Professional Documents
Culture Documents
MBA-III Project Management-PART-2
MBA-III Project Management-PART-2
Project Management
NOTES
YOUR M.B.A EXAM
PREPARATION BECOMES VERY EASY
IN OUR EXPERT GUIDANCE
https://rajnishsharmaclasses.classx.co.in/
Project Management
UNIT-3
Financial feasibility
Determinants of cost of project
Its nancing and deciding optimum capital structure
Cash ows from project and owner’s prospective
Project appraisal
UNIT-4Types of Risk
Techniques of risk evaluation and its mitigation
Sensitivity analysis, Hiller’s model
Scenario analysis
Project Management Numerical Questions
Performance Analysis
Q-1. A Project begin on 1st Jan., 2000 and was expected to be completed by 30th Sept., 2000 The project is
being reviewed on 30th June, 2000 and following information has been developed.
(i) Budgeted Cost for Work Scheduled (BCWS) Rs. 15,00,000
(ii) Budgeted Cost for Work Performed (BCWP) Rs. 14,00,000
(iii) Actual Cost for Work Performed (ACWP) Rs. 16,00,000
(iv) Budgeted Cost for Total Work (BCTW) Rs. 25,00,000
(v) Addition Cost for Completion (ACC) Rs 12,00,000
Determine the following:
(a) Cost Variance
(b) Schedule Variance in Cost Terms
(c) Cost Performance Index.
LIVE CLASSES
UNSOLVED
PAPERS
NOTES
UNIVERSITY
ALERTS
Q-4. ABC Ltd. is planning to start a new project with a xed investment of Rs. 7 Crores. The expected sales
in various years is:
I Year II Year III Year IV Year V Year
Rs 7 crore Rs 8 crore Rs 9 crore Rs 8 crore Rs 7 crore
The raw material cost is expected to be 45% of sales. Working capital requirement is 30% of sales to be
acquired at the preceding year. Fixed Cost is Rs. 50 Lacs per year. Depreciation 25% on WDV and Tax rate
is 30%. The project will fetch net salvage value of Rs. 1.7 Crore after 5 years.
Determine project cash ows and NPV if = 10%
Capital Budgeting
Q-1. Project costs Rs. 10,00,000 and yields an annual cash inow of Rs. 2,00,000 for 8 years. Calculate its
pay-back period.
1 2 3
(Rs.) (Rs.) (Rs.)
Capital Cost 30,000 30,000 30,000
Sales (at standard prices) 50,000 40,000 45,000
Net Cost of Production :
Direct Material 4,000 5,000 4,800
Direct Labour 5,000 3,000 3,600
Factory Overheads 6,000 5,000 5,800
Administration Costs 2,000 1,000 1,500
Selling and Distribution Costs 1,000 1,000 1,000
For Search
M.B.A. Exam on
Preparation
The economic life of machine no. 1 is 2 year, while it is 3 years for the other two. The scrap values are Rs.
4,000 Rs. 2,500 and Rs. 3,000 respectively.
Tax to be paid is expected at 50% of the net earnings of each year. Interest on capital has to be paid at 8%
per annum.
You are req uested to show which machine would be the most protable investment on the principle of “pay-
back method.”
Taxation is
Machine „X Machine „Y
to be
Estimated life of machine (years) 5 6
regarded as
Cost of Machine Rs. 15,00,000 Rs. 25,00,000
50% of
Cost of Indirect materials (p.a.) 60,000 80,000
prot.
Estimated savings in scrap (p.a.) 1,00,000 1,50,000
Which
Additional cost of maintenance (p.a.) 1,90,000 2,70,000
model
Estimated savings in direct wages :
would you
Employees not required (number) 150 200
recommend
Wages per employee 6,000 6,000 ? State your
reasons.
