocation of some coach parking bays on Glamis Road. Possible effect of foreshore construction activities on river navigation and river users of the River Thames, including the Shadwell Basin Outdoor Activity Centre.
21
Our response
Since phase one consultation, we have relocated the construction site access point to Glamis Road on the west of the site, to reduce effects on the nearest residential properties. The contractor would also be required to implement noise and vibration control measures at the worksite, which will be set out in the CoCP. Preliminary findings indicate that while there is the potential for dust nuisance effects, there are unlikely to be any significant local air quality effects at any of the sites. The contractor would put in place air and dust control measures at the worksite, which will be set out in the CoCP. Since phase one consultation, we have reduced the area of temporary cofferdam foreshore extension to reduce potential effects on ecology. Ecological surveys are also being undertaken to identify possible effects arising from construction activities. The contractor would put in place various control measures at the worksite to minimise these effects as far as possible. These will be set out in the CoCP.
22
Future use
Design
Since phase one consultation we have progressed the design for the permanent use and appearance of the structures at King Edward Memorial Park Foreshore. The design of the permanent proposals follows our schemewide principles and takes into account comments made and ongoing engagement with the London Borough of Tower Hamlets and other technical consultees.
Future use
23
Our response
Careful siting of foreshore extension and permanent works to avoid infringing into the protected zone of the Rotherhithe Tunnel.
Careful siting of foreshore extension and permanent works to ensure that the two further CSOs not being intercepted remain operational either side of the new structure. Avoiding interference with these CSOs ensures that they do not need to be incorporated into the works and therefore the size of construction site required is minimised.
The proposed above ground structures have been reduced in size since phase one consultation, as a result of the modified scheme-wide ventilation strategy. In addition the proposed electrical and control kiosk has been relocated to the eastern perimeter of the park. Removing this structure from the foreshore extension makes it less visible and avoids interrupting views of the River Thames. A number of architectural design developments have taken place to ensure that the architectural design of the above ground structures and the foreshore extension is sympathetic to the park. The new foreshore structure would extend the area of the park as it will be designed to blend with the existing green space.
Effect on the setting of the Grade II listed Rotherhithe Tunnel ventilation shaft and character of the Wapping Wall Conservation Area.
The majority of the proposed permanent works on this site would be below or at ground level to avoid any significant effect on the setting of the listed buildings or character of the Conservation Area. Landscaping for the extended and reinstated areas of the park would be designed in consultation with the relevant stakeholders to ensure that the character of the Conservation Area is preserved and enhanced.
24
Future use
Issue
Our response
We have reduced the size of the foreshore area required for permanent works since phase one consultation by moving the shaft closer to the river wall and re-profiling the foreshore extension to minimise effects on river flows.
Preliminary modelling has indicated that the proposed design is acceptable in terms of river flow. The proposals have been discussed with the Port of London Authority and other key stakeholders to develop a layout that has a minimal effect on river navigation. Our proposals for the permanent layout and design of the site have sought to reduce the extent of the permanent works within the foreshore to minimise effects on water ecology as far as possible.
Loss of foreshore habitat and effects on ecology within the River Thames.
Ecological surveys of the River Thames and its foreshore are being undertaken to identify possible effects, and design measures will be incorporated where required. Construction of the tunnel would also deliver river wide improvements to local water quality, which would result in positive effects on river ecology, including habitat improvements and reduced fish kills. The permanent arrangement for the access route to our site from Glamis Road would provide an opportunity to use this as an enhanced Thames Path route for pedestrians and cyclists. The current Thames Path off Glamis Road is via a narrow and enclosed footway which could be widened and include potential landscaping improvements. The design of this route would be informed by the assessments of the current use and quality of the park along with ongoing consultation with the key stakeholders including the local authority.
