You are on page 1of 1

GENERAL NOTES & SPECIFICATIONS

1. ALL MECHANICAL WORKS SHALL BE INSTALLED IN ACCORDANCE WITH THE LATEST


REQUIREMENT OF THE PHILIPPINE NATIONAL BUILDING CODE AND LOCAL
REGULATIONS.
LEGEND :
2. THE TOTAL SCOPE OF WORK SHALL INCLUDE ALL WORKS DESCRIBED IN THE PLANS
AND IN THE GENERAL PROVISIONS OF THE TECHNICAL SPEC. FOR MECHANICAL WORKS.
ACU 1 - WINDOW TYPE AIR CONDITIONING
3. ALL WORKS SHALL BE EXECUTED IN CLOSE COORDINATION WITH THE WORKS OF
OTHER TRADES. COORDINATED WITH THE ARCHITECT AND ELECTRICAL THE EXACT - FIRE EXTINGUISHER
LOCATION OF FANS, PIPES AND A/C EQUIPMENT.
4. CONTRACTOR/SUPPLIERS SHALL INSTALL ALL EQUIPMENT IN ACCORDANCE WITH THE - WALL MOUNTED EXHAUST FAN
MANUFACTURER'S RECOMMENDATION. EF 2 - CEILING MOUNTED EXHAUST FAN
5. ALL FLOORS SLAB MOUNTED VIBRATING EQUIPMENT SHALL BE PROVIDED WITH
VIBRATION INSULATORS TO PREVENT VIBRATION AND NOISE TRANSMISSION.
6. PIPE ALL EQUIPMENT CONDENSATE DRAIN LINE TO THE NEAREST FLOOR/CATCH

CLEAN-OUT.
7. PROVIDE 20mm THK. ELASTOMERIC RUBBER INSULATION TO ALL REFRIGERANT
SUCTION LINES WITH WHITE FILM TAPE AS FINISH.
8. FIRE EXTINGUISHER SHALL BE INSTALL WITH CABINET AND 1.50 METERS HIGH BOTTOM
TO FINISH FLOOR LEVEL.

SECOND FLOOR SCHEDULE OF A/C SYSTEM

SPLIT AIR CONDITIONER


ELECTRICAL
TAG NO. DESCRIPTION MAKE / MODEL QTY CAPACITY
VOLTS �� Hz
ACU - 1 WINDOW TYPE AIR CONDITIONING CARRIER OPTIMA 1.0 3 1.0 HP 220 - 240 1 60

GROUND FLOOR SCHEDULE OF A/C SYSTEM


ACU - 2 PORTABLE AIR CONDITIONING WITH AIR PURIFYING FILTER PAC-100AIG 2 1.0 HP 230 1 60