Machine A Machine B
Original Cost Rs. 5,61,250 Rs. 5,61,250
Addl. Investment in net working capital 50,000 60,000
Estimated life in years 5 5
Estimated salvage value 30,000 30,000
Average income-tax rate 55% 55%
Annual estimated income after depr. And tax
1st year 33,750 1,13,750
2nd year 53,750 93,750
3rd year 73,750 73,750
4th year 93,750 53,750
5th year 1,13,750 33,750
3,68,750 3,68,750
MBA 3 rd
SEM.
All Practical In Just One STUDY
Subjects CLICK
ANY Time
Where
UNSOLVED
PAPERS
UNIVERSITY
ALERTS
WWW. rajnishsharmaclasses.classx.co.in
M.B.A. 2015 Q.9
For Solution See Video Lecture 12
(Capital Budgeting) on the App
Q-12. Compare the two mutually exclusive projects using (a) PBP (b) ARR (c) NPV (d) IRR. Which project
should be selected and why? Assume = 10%:
Project A Project B
Fixed Investment Rs 3,00,000 Rs 2,00,000
Working Capital Rs 50,000 Rs 80,000
Project Life 15 Years 12 Years
CF/ Year Rs 80,000 Rs 60,000
Salvage Value Rs 40,000 Rs 30,000
(b) Also compare two projects by IRR method (assuming IRR-of 19%. 25%, 21%, 26%, 27% and 28%).
M.B.A. Exam on
Preparation
Q-3. There are two projects X and Y. Each involves an investment of Rs 40,000. The expected cash inows
and the certainly coefcients are as under:
Project X Project Y
Year Cash Inow Certainly Coefcient Cash Inow Certainly Coefcient
1 25000 0.8 20000 0.9
2 20000 0.7 30000 0.8
3 20000 0.9 20000 0.7
Risk-free cut off rate is 10% Suggest which of the two projects should be preferred.
WWW. rajnishsharmaclasses.classx.co.in
TARGET YOUR
UNIVERSITY EXAMS
Q-5. A company used Risk Adjusted Discount Rate Method. Certain CFAT and Certainty Equivalents for
two projects Project X and Project Y are given as follows :
Project X Project Y
Year Certain CFAT Certainly Equivalent Certain CFAT Certainly Equivalent
0 (40,00,000) 1.00 (45,00,000) 1.00
1 14,25,000 0.95 22,50,000 0.90
2 15,30,000 0.85 16,00,000 0.80
3 14,00,000 0.70 17,50,000 0.70
4 13,00,000 0.65 10,80,000 0.60
Which project should be accepted if risk free rate of return of company is 9%, cost of capital is 13% and risk
adjusted discount rate (for Project X and Project Y) is 16% ?
LIVE CLASSES
UNSOLVED
PAPERS
NOTES
UNIVERSITY
ALERTS
Q-8. A project involving an initial outlay of Rs 10,000 has the fo llowing benets associated with it:
Year 1 Year 2 Year 3
Net Cash Probability Net Cash Probability Net Cash Probability
Flow Rs. Flow Rs. Flow Rs.
3,000 0.3 2,000 0.2 3,000 0.3
5,000 0.4 4,000 0.6 5,000 0.4
7,000 0.3 6,000 0.2 7,000 0.3
Calculate: (a) Expected Net Present Value and (b ) Standard Deviation of net present value, assuming that i=
6 per cent.
M.B.A. Exam on
Preparation
Q-11. ABC Ltd. is considering a project with following cash ows:
Year Purchase of Plant (Rs) Running Cost (Rs) Saving (Rs)
0 (7,000) - -
1 - 2,000 6,000
2 - 2,500 7,000
The cost of capital is 8%
Measure the sensitivity of the project to changes in the levels of Plant value, costs, and savings (Considering
each factor at a time) such that the net present value becomes zero. What factor is most sensitive to affect the
acceptability of the project. The present value factor at 8% are: 0.93 (at year-end 1) and 0.86 (at year-end 2)
MBA 3 rd
SEM.
All Practical In Just One STUDY
Subjects CLICK
ANY Time
Where