Table 3.1: Site specific issues that have influenced our permanent design
25
26
Future use
Figure 3B: Artists impression of the site after the works are completed
27
The Highway
Glamis Road
Controlled (daytime) crossing of construction access route open unless required by construction activities
N Thames Path remains open during construction Minor reconfiguration of tennis courts Relocated childrens play area Paving and landscaping improvements to area around Rotherhithe Tunnel ventilation shaft Advanced tree planting to improve Memorial Avenue
28
Future use
Memorial Park benches relocated on line with Memorial Electrical and control kiosk against existing brick wall
Relocated bandstand
The Highway
Glamis Road
Bowling green Football pitch Tennis courts New North East Storm Relief CSO outlet
Thames Path widened and improved. Provides maintenance access to shaft N Bike stands New gated entrance to park and Thames path Activity/ fitness zone Seating area Ventilation columns Grassed area around relocated bandstand
29
30
Future use
Issue
Our response
Odour effects at this site are expected to be negligible because we have developed an Air management plan to minimise possible odour and air quality effects arising from the operation of the tunnel. The technology we are proposing to use at this site includes the use of passive below ground carbon filters that will remove possible odour before air leaves the ventilation equipment. Permanent access would be required for maintenance and servicing purposes to the shaft and ventilation equipment. Any planned maintenance visits would be undertaken during normal working hours and all visits managed to avoid disruption to local residents, businesses and users of affected public areas as far as possible.
31
Further information
This section sets out documents which may be of particular interest. Further information on our proposals can be found on our website (www.thamestunnelconsultation.co.uk) or is available upon request (call our customer centre on 0800 0721 086).
Q&A
Consultation
Design
Environment
Managing construction
Odour
Sets out our Air management plan and how it will work.
Options
32
Sets out the preferred route of the main tunnel and the reasons for our preference.
Sets out the process we followed to find and select our preferred sites. Contains information on the different transport options we have considered for delivering and removing materials from our sites.
Transport
33
Further information
Technical reports
Theme Interim engagement Phase one consultation Icon Title Interim engagement report Report on phase one consultation: summary report Details Provides a summary of the public engagement we have undertaken between phase one and phase two consultations. Provides a summary of the comments made at phase one consultation and our responses.
SUMMARY
Code of construction practice Part A: Sets out control measures to be adopted during the project General requirements construction period. (CoCP) Air management plan Outlines the methods which we will use to manage odour from the main tunnel at all our preferred sites. Contains initial assessments on the environmental effects of the Thames Tunnel project based on information collected to date. Please refer to volume 23 of the non-technical summary and volume 23 of the PEIR for more information on this site. Provides a general overview of how the scheme design at each site has evolved to date. Please refer to chapter 20 for more information on this site. Provides an overview of the development of the Thames Tunnel project and how each site was chosen. Please refer to Appendix S for more information on this site.
34
Site glossary
Term
Carbon filters Cofferdam Combined sewer Combined sewer overflow (CSO) Connection tunnel Conservation area Draft limit of land to be acquired or used Drop shaft Foreshore Interception chamber Main tunnel Operational phase Scour Thames Tunnel project Transport for London Road Network (TLRN)
Definition
Filters that remove odours before the air is released from the tunnel. A wall that is constructed within the river around the outside of the working area and then pumped dry. The inside of the cofferdam can then be filled to create a safe working area. A single sewer system that takes both rainwater and domestic and industrial wastewater. A structure, or series of structures, that allows sewers to overflow into the river when they are full as a result of increased rainfall. Without the overflow, the sewer would back up and cause flooding in streets or houses. A tunnel connecting a drop shaft to the main tunnel. An area designated by the local authority or English Heritage as having special architectural or historical interest. The extent of land that we may need to use or acquire, or over which rights may be needed to carry out works that are essential to the project. A vertical circular concrete structure, used to drop flows from the high level of the CSO to the low level of the main tunnel. It would also be used to provide access to construct the connection tunnels. Ground uncovered by the river when the tide is low. A structure, built on an existing combined sewer, which diverts stormwater overflow into the main tunnel. The tunnel from Acton Storm Tanks to Abbey Mills Pumping Station. After the completion of the construction work when the main tunnel is in use. Movement of the riverbed materials due to the force of the water. The Thames Tunnel project comprises a storage and transfer tunnel, from west London to Beckton Sewage Treatment Works in east London, and the control of 34 CSOs along the Thames Tideway. The network of roads managed by Transport for London. These are the major or strategic roads, which have high capacity.
35
Phase two consultation: King Edward Memorial Park Foreshore Autumn 2011 110-ED-PNC-00000-000086
For further information or to comment on our proposals see our website: www.thamestunnelconsultation.co.uk
It is very important that you understand the information we have provided. If you need further information in another language, braille, large print or audio format please contact us on 0800 0721 086.