III. COMPUTATIONS:
A. Velocity:
V d 0.021 m
¿= = =0.0029m / s¿
t 7.28 s
d 0.021 m
V middle = = =0.0026 m/s
t 8.14 s
d 0.021 m
V ¿= = =0.0022 m/s
t 9.62 s
B. Discharge:
C. Roughness Coefficient:
1 2/ 3 1 /2
Q= R S
n
Left Bank:
−5 3 1 2/ 3 1/ 2
3.712 x 10 m /s= (0.02) (tan 0.001)
n
n= 8.2925
Middle Section:
−5 3 1 2 /3 1 /2
3.328 x 10 m / s= (0.02) (tan 0.001)
n
n= 9.2493
Left Bank:
−5 3 1 2 /3 1 /2
2.816 x 10 m / s= (0.02) (tan 0.001)
n
n= 10.9310
IV. DOCUMENTATION:
Measuring the Width of the Channel Getting the Depth of the Channel
Letting the float traverse the Letting the float traverse the
Left bank section of the channel right bank section of the channel
Letting the float traverse the
middle section of the channel